Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
Singapore

SHIMIZU CORPORATION v STARGOOD CONSTRUCTION PTE LTD

In SHIMIZU CORPORATION v STARGOOD CONSTRUCTION PTE LTD, the Court of Appeal of the Republic of Singapore addressed issues of .

300 wpm
0%
Chunk
Theme
Font

Case Details

  • Citation: [2020] SGCA 37
  • Title: Shimizu Corporation v Stargood Construction Pte Ltd
  • Court: Court of Appeal of the Republic of Singapore
  • Date of Decision: 21 April 2020
  • Civil Appeal No: Civil Appeal No 204 of 2019
  • Originating Summons: Originating Summons No 1099 of 2019
  • Appellant: Shimizu Corporation
  • Respondent: Stargood Construction Pte Ltd
  • Judges: Sundaresh Menon CJ, Tay Yong Kwang JA and Steven Chong JA
  • Legal Area: Building and Construction Law; Security of Payment; Termination and contractual consequences
  • Statutes Referenced: Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) (“SOPA”); Building and Construction Industry Security of Payment (Amendment) Bill (No 38 of 2018) (“2018 Amendments”)
  • Cases Cited: [2019] SGHC 261; [2020] SGCA 37
  • Judgment Length: 28 pages; 7,901 words

Summary

Shimizu Corporation v Stargood Construction Pte Ltd [2020] SGCA 37 addresses a recurring question in Singapore construction disputes under the Building and Construction Industry Security of Payment Act (SOPA): whether a subcontractor may continue to serve payment claims after termination of the subcontract, and whether the SOPA creates an independent statutory entitlement that can override the parties’ contractual termination regime. The Court of Appeal rejected the notion of a “dual railroad track system” in which the SOPA would operate independently of the underlying contract’s substantive rights and termination consequences.

The Court of Appeal held that the first port of call in determining entitlement to submit payment claims remains the underlying construction contract, particularly the provisions governing what happens after termination. While the SOPA facilitates cashflow through a statutory adjudication and payment claim mechanism, it does not alter the substantive allocation of rights and obligations agreed by the parties. Accordingly, whether payment claims can be served post-termination depends on the contract’s termination provisions and the continued existence (or absence) of any contractual payment certification regime.

What Were the Facts of This Case?

Shimizu Corporation (“Shimizu”) was engaged as the main contractor for a project at 79 Robinson Road, Singapore. Stargood Construction Pte Ltd (“Stargood”) was engaged as one of Shimizu’s subcontractors under a letter of acceptance dated 8 February 2018. The letter incorporated the Real Estate Developers’ Association of Singapore Design and Build Conditions of Contract (3rd Ed, 2013), as amended, forming the subcontract (“the Subcontract”).

Under the Subcontract, Shimizu appointed a project director (“the Project Director”) to act on its behalf in relation to subcontract matters, including the certification of progress payments. Clause 28 provided that payment claims were to be submitted by Stargood to the Project Director, who would issue a payment response. The payment response would reflect the amount due from Shimizu to Stargood, thereby linking the SOPA-style payment claim process to a contractual certification mechanism.

After alleged breaches by Stargood, Shimizu issued a notice of default on 4 March 2019. On 22 March 2019, Shimizu exercised its termination rights under cl 33.2 of the Subcontract. The clause provided a structured default-and-rectification process: once the Project Director was satisfied that Stargood had defaulted, a notice of default would be issued, and if Stargood failed to rectify within seven days, Shimizu could terminate the employment of the subcontractor by issuing a notice of termination. This distinction—termination of the subcontractor’s employment rather than necessarily termination of the entire subcontract—became important in the litigation.

On 30 April 2019, after termination, Stargood served Payment Claim No 12 (“PC 12”) on Shimizu for $2,599,359.44 for works done up to April 2019. Shimizu did not serve a payment response. Stargood then lodged an adjudication application (Adjudication Determination No SOP/AA203/2019, “AA 203”) on 4 June 2019. In its adjudication response, Shimizu argued that PC 12 was not properly served and that PC 12 was outside the scope of the SOPA because it was served after termination.

Stargood anticipated the possibility of a service defect and served Payment Claim No 13 (“PC 13”) on 31 May 2019, before the commencement of AA 203. PC 13 was materially similar to PC 12, except that it claimed payment for works done up to May 2019. Shimizu served a payment response to PC 13 stating “nil”. Stargood then lodged a second adjudication (Adjudication Determination No SOP/AA245/2019, “AA 245”) on 5 July 2019. The adjudicator dismissed AA 245 on the basis that Stargood was bound by the earlier determination in AA 203.

In AA 203, the adjudicator dismissed Stargood’s claim on two distinct grounds: (a) PC 12 had not been properly served; and (b) PC 12 was served after Shimizu had terminated the Subcontract, rendering the Project Director functus officio in relation to his certification function. Because the Subcontract did not provide a post-termination payment certification regime, the adjudicator concluded that Stargood could no longer serve a payment claim under the contractual mechanism.

Stargood then filed OS 1099 of 2019 to set aside the adjudication determinations in AA 203 and AA 245 and sought declarations that it was entitled to serve further payment claims on Shimizu.

The Court of Appeal framed two issues. The first was whether the SOPA provides an independent right to continue serving payment claims for works completed regardless of the provisions of the underlying contract. This issue required the Court to consider the effect of the 2018 amendments to the SOPA, which amended the definition of “contract” to include a construction contract (or supply contract) “that has been terminated”.

Within Issue 1, the Court also examined whether there was a separate statutory entitlement under s 5 of the SOPA to progress payments and whether there was a separate statutory entitlement under s 10 of the SOPA to serve a payment claim, even if the underlying contract would not permit it post-termination. The Court further addressed the parties’ competing interpretations of the SOPA’s relationship with the underlying contract, including the argument that the SOPA operates as a “dual railroad track system” allowing a claimant to elect a statutory route that could override contractual restrictions.

The second issue was, if the SOPA did not provide an independent right, whether Stargood was entitled under the Subcontract to serve payment claims on the Project Director following termination. This required analysis of the termination provisions and the payment mechanism in the Subcontract, including whether the Project Director became functus officio and what consequences followed for certification and payment claims.

How Did the Court Analyse the Issues?

The Court of Appeal began by situating the dispute within its earlier decision in Far East Square Pte Ltd v Yau Lee Construction (Singapore) Pte Ltd [2019] 2 SLR 189 (“Far East Square”). In Far East Square, the Court emphasised that determining a contractor’s entitlement to submit payment claims under the SOPA requires regard to the provisions of the underlying construction contract. The Court of Appeal in Shimizu v Stargood treated this as a controlling interpretive principle: the SOPA does not exist in a vacuum, and the contract’s substantive rights remain central to the analysis.

On Issue 1, the Court addressed the “dual railroad track system” argument advanced by Stargood. The argument suggested that the SOPA was designed to provide an option to elect between statutory and contractual entitlement to payment. Under that view, a subcontractor could submit a payment claim under the SOPA even if such submission would be contrary to the contract’s terms, and the SOPA would override the contract. The Court of Appeal rejected this interpretation as inconsistent with Far East Square, where the Court held that the SOPA was not meant to alter substantive contractual rights or create a payment regime independent of the contract.

The Court’s reasoning proceeded from the statutory purpose and structure of the SOPA. While the SOPA aims to improve cashflow and reduce the risk of non-payment by providing a fast adjudication mechanism, it does so by enabling payment claims and responses within the framework of the parties’ contractual arrangements. The Court therefore treated the SOPA as facilitating enforcement of payment entitlements rather than rewriting the parties’ substantive bargain. In other words, the SOPA may provide a procedural route (payment claim, response, adjudication), but it does not necessarily create substantive entitlement where the contract has extinguished or suspended the relevant contractual payment certification regime.

The Court then considered the effect of the 2018 amendments. Stargood relied on the amended definition of “contract” to include a construction contract “that has been terminated”, arguing that this expanded the SOPA’s reach to allow payment claims even after termination. The Court of Appeal accepted that the amendments broadened the scope of what counts as a “contract” for SOPA purposes. However, it did not accept that this automatically meant that termination could be ignored for all substantive questions. The Court’s approach was that the amendments must be read consistently with Far East Square: the SOPA’s expanded definition does not displace the contract’s termination provisions governing post-termination rights and mechanisms.

Having rejected the notion of an independent statutory entitlement that overrides the contract, the Court answered Issue 1 in the negative. The SOPA does not provide a standalone right to continue serving payment claims regardless of the contract’s termination consequences. Instead, whether claims can be served post-termination depends on the contract’s terms, including whether it preserves a certification/payment mechanism after termination.

On Issue 2, the Court turned to the Subcontract’s termination and payment provisions. A key factual and legal distinction concerned whether Shimizu terminated only Stargood’s employment or terminated the entire Subcontract. The Court of Appeal noted that the adjudicator had treated the termination as rendering the Project Director functus officio and had concluded that no post-termination certification regime existed. The Judge below had taken a different view, holding that Shimizu had only terminated Stargood’s employment, and that Stargood could continue to use the payment certification process. The Court of Appeal ultimately disposed of the functus officio debate by focusing on the Subcontract’s termination provisions, rather than engaging in broader speculation about the general doctrine.

Clause 33.2, as quoted in the judgment extract, empowered the Contractor to terminate the employment of the subcontractor upon failure to rectify a default. The Court treated this as a contractual signal that the parties had contemplated consequences short of necessarily extinguishing all mechanisms for assessing and certifying payment for works already performed. However, the Court also emphasised that the parties had not drafted clear post-termination payment certification provisions. Where the contract’s payment mechanism depended on the Project Director’s certification function and did not provide a workable post-termination regime, the ability to serve payment claims could be undermined.

In this context, the Court’s analysis of functus officio served a narrower purpose: it was not an abstract doctrine applied in isolation, but a consequence of the contract’s allocation of certification powers and the effect of termination on those powers. The Court therefore concluded that the Project Director’s certification function could not be assumed to continue indefinitely after termination if the contract did not provide for it. The Court’s approach aligned with its earlier insistence that the underlying contract governs substantive rights and mechanisms, including those relevant to SOPA payment claims.

What Was the Outcome?

The Court of Appeal allowed Shimizu’s appeal and set aside the Judge’s contrary conclusions. The practical effect was that Stargood’s post-termination payment claims (PC 12 and PC 13) could not be sustained on the basis that the SOPA independently preserved a right to serve payment claims after termination regardless of the contractual termination regime.

As a result, the adjudication determinations were not upheld, and Stargood did not obtain the declarations it sought that it was entitled to serve further payment claims post-termination. The decision reinforces that parties must look to the contract’s termination provisions to determine whether the SOPA mechanism can be invoked after termination.

Why Does This Case Matter?

Shimizu v Stargood is significant because it clarifies the interaction between the SOPA and construction contracts in the post-termination context. Practitioners often face disputes where a subcontractor serves payment claims after termination and argues that the SOPA’s statutory framework should override contractual restrictions. This decision confirms that such an argument is unlikely to succeed where the contract’s termination provisions remove or alter the certification/payment mechanism upon which the SOPA process depends.

The case also matters for how lawyers should advise on drafting and risk management. If parties intend that payment certification and progress payment mechanisms should continue after termination (for example, to assess and certify work done up to termination), the contract should expressly provide for a post-termination certification regime and the relevant procedural steps. The Court’s reasoning demonstrates that courts will not infer a post-termination payment regime where the contract is silent or where termination provisions indicate that the contractual machinery has ended.

From a litigation strategy perspective, the decision underscores that SOPA disputes are not purely statutory. Even though SOPA provides a fast adjudication mechanism, the threshold question of entitlement to serve payment claims after termination is closely tied to contractual interpretation. Lawyers should therefore treat the underlying contract as essential evidence and structure submissions around the contract’s termination consequences, rather than relying solely on the SOPA’s amended definitions.

Legislation Referenced

Cases Cited

Source Documents

This article analyses [2020] SGCA 37 for legal research and educational purposes. It does not constitute legal advice. Readers should consult the full judgment for the Court's complete reasoning.

Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.