Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Singapore

Kori Construction (S) Pte Ltd v Nam Hong Construction & Engineering Pte Ltd [2015] SGHC 25

In Kori Construction (S) Pte Ltd v Nam Hong Construction & Engineering Pte Ltd, the High Court of the Republic of Singapore addressed issues of Building and Construction Law — statutes and regulations, Statutory Interpretation.

Case Details

  • Citation: [2015] SGHC 25
  • Case Title: Kori Construction (S) Pte Ltd v Nam Hong Construction & Engineering Pte Ltd
  • Court: High Court of the Republic of Singapore
  • Date of Decision: 30 January 2015
  • Judge: Hoo Sheau Peng JC
  • Coram: Hoo Sheau Peng JC
  • Case Number: District Court Appeal No 45 of 2014
  • Proceedings Below: Nam Hong Construction & Engineering Pte Ltd v Kori Construction (S) Pte Ltd [2014] SGDC 271
  • Appellant/Applicant: Kori Construction (S) Pte Ltd (“Kori”)
  • Respondent: Nam Hong Construction & Engineering Pte Ltd (“Nam Hong”)
  • Counsel for Appellant: Twang Kern Zern (Central Chambers Law Corporation)
  • Counsel for Respondent: Andrew John Hanam (Andrew LLC)
  • Legal Area(s): Building and Construction Law — statutes and regulations; Statutory Interpretation
  • Statutory Provisions Referenced: Building Control Act (Cap 29, 1999 Rev Ed) (“BCA”) s 2; s 29A; s 29B
  • Other Statutes Referenced: Interpretation Act; Bankruptcy Act (Cap 20, 2009 Rev Ed); A of the Interpretation Act (as referenced in the metadata)
  • Judgment Length: 10 pages, 5,207 words
  • Subsequent History: Appeal to this decision in Civil Appeal No 44 of 2015 allowed by the Court of Appeal on 8 July 2016 (see [2016] SGCA 42)

Summary

Kori Construction (S) Pte Ltd v Nam Hong Construction & Engineering Pte Ltd concerned a contractor’s ability to recover unpaid sums where the contractor had allegedly carried out “specialist building works” without the requisite licence under the Building Control Act (Cap 29, 1999 Rev Ed) (“BCA”). The dispute arose from an unpaid invoice issued by Nam Hong, a sub-contractor on the MRT Downtown Line project, for fabrication and related steel strutting works.

The High Court (Hoo Sheau Peng JC) allowed Kori’s appeal on a preliminary question of law. The key question was whether “structural steelwork” under the definition of “specialist building works” in s 2 of the BCA should be construed such that the three limbs in s 2(1) (d)(i)–(iii) are read conjunctively or disjunctively. The District Judge had construed the limbs conjunctively, holding that all three elements were required. The High Court disagreed and held that the limbs should be read disjunctively, with the result that Nam Hong’s conduct fell within “structural steelwork” and therefore triggered the licensing consequences in s 29B(4).

What Were the Facts of This Case?

Kori was a sub-contractor for the MRT Downtown Line project. Nam Hong was engaged as Kori’s sub-contractor for a defined scope of works under a Letter of Award dated 23 January 2013. Clause 2 of that Letter of Award required Nam Hong to fabricate, load and unload steel strutting works, including connection plates and stiffeners, and to provide sufficient qualified personnel and equipment to carry out the works according to the schedule.

In performance of this scope, Nam Hong issued 11 invoices to Kori. Kori paid the amounts due under the first ten invoices but did not pay the 11th invoice. Nam Hong therefore commenced proceedings in the District Court to recover $147,538.39 said to be due under the 11th invoice.

Before the District Judge, Kori raised a preliminary question of law grounded in the BCA’s licensing regime. At the relevant time, Nam Hong did not hold either a general builder’s licence or a specialist builder’s licence from the Building and Construction Authority (“the Authority”). Kori’s position was that Nam Hong had carried out “specialist building works” without the required licence, and that s 29B(4) of the BCA barred Nam Hong from recovering any charge, fee or remuneration for such works in court.

The parties’ dispute turned on whether the works performed by Nam Hong amounted to “structural steelwork”, which is one category of “specialist building works” under s 2 of the BCA. The definition of “structural steelwork comprising” includes (i) fabrication of structural elements; (ii) erection work such as site cutting, site welding and site bolting; and (iii) installation of steel supports for geotechnical building works. The District Court proceeded on an undisputed factual basis that Nam Hong performed fabrication and erection work corresponding to limbs (i) and (ii). The only question was whether limb (iii) was also required for the works to qualify as “structural steelwork”.

The High Court framed the appeal as turning on statutory interpretation: whether the three limbs in the definition of “structural steelwork” within s 2 of the BCA should be read conjunctively or disjunctively. This was described as the “narrow issue”. The broader consequence was whether, if the definition was satisfied, s 29B(4) would prevent Nam Hong from pursuing its claim for payment under the 11th invoice.

In the District Court, the judge had held that the limbs were to be read conjunctively. That approach meant that a contractor would need to carry out all three types of work to fall within the definition of “structural steelwork”. Kori’s appeal challenged this approach, arguing that the limbs should be read disjunctively so that performing any one or more of the listed activities could amount to “structural steelwork”.

Accordingly, the legal issue was not merely linguistic. It required the court to consider the statutory purpose of the licensing regime and the interpretive principles governing how words such as “and” operate in statutory lists. The court also had to assess whether reading the definition disjunctively would align with Parliament’s intention and avoid unintended overbreadth.

How Did the Court Analyse the Issues?

The High Court began by setting out the relevant statutory framework. Section 29B(2) requires persons carrying on the business of a general builder or specialist builder to possess the appropriate licence. Section 29B(3) makes it an offence to carry on such business without the appropriate licence. Crucially, s 29B(4) provides that, subject to the Act, a person who carries out general building works or specialist building works in contravention of s 29B(2) is not entitled to recover in any court any charge, fee or remuneration for those works. This provision is designed to remove the incentive and ability to profit from unlicensed high-risk work.

The interpretive focus was therefore the definition of “specialist building works” in s 2 of the BCA. That definition lists seven categories, and only s 2(1)(d) was relevant. The court noted that s 2(1)(d) defines “structural steelwork comprising” three types of work. The dispute was whether the word “and” in the phrase “structural steelwork comprising … (i) …; (ii) …; and (iii) …” should be treated as requiring all three limbs (conjunctive reading) or whether it could operate disjunctively such that the performance of one or more limbs suffices.

On behalf of Kori, counsel relied on the Court of Appeal’s reasoning in Lim Lye Hiang v Official Assignee [2012] 1 SLR 228. In Lim Lye Hiang, the Court of Appeal had read two limbs of s 78(1) of the Bankruptcy Act disjunctively even though the word “and” connected them. The High Court accepted the general principle that “and” may be read disjunctively where the joined items function as a list of different objects or classes, related only by the fact that they qualify to be included in that list. Kori argued that the structure of s 2(1)(d) was analogous: the three limbs were different types of work that could each qualify as “structural steelwork” for the purposes of the definition.

Nam Hong’s response was that the interpretive choice depended on the statutory context and parliamentary intention. Nam Hong argued that reading the limbs conjunctively better reflected the licensing regime’s purpose: to ensure that contractors performing high-risk work have the requisite competence. On this view, the high-risk element was the installation of steel supports for geotechnical building works (limb (iii)). By contrast, fabrication of structural elements and erection work such as site cutting, welding and bolting (limbs (i) and (ii)) were said to be less inherently dangerous. If the definition were read disjunctively, Nam Hong argued, it would effectively require licensing for a wide range of contractors who perform only fabrication or erection tasks, thereby expanding the licensing regime beyond what Parliament intended.

The High Court’s analysis proceeded by applying established statutory interpretation principles, including the need to give effect to every word while also considering the overall scheme and purpose of the legislation. The court considered that the definition in s 2(1)(d) uses the phrase “comprising” and sets out a structured list of activities. The court treated the list as capable of operating disjunctively, consistent with the approach in Lim Lye Hiang, rather than as a set of cumulative requirements. In other words, the court was not persuaded that Parliament intended “structural steelwork” to be limited to a contractor who performs all three specified activities, particularly where the statutory text defines the category by reference to the listed components.

Although the licensing rationale was acknowledged, the High Court did not accept that the risk-based purpose necessarily required a conjunctive reading of the definition. The court’s reasoning emphasised that the licensing consequence in s 29B(4) is triggered by carrying out “specialist building works” without the appropriate licence. If the statutory definition is satisfied by the performance of the listed activities, then the licensing consequence follows. The court therefore treated the interpretive question as primarily one of how the statutory definition is constructed, rather than as a policy exercise to narrow the definition to only the most dangerous sub-activity.

In allowing the appeal, the High Court concluded that the three limbs of s 2(1)(d) should be read disjunctively. On the facts, Nam Hong had accepted that it performed fabrication (limb (i)) and erection work (limb (ii)). The court’s disjunctive interpretation meant that this was sufficient to constitute “structural steelwork” under the BCA definition. As a result, Nam Hong had carried out “specialist building works” without the required specialist builder’s licence, and s 29B(4) barred it from recovering remuneration for those works.

What Was the Outcome?

The High Court allowed Kori’s appeal and set aside the District Judge’s decision. The court held that “structural steelwork” under s 2(1)(d) of the BCA should be construed disjunctively, so that the performance of fabrication and erection work (limbs (i) and (ii)) fell within the definition even without the performance of installation of steel supports for geotechnical building works (limb (iii)).

Practically, this meant that Nam Hong’s claim for the unpaid 11th invoice was barred by s 29B(4) because Nam Hong carried out specialist building works without the requisite licence. The decision therefore reinforced the strict consequences of non-compliance with the BCA licensing regime for specialist building works.

Why Does This Case Matter?

This case is significant for practitioners because it clarifies how courts may interpret statutory definitions that use list-based language in the context of regulatory licensing regimes. The High Court’s approach demonstrates that a disjunctive reading of “and” is not confined to exceptional drafting patterns; it can apply where the statutory structure and interpretive principles support treating listed items as alternative qualifying activities within a defined category.

For construction lawyers and contractors, the decision highlights the commercial risk of relying on a narrow reading of “specialist building works”. If a contractor performs any of the activities that fall within the definition of “structural steelwork”, it may be exposed to the s 29B(4) bar on recovery, even if it does not perform all sub-activities listed in the definition. This has direct implications for subcontracting arrangements, scope-of-works drafting, and licensing compliance strategies.

From a statutory interpretation perspective, the case is also useful because it engages with the Court of Appeal’s reasoning in Lim Lye Hiang and applies it to a different statutory context. It illustrates how courts balance textual analysis (including the role of “comprising” and list structure) with legislative purpose (the competence and risk rationale behind licensing). Even where policy arguments favour a narrower interpretation, the court may still give effect to the statutory text where the definition’s structure supports disjunctive operation.

Legislation Referenced

  • Building Control Act (Cap 29, 1999 Rev Ed) — s 2 (definition of “specialist building works”, including s 2(1)(d) “structural steelwork”); s 29A; s 29B(2), s 29B(3), s 29B(4)
  • Interpretation Act (as referenced in the metadata)
  • Bankruptcy Act (Cap 20, 2009 Rev Ed) — s 78(1) (as referenced in Lim Lye Hiang)

Cases Cited

  • [2014] SGDC 271
  • [2015] SGHC 25
  • [2016] SGCA 42
  • Lim Lye Hiang v Official Assignee [2012] 1 SLR 228

Source Documents

This article analyses [2015] SGHC 25 for legal research and educational purposes. It does not constitute legal advice. Readers should consult the full judgment for the Court's complete reasoning.

Written by Sushant Shukla

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.