Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
Singapore

Shimizu Corporation v Stargood Construction Pte Ltd [2020] SGCA 37

The SOPA does not create an independent right to progress payments or to serve payment claims after the termination of a construction contract if the contract itself does not provide for such rights.

300 wpm
0%
Chunk
Theme
Font

Case Details

  • Citation: [2020] SGCA 37
  • Court: Court of Appeal of the Republic of Singapore
  • Decision Date: 21 April 2020
  • Coram: Sundaresh Menon CJ, Tay Yong Kwang JA and Steven Chong JA
  • Case Number: Civil Appeal No 204 of 2019
  • Hearing Date(s): 2 March 2020
  • Claimants / Plaintiffs: Shimizu Corporation (Appellant)
  • Respondent / Defendant: Stargood Construction Pte Ltd (Respondent)
  • Counsel for Appellant: Yong Boon On, Amanda Koh Jia Yi and Lee Shu Qing (Eldan Law LLP)
  • Counsel for Respondent: Christopher Chong and Chen Zhihui (Drew & Napier LLC)
  • Practice Areas: Building and Construction Law; Statutes and regulations; Building and Construction Industry Security of Payment Act; Termination

Summary

The Court of Appeal in Shimizu Corporation v Stargood Construction Pte Ltd [2020] SGCA 37 delivered a landmark ruling clarifying the boundaries of the Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) (“SOPA”) in the context of terminated contracts. The central dispute involved whether a subcontractor, following the termination of its employment, retained an independent statutory right under the SOPA to continue serving payment claims for work performed prior to termination, even where the underlying contract provided no mechanism for post-termination certification. This case serves as the definitive rejection of the "dual railroad track system" theory, which suggested that the SOPA creates a payment regime entirely independent of the parties' contractual bargain.

The appeal arose from a decision of the High Court which had held that the SOPA provided a claimant with a statutory right to serve payment claims that survived the termination of the contract, regardless of whether the contract itself permitted such claims. The High Court had relied on the 2018 amendments to the SOPA, which expanded the definition of "contract" to include terminated contracts, as evidence of a legislative intent to preserve payment claim rights post-termination. However, the Court of Appeal reversed this finding, emphasizing that the SOPA is essentially a "gap-filler" designed to facilitate cash flow within the framework of the parties' agreement, rather than a statute intended to override the substantive allocation of rights and obligations regarding payment certification.

The Court of Appeal applied the principles established in Far East Square Pte Ltd v Yau Lee Construction (Singapore) Pte Ltd [2019] 2 SLR 189, holding that the court must necessarily have regard to the provisions of the underlying construction contract to determine a contractor’s entitlement to submit payment claims. The court concluded that if a contract terminates the certifier's authority and provides no alternative mechanism for certifying payments after termination, the SOPA does not step in to create a new right to serve payment claims. The judgment clarifies that while the SOPA applies to terminated contracts, it does not automatically grant a right to progress payments if the contractual conditions for such payments—specifically the existence of a valid certification process—are no longer met.

This decision has profound implications for the construction industry, particularly regarding the drafting of termination clauses. It reinforces the primacy of the contract in determining the procedural and substantive rights of the parties, even when seeking the protection of the SOPA. By setting aside the High Court's orders, the Court of Appeal restored the adjudicators' original determinations and confirmed that the "functus officio" status of a payment certifier upon termination is a critical factor that can render subsequent payment claims invalid under the SOPA framework.

Timeline of Events

  1. 8 February 2018: Stargood Construction Pte Ltd (“Stargood”) was engaged as a subcontractor for Shimizu Corporation (“Shimizu”) for a project at 79 Robinson Road, Singapore, pursuant to a letter of acceptance.
  2. 4 March 2019: Shimizu issued a notice of default to Stargood following alleged performance failures.
  3. 22 March 2019: Shimizu exercised its termination rights under Clause 33.2 of the Subcontract, terminating Stargood's employment.
  4. 30 April 2019: Stargood served Payment Claim No 12 (“PC 12”) on Shimizu, claiming a sum of $2,599,359.44 for works performed up to April 2019.
  5. 31 May 2019: Stargood served Payment Claim No 13 (“PC 13”) on Shimizu.
  6. 4 June 2019: Stargood commenced adjudication proceedings (AA 203) in relation to PC 12.
  7. 21 June 2019: Stargood commenced adjudication proceedings (AA 245) in relation to PC 13.
  8. 27 June 2019: The adjudicator in AA 203 dismissed the claim, finding that PC 12 was served after termination and that the Project Director was functus officio.
  9. 6 August 2019: The adjudicator in AA 245 dismissed the claim on similar grounds to AA 203.
  10. 2 March 2020: The Court of Appeal heard the substantive appeal in Civil Appeal No 204 of 2019.
  11. 21 April 2020: The Court of Appeal delivered its judgment, allowing Shimizu's appeal and setting aside the High Court's orders.

What Were the Facts of This Case?

Shimizu Corporation (“Shimizu”), the appellant, was the main contractor for a construction project located at 79 Robinson Road, Singapore. On 8 February 2018, Shimizu entered into a subcontract with Stargood Construction Pte Ltd (“Stargood”), the respondent, for the provision of construction works. The subcontract incorporated the Real Estate Developers’ Association of Singapore Design and Build Conditions of Contract (3rd Ed, 2013) (“REDAS Conditions”), subject to certain amendments (collectively, “the Subcontract”). Under the terms of the Subcontract, Shimizu appointed a Project Director to act as the certifier for progress payments. The certification process was a central feature of the parties' agreement, requiring Stargood to submit payment claims to the Project Director, who would then issue payment responses and certificates.

The relationship between the parties deteriorated, leading Shimizu to issue a notice of default to Stargood on 4 March 2019. Shimizu alleged that Stargood had failed to perform its obligations under the Subcontract. When the default was not rectified within the stipulated period, Shimizu proceeded to exercise its rights under Clause 33.2 of the Subcontract. On 22 March 2019, Shimizu formally terminated Stargood’s employment. The termination was effected pursuant to the mechanism in the REDAS Conditions, which allowed the main contractor to terminate the subcontractor's employment in the event of an unremedied default.

Following the termination, Stargood sought to recover payment for work it claimed to have completed prior to the cessation of its employment. On 30 April 2019, more than a month after the termination, Stargood served PC 12 on Shimizu, claiming $2,599,359.44. Shimizu did not provide a payment response. Stargood subsequently served PC 13 on 31 May 2019. Stargood then initiated two separate adjudication applications under the Building and Construction Industry Security of Payment Act: AA 203 (relating to PC 12) and AA 245 (relating to PC 13).

In both adjudications, the adjudicators dismissed Stargood's claims. The primary reasoning in AA 203, delivered on 27 June 2019, was that PC 12 was invalid because it was served after the Subcontract had been terminated. The adjudicator found that upon termination, the Project Director became functus officio, meaning he no longer had the authority or the capacity to certify payment claims. Consequently, there was no longer a contractual mechanism in place to support the service of payment claims or the issuance of payment responses. The adjudicator in AA 245 followed this reasoning in a decision dated 6 August 2019.

Stargood challenged these adjudication determinations in the High Court via Originating Summons No 1099 of 2019. The High Court Judge, in [2019] SGHC 261, set aside the adjudication determinations. The Judge reasoned that the SOPA provided an independent statutory right to progress payments that was not extinguished by the termination of the Subcontract. The Judge also noted that the 2018 amendments to the SOPA, which included "terminated contracts" in the definition of "contract," supported the view that the statutory payment regime continued to operate post-termination. The Judge further held that Shimizu had only terminated Stargood's employment, not the Subcontract itself, and therefore the certification machinery should remain available for work already done. Shimizu appealed this decision to the Court of Appeal.

The Court of Appeal identified two primary issues for determination, which struck at the heart of the relationship between statutory security of payment regimes and private law contracts:

  • Issue 1: Whether the SOPA provides an independent right to continue serving payment claims for works completed regardless of the provisions of the underlying contract (“Issue 1”). This issue required the court to address the "dual railroad track system" argument—the notion that a claimant has a statutory right to serve payment claims that exists alongside and independent of its contractual rights.
  • Issue 2: Whether the respondent was entitled under the terms of the Subcontract to serve payment claims on the Project Director following its termination (“Issue 2”). This involved a close analysis of the specific termination clauses (Clauses 33.2, 33.4, and 33.5) of the REDAS Conditions and whether the Project Director’s certification role survived the termination of the subcontractor's employment.

The resolution of these issues necessitated a deep dive into the legislative intent behind the Building and Construction Industry Security of Payment Act and the 2018 amendments, as well as an application of the "functus officio" doctrine to contractually appointed certifiers in the construction industry.

How Did the Court Analyse the Issues?

The Court of Appeal began its analysis by reaffirming the principle of the primacy of the contract. Delivering the judgment of the court, Steven Chong JA emphasized that the SOPA does not exist in a vacuum but is inextricably linked to the underlying construction contract. The court relied heavily on its prior decision in Far East Square Pte Ltd v Yau Lee Construction (Singapore) Pte Ltd [2019] 2 SLR 189, quoting the following passage at [31]:

“in order to determine a contractor’s entitlement to submit payment claims under the [Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) (“SOPA”)], the court must necessarily have regard to the provisions of the underlying construction contract”

The Rejection of the "Dual Railroad Track System"

The court explicitly rejected the "dual railroad track system" argument proposed by Stargood and accepted by the High Court. This theory suggested that the SOPA provides a statutory right to serve payment claims that is independent of the contract. The Court of Appeal held that this interpretation was "at odds" with the court’s decision in Far East Square (at [3]). The court clarified that the SOPA is a "gap-filler" (at [29]). It operates to provide a right to progress payments where the contract is silent, but it does not override express contractual terms that define when and how payments are to be made, or what happens upon termination.

The court analyzed Section 5 of the SOPA, which states that any person who has carried out construction work "under a contract" is entitled to a progress payment. The court reasoned that the phrase "under a contract" means that the entitlement is rooted in the contract itself. If the contract, through its termination provisions, removes the mechanism for progress payments and replaces it with a different post-termination accounting procedure, the SOPA does not provide a "backdoor" to continue the progress payment regime.

The Impact of the 2018 Amendments

A significant portion of the analysis focused on the 2018 amendments to the SOPA. The High Court had interpreted the new definition of "contract" in Section 2—which includes "a construction contract... that has been terminated"—as a legislative signal that payment claims could always be served after termination. The Court of Appeal disagreed. It held that the amendment was intended to clarify that the SOPA applies to disputes arising from terminated contracts (e.g., for work done before termination), but it does not create new substantive rights that did not exist before (at [35]).

The court noted that the amendment was likely a response to previous uncertainties about whether an adjudicator had jurisdiction over a contract that had been terminated. By including terminated contracts in the definition, Parliament ensured that parties could still use the SOPA's adjudication machinery for claims that were validly made. However, the validity of the claim itself still depends on whether the contract supports the service of that claim at that specific time.

The Functus Officio Status of the Project Director

On Issue 2, the court examined the specific terms of the Subcontract. It noted that the REDAS Conditions distinguish between the termination of the contract and the termination of the subcontractor's employment. Under Clause 33.2, Shimizu terminated Stargood's employment. Clause 33.4 then set out the consequences: the subcontractor must vacate the site, and the main contractor may employ others to complete the work. Crucially, Clause 33.5 provided that the main contractor is not bound to make any further payment to the subcontractor until the works are completed and a final account is settled.

The court held that these clauses effectively suspended the progress payment regime. Because the Project Director's role was to certify progress payments for an ongoing project, that role became functus officio once the subcontractor's employment was terminated and the progress payment regime was replaced by the Clause 33.5 accounting mechanism. The court observed at [51]:

“This would mean that the Project Director became functus officio upon the termination of the Subcontract”

The court distinguished this from cases like Tienrui Design & Construction Pte Ltd v G & Y Trading and Manufacturing Pte Ltd [2015] 5 SLR 852 and CHL Construction Pte Ltd v Yangguang Group Pte Ltd [2019] 4 SLR 1382. In those cases, the contracts did not have the same rigorous post-termination regimes as the REDAS Conditions. The court emphasized that the specific language of the REDAS Conditions was "clear and unambiguous" in halting the progress payment process upon termination.

What Was the Outcome?

The Court of Appeal allowed the appeal in its entirety. The court's decision effectively reversed the High Court's ruling and reinstated the position that Stargood was not entitled to serve PC 12 and PC 13 after its employment had been terminated under the Subcontract. The court's operative order was stated as follows:

“For the above reasons, we allow the appeal and set aside the orders made by the Judge below.” (at [53])

The practical consequences of this outcome were as follows:

  • Setting Aside of High Court Orders: The High Court's orders setting aside the adjudication determinations in AA 203 and AA 245 were themselves set aside. This meant the original adjudicators' decisions to dismiss Stargood's claims stood.
  • Invalidity of Post-Termination Claims: PC 12 and PC 13 were confirmed to be invalid for the purposes of the SOPA because they were served at a time when the contractual certification machinery (the Project Director) was functus officio.
  • Costs: The court ordered Stargood to pay Shimizu the costs of the appeal. These costs were fixed at $25,000, inclusive of disbursements (at [54]).
  • Restoration of Adjudication Status: The court's decision clarified that Shimizu was not in breach of the SOPA by failing to provide payment responses to PC 12 and PC 13, as those claims did not trigger the statutory obligation to respond.

The court's decision provided a definitive end to the litigation regarding these specific payment claims, confirming that Stargood's remedy, if any, lay in the final accounting process under Clause 33.5 of the Subcontract rather than the interim adjudication process of the SOPA.

Why Does This Case Matter?

Shimizu Corporation v Stargood Construction Pte Ltd is a pivotal decision in Singapore's construction law landscape for several reasons. First and foremost, it clarifies the relationship between the SOPA and the underlying contract. For years, there was a debate among practitioners and in lower courts about whether the SOPA created a "dual railroad track" where statutory rights could override contractual limitations. The Court of Appeal has now firmly shut the door on this theory, reinforcing that the SOPA is a procedural "gap-filler" and not a source of substantive rights that can bypass the parties' agreed-upon termination consequences.

Secondly, the case provides essential guidance on the interpretation of the 2018 amendments to the SOPA. By clarifying that the inclusion of "terminated contracts" in Section 2 does not automatically preserve the right to serve payment claims, the court has prevented a potential flood of post-termination adjudications that would have undermined the finality of contractual termination mechanisms. This ensures that the SOPA remains a tool for maintaining cash flow during the life of a project, rather than a weapon to be used after the relationship has ended and a different accounting regime has taken over.

Thirdly, the decision highlights the importance of the functus officio doctrine in the context of construction certifiers. Practitioners must now be acutely aware that once a certifier's authority is terminated—whether by the completion of the project or the termination of the contract—any payment claims served thereafter may be legally "dead on arrival" for the purposes of the SOPA. This places a premium on the timing of payment claims and the careful management of the termination process.

Finally, the case reinforces the importance of standard form contracts like the REDAS Conditions. The court’s willingness to give full effect to Clause 33.5, which suspends payments until final accounting, provides main contractors with significant protection and certainty. It confirms that well-drafted termination clauses will be respected by the courts and will not be easily circumvented by statutory adjudication. This decision will likely lead to more standardized approaches to termination and payment in the Singapore construction industry, as parties seek to align their contracts with the Court of Appeal's "contract-first" philosophy.

Practice Pointers

  • Review Termination Clauses: Practitioners should ensure that termination clauses (like Clause 33.5 of REDAS) clearly specify the consequences for payment. If the intention is to halt progress payments and move to a final account, the language must be "clear and unambiguous" to ensure the certifier becomes functus officio.
  • Timing of Payment Claims: Subcontractors facing potential termination must serve their payment claims before the notice of termination takes effect. Once the employment is terminated, the window for SOPA claims may close permanently if the contract does not provide for post-termination certification.
  • Certifier Authority: Main contractors should clearly define the scope and duration of the certifier's authority. If a certifier is intended to remain active after termination to settle outstanding claims, this must be expressly stated in the contract to avoid functus officio challenges.
  • SOPA as a Gap-Filler: Do not rely on the SOPA to "save" a claim that is contractually prohibited. The SOPA will only supply terms (like the 35-day cycle) where the contract is silent; it will not override express terms that govern the post-termination relationship.
  • 2018 Amendments: Understand that the 2018 amendments regarding "terminated contracts" are jurisdictional, not substantive. They allow an adjudicator to hear a dispute about a terminated contract, but they do not change the fact that the claimant must still prove a contractual entitlement to the payment claimed.
  • Adjudication Strategy: When responding to a post-termination adjudication, main contractors should immediately raise the functus officio argument and the suspension of the progress payment regime as jurisdictional objections, citing Shimizu v Stargood.

Subsequent Treatment

Since its delivery, Shimizu Corporation v Stargood Construction Pte Ltd [2020] SGCA 37 has been the leading authority in Singapore for the proposition that the SOPA does not create an independent right to progress payments post-termination. It is frequently cited in adjudications and High Court set-aside applications to challenge the validity of payment claims served after a contract has been terminated or after a certifier has issued a final certificate. The case is seen as the final word on the "dual railroad track" debate, and its "gap-filler" characterization of the SOPA is now a fundamental principle of Singapore construction law.

Legislation Referenced

Cases Cited

  • Applied: Far East Square Pte Ltd v Yau Lee Construction (Singapore) Pte Ltd [2019] 2 SLR 189
  • Referred to: Stargood Construction Pte Ltd v Shimizu Corporation [2019] SGHC 261
  • Referred to: Tienrui Design & Construction Pte Ltd v G & Y Trading and Manufacturing Pte Ltd [2015] 5 SLR 852
  • Referred to: CHL Construction Pte Ltd v Yangguang Group Pte Ltd [2019] 4 SLR 1382
  • Referred to: Choi Kum Peng and another v Tan Poh Eng Construction Pte Ltd [2014] 1 SLR 1210
  • Referred to: LW Infrastructure Pte Ltd v Lim Chin San Contractors Pte Ltd [2011] 4 SLR 477

Source Documents

Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.