Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
uae-difc-cases

FIVE REAL ESTATE DEVELOPMENT v REEM EMIRATES ALUMINIUM [2021] DIFC TCD 009 — Immediate judgment on FIDIC-based claims (04 May 2021)

The DIFC Court of First Instance clarifies the limits of challenging an Engineer’s Determination under a FIDIC 1999 contract, granting immediate judgment where the claimant’s arguments contradict the underlying certified figures.

300 wpm
0%
Chunk
Theme
Font

This order addresses the court's power to grant immediate judgment when a claimant’s construction dispute is mathematically inconsistent with a binding Engineer’s Determination under a FIDIC contract.

What was the nature of the dispute between Five Real Estate Development and Reem Emirates Aluminium regarding the AED 7,744,388.00 claim?

The dispute arose from a sub-contract agreement dated 29 May 2018 for aluminum and glazing works at the Five Palm Jumeirah project. The Claimant, Five Real Estate Development, sought to recover AED 7,744,388.00 from the Defendant, Reem Emirates Aluminium, alleging that the Defendant failed to comply with an Engineer’s Determination issued on 4 March 2020. The Claimant argued that this sum represented descoping, cost savings, liquidated damages, and contra charges that the Defendant was obligated to account for under the FIDIC 1999 contract framework.

The core of the disagreement centered on the interpretation of the Engineer’s Determination. The Claimant contended that the Defendant was in breach of Clause 3.5 of the FIDIC conditions for failing to give effect to the findings within that document. As noted in the court records:

On 27 October 2020, the Claimant issued its Claim Form claiming AED 7,744,388.00 “compromising the descoping/cost savings, liquidated damages and contra charges” and averring that the Defendant was in breach of Clause 3.5 of FIDIC for failing “to give effect to the Determination”.

The Defendant countered that the claim was fundamentally flawed because the Engineer’s Determination had already accounted for the relevant financial adjustments, ultimately concluding that the Defendant was entitled to a total payment of AED 41,334,961.90. The Defendant argued that the Claimant’s attempt to relitigate these items was an attempt to bypass the finality of the Engineer’s assessment. Further details on the procedural history of this dispute can be found in the sibling order: FIVE REAL ESTATE DEVELOPMENT v REEM EMIRATES ALUMINIUM [2021] DIFC TCD 009 — Dismissal of strike-out application regarding FIDIC determination (31 May 2021).

Which judge presided over the TCD 009/2020 application for immediate judgment on 04 May 2021?

The application for immediate judgment was heard by Justice Sir Richard Field in the Technology and Construction Division (TCD) of the DIFC Courts. The order was issued on 04 May 2021, following the Defendant’s application dated 15 March 2021.

The Defendant, Reem Emirates Aluminium, argued that the Claimant’s case was entirely devoid of merit because the items forming the basis of the AED 7,744,388.00 claim had already been adjudicated by the Engineer. They relied on the witness statement of Athanasios Karvelis, which demonstrated that the Engineer’s Determination of 4 March 2020 had already factored in the contract value, variations, delay penalties, and contra charges. The Defendant asserted that the Claimant’s claim was a mischaracterization of the Engineer's final assessment, which actually showed that the Defendant was owed money, not the other way around.

Conversely, the Claimant attempted to pivot by filing an application on 25 April 2021 to amend its Particulars of Claim. This application sought to introduce new claims for indemnity regarding losses suffered by the project owner, Unlimited 1 Limited, and a separate claim for defects. The Claimant’s position was that these amendments would provide a new basis for the litigation. However, the Court found these proposed amendments insufficient to salvage the original claim, noting that they did not constitute a valid defense to the Defendant’s application for immediate judgment.

What was the precise doctrinal issue the court had to resolve regarding the Claimant’s prospect of success under RDC 24.1 (a)?

The Court had to determine whether the Claimant had any "real prospect of succeeding" on its claim, as required by the Rules of the DIFC Courts (RDC). The doctrinal issue was whether a party can maintain a claim for breach of contract based on an Engineer’s Determination when the underlying financial figures in that Determination explicitly contradict the Claimant’s calculation of the debt owed. The Court had to decide if the claim was so logically inconsistent with the contract documents that it warranted summary disposal without a full trial.

How did Justice Sir Richard Field apply the test for immediate judgment to the FIDIC-based claim?

Justice Sir Richard Field applied the test set out in RDC 24.1 (a), which permits the court to grant immediate judgment if a claim lacks a real prospect of success. The Judge reviewed the Engineer’s Determination of 4 March 2020 and compared it against the Claimant’s assertions. He found that the Engineer had clearly set out the financial position, including the "Revised Contract Value" and the specific deductions for delay penalties and contra charges.

The Judge concluded that the Claimant’s attempt to claim AED 7,744,388.00 was mathematically incompatible with the Engineer’s findings. He emphasized that the Engineer had already determined the sum due to the Defendant was AED 41,334,961.90. As the Judge noted:

It follows, and I so find, that the Claimant has no viable case based on the Determination on which it relies for its claim that the Defendant owes the Claimant the AED 7,744,388.70.

The Judge further reasoned that the Claimant’s reliance on Clause 3.5 of the FIDIC contract was misplaced because the Defendant had not failed to give effect to the Determination; rather, the Claimant was attempting to ignore the Determination’s actual outcome.

Which specific statutes and RDC rules were applied by the court in TCD 009/2020?

The Court primarily relied on the Rules of the DIFC Courts (RDC), specifically:
* RDC 4.16 (1): Regarding the Defendant’s application to strike out the claim.
* RDC 24 (1) (a) and RDC 24.1 (a): Regarding the power of the court to grant immediate judgment where there is no real prospect of success.

The substantive dispute was governed by the FIDIC 1999 Conditions of Contract for Construction, specifically Clause 3.5, which dictates the procedure for the Engineer’s determination of matters.

How did the court utilize the cited authorities to reach its decision?

The Court utilized the Engineer’s Determination as the primary evidentiary authority to interpret the contractual obligations of the parties. By citing the specific figures within the Determination—such as the "Revised Contract Value" of AED 41,334,961.90—the Court established that the Claimant’s claim was factually unsupported. The Court also referenced the witness statement of Athanasios Karvelis to confirm the financial calculations, effectively using the documentary evidence to demonstrate that the Claimant’s position was "misconceived and without foundation."

What was the final outcome of the application and the orders made regarding costs?

The Court granted the Defendant’s application for immediate judgment on the whole of the Claimant’s claim. Consequently, the claim was dismissed. Regarding costs, the Court ordered that the Claimant bear the financial burden of the proceedings:

The Claimant will pay the costs of the dismissed claim and the costs of the Defendant’s application herein such costs to be assessed by the Registrar on the standard basis unless otherwise agreed.

What are the wider implications of this judgment for construction practitioners in the DIFC?

This judgment serves as a stern warning regarding the necessity of aligning claims with the specific findings of an Engineer’s Determination under FIDIC contracts. Practitioners must ensure that any claim for breach of contract based on an Engineer’s decision is mathematically and logically consistent with the determination itself. The Court’s willingness to grant immediate judgment demonstrates that it will not allow parties to use the court process to relitigate issues that have already been settled by the contractually appointed Engineer.

For a deeper analysis of the procedural risks involved in such disputes, see: Five Real Estate Development v Reem Emirates Aluminium [2023] DIFC TCD 009: The High Cost of Procedural Overreach in Construction Disputes.

Where can I read the full judgment in Five Real Estate Development v Reem Emirates Aluminium [2021] DIFC TCD 009?

The full judgment can be accessed via the DIFC Courts website: https://www.difccourts.ae/rules-decisions/judgments-orders/technology-and-construction-division/tcd-009-2020-five-real-estate-development-llc-v-reem-emirates-aluminium-llc-1 or via the CDN link: https://littdb.sfo2.cdn.digitaloceanspaces.com/litt/AE/DIFC/judgments/technology-and-construction-division/DIFC_TCD-009-2020_20210504.txt.

Cases referred to in this judgment:
(None explicitly cited in the provided text, though the court applied standard RDC principles.)

Legislation referenced:
* RDC 4.16 (1)
* RDC 24 (1) (a)
* RDC 24.1 (a)
* FIDIC 1999 Conditions of Contract for Construction (Clause 3.5)

Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.