Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
uae-difc-cases

FIVE REAL ESTATE DEVELOPMENT v REEM EMIRATES ALUMINIUM [2021] DIFC TCD 009 — Dismissal of application for permission to appeal (22 August 2021)

The litigation arises from a construction dispute where the parties were subject to an Engineer’s Determination regarding payment obligations. The Claimant, Five Real Estate Development, sought to strike out the Defendant’s counterclaim, arguing that the Defendant was bound by the figures set out…

300 wpm
0%
Chunk
Theme
Font

This order addresses the finality of judicial recitations in construction litigation, confirming that a court’s summary of a pleaded claim does not function as a binding judicial determination that limits the scope of that claim for the purposes of res judicata.

What was the core dispute between Five Real Estate Development and Reem Emirates Aluminium regarding the Engineer’s Determination?

The litigation centers on a construction dispute involving Five Real Estate Development (the Claimant) and Reem Emirates Aluminium (the Defendant). The conflict arose from an Engineer’s Determination concerning payment entitlements under their contract. The Claimant sought to strike out the Defendant’s Counterclaim, arguing that the Defendant was bound by the figures set out in the Engineer’s Determination and could not seek a higher amount. Specifically, the Claimant contended that the Defendant had already accepted the Determination’s validity to secure a previous order and was now barred from challenging its underlying components to inflate its claim.

The Claimant’s position was rooted in the mathematical discrepancy between the amount the Engineer determined was due (AED 1,811,884.48) and the amount the Defendant sought in its Counterclaim (AED 17,200,000). The Claimant argued that the Defendant’s attempt to challenge the Engineer’s deductions was an impermissible departure from the established contract administration process. As noted in the court records:

Given the other determinations made by the Engineer it followed, submitted Mr Kumar, that AED 1,811,884.48 remained due as per the Determination to the Defendant, and not AED 17,200,000 as claimed by the Defendant.

The deep editorial analysis of this case is at: Five Real Estate Development v Reem Emirates Aluminium [2023] DIFC TCD 009: The High Cost of Procedural Overreach in Construction Disputes

Which judge presided over the application for permission to appeal in TCD 009/2020?

The application for permission to appeal the Second Order was heard and determined by Justice Sir Richard Field in the Technology and Construction Division of the DIFC Courts. The order was issued on 22 August 2021.

Mr Raj Kumar, representing the Claimant, argued that the Defendant’s Counterclaim was barred by the doctrines of res judicata and merger. He contended that the Court’s "First Order" had effectively crystallized the Defendant’s claim at AED 1,811,884.48, and that the Defendant could not subsequently seek to re-litigate the Engineer’s Determination to increase that sum. The Claimant asserted that the Defendant had "taken the benefit" of the First Order and was therefore precluded from challenging the Determination’s correctness.

The Claimant also submits that it is has an unassailable case that, in making the First Order, the Court found that Defendant had a Counterclaim for AED 1,811,884.48 and that by reason of the doctrines of res judicata and merger, the Counterclaim has been determined and cannot be re-litigated.

Furthermore, the Claimant argued that the Defendant’s conduct worked an injustice, suggesting that the Defendant had effectively elected to treat the Determination as binding when it suited their interests in the earlier proceedings.

Did the Court’s recitation of the Counterclaim in the First Order constitute a binding judicial finding on the amount claimed?

The primary legal question was whether the Court’s mention of the AED 1,811,884.48 figure in the reasons for the First Order functioned as a judicial determination that limited the scope of the Defendant’s Counterclaim. The Claimant argued that this recitation was a finding of fact that triggered res judicata. The Court had to determine if a judge’s summary of a party’s pleading in a previous order creates a binding limit on that party’s ability to pursue a claim for a different amount, or if it is merely a descriptive reference to the pleadings as they stood at that time.

How did Justice Sir Richard Field apply the test for permission to appeal under RDC 44.19(a)?

Justice Sir Richard Field evaluated the application based on whether the proposed appeal had a "real prospect of success." He emphasized that the reasons for the Second Order must be viewed in the context of the procedural posture—specifically, that the Court was dealing with a strike-out application rather than a final determination of a preliminary issue. He reasoned that the Defendant had a reasonably arguable case to challenge specific deductions made by the Engineer, even if the Claimant contended the Determination was binding.

The judge clarified that the Court’s earlier reference to the AED 1,811,884.48 figure was merely a recitation of the pleadings, not a substantive ruling on the merits of the Counterclaim’s value.

The reasons given for the Second Order have to be understood against the background of the parties’ submissions addressed to the Court on the Claimant’s application to strike out the Counterclaim.

The Court concluded that the Claimant’s arguments regarding res judicata were "hopeless" and that the First Order did not preclude the Defendant from arguing that certain parts of the Engineer’s Determination were incorrect.

Which specific RDC rules and legislative frameworks were central to the Court’s reasoning?

The application was governed by RDC 44.19(a), which sets the threshold for granting permission to appeal. Additionally, the Court referenced the DIFC Arbitration Law in the context of the Claimant’s procedural arguments. The Claimant’s reliance on the doctrine of election and res judicata was addressed through the lens of common law principles, as the Court examined whether the Defendant had irrevocably committed to a specific interpretation of the Engineer’s Determination.

How did the Court address the Claimant’s reliance on the doctrine of election?

The Claimant argued that the Defendant had elected to accept the Determination as binding by relying on it in previous stages of the litigation. The Court rejected this, noting that the Claimant failed to reference leading authorities on the doctrine of election. Justice Sir Richard Field found that the Defendant’s position—that it accepted the numbers as stated in the pleadings but disputed their correctness—was a valid procedural stance.

Mr Kumar further submitted that it appeared odd, in that it works an injustice against the Claimant, for the Defendant to be allowed to challenge the Determination to pursue its Counterclaim having taken the benefit of the First Order.

The Court held that the Defendant was not barred from challenging the Engineer’s deductions simply because it had previously acknowledged the existence of the Determination.

What was the final disposition of the application and the order regarding costs?

The Court dismissed the Claimant’s application for permission to appeal, finding that the proposed appeal lacked a real prospect of success. Consequently, the Claimant was ordered to bear the costs of the application.

The Claimant shall pay the Defendant’s costs of this application to be assessed by the Registrar on the standard basis, if not agreed.

The Court maintained the Second Order, allowing the Defendant to proceed with its Counterclaim.

What does this case mean for practitioners regarding the finality of court recitations?

This decision serves as a warning against over-interpreting judicial summaries of pleadings. Practitioners should be aware that a court’s recitation of a claim in an order—even when referencing specific monetary figures—does not necessarily constitute a binding judicial finding that limits the scope of that claim for future proceedings. The case reinforces that strike-out applications are a high bar; unless a claim is truly unsustainable, the Court will preserve the right of a party to challenge the underlying components of an Engineer’s Determination, provided there is a reasonably arguable case.

Sibling orders in the same case family:
- FIVE REAL ESTATE DEVELOPMENT v REEM EMIRATES ALUMINIUM [2021] DIFC TCD 009 — Leave to file counterclaim (02 February 2021)
- FIVE REAL ESTATE DEVELOPMENT v REEM EMIRATES ALUMINIUM [2021] DIFC TCD 009 — Immediate judgment on FIDIC-based claims (04 May 2021)
- FIVE REAL ESTATE DEVELOPMENT v REEM EMIRATES ALUMINIUM [2021] DIFC TCD 009 — Dismissal of strike-out application regarding FIDIC determination (31 May 2021)
- FIVE REAL ESTATE DEVELOPMENT v REEM EMIRATES ALUMINIUM [2021] DIFC TCD 009 — Dismissal of appeal against strike out and amendment nullification (08 June 2021)
- FIVE REAL ESTATE DEVELOPMENT v REEM EMIRATES ALUMINIUM [2021] DIFC TCD 009 — Default Costs Certificate (28 July 2021)

Where can I read the full judgment in Five Real Estate Development v Reem Emirates Aluminium [2021] DIFC TCD 009?

Full Judgment Source | CDN PDF Copy

Cases referred to in this judgment:

Case Citation How used
N/A N/A N/A

Legislation referenced:

  • Arbitration Law
  • RDC 44.19 (a)
Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.