Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
uae-difc-cases

THE INDUSTRIAL GROUP v ABDELAZIM EL SHIKH EL FADIL HAMID [2018] DIFC CFI 029 — Default judgment set-aside and stay of execution (25 October 2018)

The dispute arose from a default judgment entered against the Defendant, Mr. Abdelazim El Shikh El Fadil Hamid, in the amount of AED 1,376,000. The Claimant, The Industrial Group Ltd, sought recovery of these funds, alleging that the payments made to the Defendant lacked proper justification or…

300 wpm
0%
Chunk
Theme
Font

This order clarifies the high threshold for setting aside a default judgment in the DIFC Courts, specifically distinguishing between a valid defence by way of set-off and an independent counter-claim.

What was the specific factual dispute in CFI 029/2018 regarding the AED 1,376,000 claim?

The dispute arose from a default judgment entered against the Defendant, Mr. Abdelazim El Shikh El Fadil Hamid, in the amount of AED 1,376,000. The Claimant, The Industrial Group Ltd, sought recovery of these funds, alleging that the payments made to the Defendant lacked proper justification or were improperly procured. The core of the conflict centered on whether the Defendant could challenge this judgment by asserting that he was owed money by the Claimant, thereby creating a set-off against the initial claim.

As noted in the court’s schedule of reasons:

That is the sum that is claimed in respect of monies paid to the Defendant when there was, in respect of those payments, insufficient and/or improper justification advanced in order to procure payment.

The Defendant attempted to introduce an expert report to substantiate his position, arguing that his own financial claims against the Claimant should negate the default judgment. The court had to determine if these assertions constituted a legitimate defence to the claim or merely a separate, unrelated counter-claim.

Which judge presided over the application to set aside the default judgment in CFI 029/2018?

The application was heard by Sir Justice Richard in the DIFC Court of First Instance. The hearing took place on 15 October 2018, with the formal Order with Reasons issued on 25 October 2018. The proceedings were conducted in the DIFC, following an application filed by the Defendant on 12 August 2018 to challenge the default judgment previously entered by Judicial Officer Nassir Al Nasser on 30 July 2018.

The Claimant, represented by Mr. Russell, Queen's Counsel, adopted a pragmatic stance. While opposing the setting aside of the default judgment, the Claimant acknowledged the existence of the Defendant's cross-claims. They proposed that the court maintain the judgment but grant a stay of execution, allowing the cross-claims to be litigated separately. This approach aimed to preserve the Claimant’s security while permitting the Defendant to pursue his claims in a consolidated proceeding.

Mr. Hamid, appearing as the Defendant, argued that he had a real prospect of successfully defending the claim. He relied on an expert report to substantiate his position. However, he initially failed to provide a signed witness statement attesting to his honest belief in the defence, an omission the court noted as problematic. He subsequently cured this by providing sworn oral evidence in the witness box, asserting that his defence was rooted in the claims identified within his expert report.

What was the doctrinal question the court had to answer regarding the distinction between a counter-claim and a defence by way of set-off?

The court was tasked with determining whether the Defendant’s cross-claims, as articulated in his expert report, met the legal threshold to constitute a "defence" under RDC Rule 14.2. The doctrinal issue was whether the cross-claim possessed a sufficiently "close relationship" to the Claimant's original claim to qualify as a set-off. If the cross-claim were merely an independent claim, it would not provide a basis to set aside a default judgment, as it would not negate the Claimant's right to the judgment sum.

How did Sir Justice Richard apply the test for a set-off to the facts of this case?

Sir Justice Richard applied the principle that for a cross-claim to function as a defence, it must amount to a set-off, which requires a nexus between the parties' respective claims. The judge found that the Defendant’s expert report failed to establish this necessary connection.

As articulated in the court's reasoning:

In my judgment, there is no such sufficient relationship between the claim made by the Claimant for payments, which have been received and improperly indented for and the claims which are identified in the expert's report.

The court concluded that because the cross-claims were not sufficiently linked to the Claimant’s demand for the return of improperly justified payments, they could not serve as a valid defence to the default judgment. Consequently, the application to set aside the judgment was dismissed, as the Defendant failed to demonstrate a real prospect of successfully defending the claim through the mechanism of a set-off.

Which specific RDC rules were applied by the court in evaluating the application to set aside the default judgment?

The court’s decision was primarily governed by the Rules of the DIFC Courts (RDC). Specifically, the application was brought under RDC Rule 14.2, which requires a defendant to show a "real prospect of successfully defending the claim" to set aside a default judgment. Additionally, the court referenced RDC Rule 14.4, which mandates that such an application must be supported by evidence. The court also noted that the original judgment was entered under RDC Rule 13.

How did the court address the procedural requirements for evidence under RDC Rule 14.4?

The court addressed the Defendant's failure to provide a signed witness statement as required by RDC Rule 14.4. The judge highlighted the procedural deficiency:

An expert's report has been tendered in evidence, which is relied on, but the Defendant had not put before the Court a signed witness statement attesting to his honest belief that he had a defence to the claim, nor was there a witness statement setting out the basis of such an honest belief.

Although the court noted this was an "unfortunate omission," it allowed the Defendant to cure the defect by providing sworn testimony in the witness box. This demonstrated the court's willingness to prioritize the substance of the argument over technical procedural failures, provided the evidentiary gap could be filled during the hearing.

What was the final disposition and the specific orders made regarding the judgment and costs?

The court dismissed the application to set aside the default judgment but granted a stay of execution. This allowed the Claimant to retain the judgment while preventing immediate enforcement, pending the trial of the Defendant’s cross-claims. Regarding costs, the court ordered the Defendant to pay the Claimant’s costs on the standard basis.

As stated in the order:

The Application is dismissed with a stay of execution on judgment pending trial of the Defendant’s cross-claims.

Regarding the costs, the court clarified:

I so order that the Applicant, the Defendant, Mr Hamid, must pay the costs on the standard basis if they are not agreed.

What are the wider implications for DIFC practitioners regarding the use of cross-claims to set aside default judgments?

This case serves as a warning to practitioners that a counter-claim is not an automatic shield against a default judgment. To successfully set aside a judgment, a defendant must demonstrate that their cross-claim qualifies as a set-off, which necessitates a "very close relationship" between the claims. Practitioners should ensure that any evidence submitted under RDC Rule 14.4 includes a clear, signed witness statement detailing the basis of the defendant's belief in their defence. The court’s decision to stay execution rather than set aside the judgment highlights a balanced approach, protecting the Claimant’s position while ensuring that the Defendant’s substantive cross-claims are not extinguished without a trial.

Where can I read the full judgment in The Industrial Group v Abdelazim El Shikh El Fadil Hamid [2018] DIFC CFI 029?

The full judgment can be accessed via the DIFC Courts website: https://www.difccourts.ae/rules-decisions/judgments-orders/court-first-instance/cfi-0292018-industrial-group-ltd-v-abdelazim-el-shikh-el-fadil-hamid

Cases referred to in this judgment:

Case Citation How used
N/A N/A No specific case law precedents were cited in the text of the order.

Legislation referenced:

  • Rules of the DIFC Courts (RDC): Rule 13
  • Rules of the DIFC Courts (RDC): Rule 14.2
  • Rules of the DIFC Courts (RDC): Rule 14.4
Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.