Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Singapore

DAY v DAZ [2023] SGHC 185

In DAY v DAZ, the High Court of the Republic of Singapore addressed issues of Arbitration — Stay of court proceedings.

Case Details

  • Citation: [2023] SGHC 185
  • Title: DAY v DAZ
  • Court: High Court of the Republic of Singapore (General Division)
  • Date of decision: 5 July 2023
  • Judge: Chua Lee Ming J
  • Originating Application: OA 189 of 2023
  • Registrar’s Appeal: Registrar’s Appeal No 77 of 2023
  • Procedural posture: Appeal against the Assistant Registrar’s dismissal of an application to stay court proceedings in favour of arbitration
  • Plaintiff/Applicant: DAY (claimant in OA 189)
  • Defendant/Respondent: DAZ (defendant in OA 189)
  • Legal area: Arbitration — stay of court proceedings
  • Statute(s) referenced: International Arbitration Act (2020 Rev Ed) (“IAA”)
  • Key statutory provision: Section 6 of the IAA (mandatory stay where conditions are met)
  • Arbitration agreement anchor: General Term (“GT”) 14 of the LFA
  • Specific carve-out terms: Specific Terms (“ST”) 3.3 and 3.4 of the LFA
  • Arbitration seat/venue (contextual): Not fully stated in the extract; arbitration proceedings were commenced against Co1 and resulted in a final award
  • Length of judgment: 20 pages, 5,126 words
  • Cases cited (as per metadata): [2023] SGHC 185; [2023] SGHC 71

Summary

DAY v DAZ concerned an application to stay court proceedings in favour of arbitration under s 6 of the International Arbitration Act (2020 Rev Ed) (“IAA”). The defendant (DAZ) appealed against the Assistant Registrar’s decision dismissing its stay application in respect of OA 189/2023. The central dispute was not whether there was a valid arbitration agreement, but whether the specific controversy raised in OA 189 fell within the scope of that arbitration agreement or had been carved out by the parties’ contractual structure.

The High Court (Chua Lee Ming J) allowed the appeal and ordered a stay of OA 189 pursuant to s 6 of the IAA. The court held that the defendant had established, at least on a prima facie basis, that the dispute in OA 189 was within the scope of the arbitration agreement in GT 14 of the funding agreement (“LFA”), and that the mandatory stay mechanism under s 6 applied. The practical effect was that the claimant’s attempt to obtain court-ordered specific performance of ST 3.3 (relating to obtaining a binding written opinion on whether a proposed settlement was “fair and reasonable”) would be channelled to arbitration rather than litigated in court.

What Were the Facts of This Case?

On 28 October 2019, DAY (the claimant) entered into a funding agreement with DAZ (the defendant), DAZ’s related company (RelCo), and DAZ’s parent company (HoldCo). Under the LFA, DAY agreed to provide funding and project support services to DAZ and RelCo to pursue claims against two target companies, Co1 and Co2. The LFA contemplated that DAY would be entitled, as a first priority, to receive certain amounts out of any settlement or judgment sum obtained. The present proceedings concerned only DAZ’s claim against Co1.

DAZ commenced arbitration proceedings against Co1 on 4 March 2020. The tribunal issued a final award on 16 September 2021 in DAZ’s favour (the “Final Award”). DAY funded the arbitration costs pursuant to the LFA. After the award, Co1 applied to the English High Court to set aside parts of the Final Award; that application was dismissed on 11 January 2022. During that English set-aside process, DAY funded the costs incurred by DAZ in defending Co1’s application.

Following the English proceedings, DAZ and Co1 entered settlement negotiations. Between July 2022 and September 2022, the parties exchanged drafts of settlement agreements. Around 21 September 2022, DAZ’s solicitors sent a draft settlement agreement (the “Draft Settlement Agreement”) to Co1’s solicitors. Co1 agreed to the terms by email dated 22 September 2022. Importantly, DAY also agreed that the terms were acceptable and appropriate.

However, on 26 September 2022, DAZ informed DAY that it would not enter the Draft Settlement Agreement unless DAY agreed to share the first instalment payment with DAZ. DAY did not agree. On 11 October 2022, DAY put DAZ on notice that DAZ’s failure to promptly execute the Draft Settlement Agreement was a breach of the LFA, including General Term (“GT”) 4.1, which required DAZ to act in good faith. DAY requested that DAZ remedy the breach by executing the Draft Settlement Agreement by 14 October 2022. DAZ responded on 13 October 2022 that it did not wish to enter the Draft Settlement Agreement, citing that the commercial rationale for accepting the instalment payment plan had “evaporated” due to DAZ’s difficult financial position. DAZ also expressed concern about the risk of Co1 defaulting on the final tranche payment and denied that it had committed an event of default under the LFA.

The LFA contained a dispute resolution mechanism specifically addressing disagreements about whether to agree to settlement. Specific Term (“ST”) 3.3 provided a process for resolving disagreements between DAY and DAZ over whether to agree to a settlement of DAZ’s claim against Co1. The first step required DAZ’s lawyers to provide a written opinion on whether the proposed settlement was fair and reasonable. If the parties still could not resolve the disagreement, an independent counsel would provide a written opinion. Under ST 3.4, the opinion of counsel instructed under ST 3 would be “final and binding” on both DAY and DAZ.

DAY’s position was that, on 20 October 2022, it was agreed that DAZ’s lawyers would prepare a written opinion under ST 3.3 on whether the Draft Settlement Agreement was fair and reasonable. DAZ denied that such an agreement was reached. While it was not disputed that DAZ’s lawyers commenced work on an opinion, DAZ contended that it was simultaneously advising DAZ on whether ST 3.3 even applied to the Draft Settlement Agreement. An email dated 21 November 2022 from DAZ’s lawyers stated that DAZ had taken legal advice and was not required under ST 3.3 to instruct its lawyers to opine on whether the Draft Settlement Agreement was fair and reasonable.

DAZ’s reasons for asserting that ST 3.3 and ST 3.4 did not apply were, in substance, that those terms concerned the settlement of “Claims” or “Proceedings” (as defined), and that the Draft Settlement Agreement related to enforcement of the Final Award rather than the settlement of DAZ’s underlying claim against Co1. DAZ argued that ST 3.3 and ST 3.4 would only be triggered if DAY had agreed to fund recognition and enforcement proceedings in accordance with the LFA. DAZ relied on GT 8.1 and GT 8.2, which required DAY to notify DAZ and its lawyers in writing that it was prepared to fund enforcement proceedings. DAY had not given such notice, so DAZ argued that the Draft Settlement Agreement was not a settlement of “the Proceedings” within the meaning of ST 3.3.

On 2 March 2023, DAY filed OA 189 seeking, in substance, specific performance of ST 3.3. DAY sought orders requiring DAZ and DAY to jointly instruct independent counsel (or have counsel appointed by the President of the Singapore Bar Association) to provide a written opinion within seven days on whether the Draft Settlement Agreement was fair and reasonable. DAY also sought orders requiring DAZ to take steps to execute the Draft Settlement Agreement if the opinion was that it was fair and reasonable, and further sought disclosure of the identity and contact details of DAZ’s secured creditors for service purposes.

DAZ responded by filing HC/SUM 860/2023 on 27 March 2023, seeking a stay of the whole action in OA 189 in favour of arbitration under s 6 of the IAA, or alternatively under the court’s inherent case management powers. DAZ relied on GT 14 of the LFA. GT 14.1 provided that any dispute arising out of the LFA “which is not subject to Specific Term 3.3 and 3.4” must be resolved in accordance with GT 14. GT 14 set out a staged dispute resolution process involving good faith endeavours, mediation (if the parties agreed), and arbitration (if unresolved).

The Assistant Registrar dismissed DAZ’s stay application on 12 April 2023. The Assistant Registrar’s view was that the anterior question—whether ST 3.3 and ST 3.4 applied to the Draft Settlement Agreement—was carved out from GT 14 and therefore fell outside the arbitration agreement. DAZ appealed to the High Court on 18 April 2023.

The High Court identified the key legal issue as whether DAZ had established a prima facie case that the dispute in OA 189 fell within the scope of the arbitration agreement in GT 14 of the LFA. This mattered because s 6 of the IAA requires the court to grant a stay if certain conditions are met, including that the dispute in the court proceedings (or part thereof) falls within the scope of the arbitration agreement.

Although the existence and validity of the arbitration agreement were not contested, the parties’ contractual drafting created a threshold interpretive question: whether the dispute about whether ST 3.3 and ST 3.4 applied to the Draft Settlement Agreement was itself “carved out” from arbitration under GT 14. In other words, the court had to decide whether the claimant’s claim for specific performance of ST 3.3 was properly characterised as a dispute that belonged to the arbitration process, or as a dispute excluded from arbitration by the LFA’s carve-out language.

Accordingly, the legal issues were twofold: first, the proper approach to a stay application under s 6 of the IAA (including the prima facie standard); and second, the construction of the LFA—particularly the interaction between GT 14 and ST 3.3/ST 3.4—to determine whether the dispute in OA 189 was within the arbitration clause’s scope.

How Did the Court Analyse the Issues?

The court began by restating the legal framework for a stay application under s 6 of the IAA. Relying on Tomolugen Holdings Ltd and another v Silica Investors Ltd and other appeals [2016] 1 SLR 373, the court emphasised that the court should grant a stay if the applicant establishes a prima facie case that: (a) there is a valid arbitration agreement; (b) the dispute in the court proceedings (or any part thereof) falls within the scope of the arbitration agreement; and (c) the arbitration agreement is not null and void, inoperative, or incapable of being performed. The court noted that the validity and non-defectiveness of the arbitration agreement were not contested.

That left the sole question of scope. The court’s analysis therefore focused on whether the dispute raised by DAY in OA 189—seeking specific performance of ST 3.3 and consequential relief—was within GT 14’s arbitration mechanism, or whether it was excluded by the carve-out in GT 14.1 for disputes “subject to Specific Term 3.3 and 3.4”. This required the court to consider how the carve-out operated when the parties disputed whether ST 3.3 and ST 3.4 applied at all.

On the contractual interpretation, the court treated the “anterior question” (whether ST 3.3 and ST 3.4 applied to the Draft Settlement Agreement) as part of the dispute. DAZ argued that DAY’s claim could not be insulated from arbitration merely by framing it as a request for specific performance of ST 3.3. The court accepted, on a prima facie basis, that the dispute about whether ST 3.3/ST 3.4 were engaged was intertwined with the broader disagreement arising out of the LFA and therefore fell within the arbitration clause’s ambit.

In reaching this conclusion, the court’s reasoning reflected the policy underlying s 6 of the IAA: where parties have agreed to arbitrate disputes, the court should not readily allow litigants to bypass arbitration by characterising issues as matters for court determination. The prima facie standard is designed to avoid a full merits determination at the stay stage. Thus, the court did not decide definitively whether ST 3.3 applied; rather, it assessed whether DAZ had shown that there was a credible basis to arbitrate that question under GT 14.

In practical terms, the court’s approach meant that the carve-out language in GT 14.1 could not be read as automatically removing from arbitration any dispute that required the tribunal to determine whether ST 3.3/ST 3.4 were applicable. If the parties’ disagreement necessarily required interpretation of the LFA’s settlement mechanism and its triggers, that interpretive dispute was itself a dispute “arising out of” the LFA. Since GT 14 provided for arbitration of disputes not subject to ST 3.3/ST 3.4, the tribunal would be the appropriate forum to determine whether the carve-out applied.

The court therefore held that DAZ had established a prima facie case that OA 189 fell within the scope of the arbitration agreement. The court’s reasoning aligns with the general principle that arbitration agreements should be construed to give effect to the parties’ agreement to arbitrate, and that disputes about the scope or applicability of contractual mechanisms are typically for the arbitral tribunal to determine, at least at the threshold stage for a stay application.

What Was the Outcome?

The High Court allowed DAZ’s appeal. It ordered that OA 189/2023 be stayed pursuant to s 6 of the IAA. This meant that DAY’s court action seeking specific performance of ST 3.3 (and related relief) would not proceed in the High Court, and the parties would instead resolve the dispute through arbitration under GT 14 of the LFA.

The practical effect is that the tribunal would determine, as part of the arbitral process, whether ST 3.3 and ST 3.4 were triggered by the Draft Settlement Agreement and, consequently, whether DAY was entitled to the relief it sought in OA 189.

Why Does This Case Matter?

DAY v DAZ is significant for practitioners because it illustrates how Singapore courts apply the mandatory stay regime under s 6 of the IAA when the parties dispute the scope of an arbitration agreement. Even where a claimant frames its case as a request for specific performance of a particular contractual term, the court will still examine whether the dispute is, in substance, within the arbitration clause’s scope.

The case also highlights the importance of careful drafting in multi-layered dispute resolution clauses. Where an agreement contains both an arbitration clause and a carve-out tied to specific terms (here, ST 3.3 and ST 3.4), disputes about whether the carve-out is engaged may themselves be treated as part of the arbitral scope. This reduces the risk that a party can avoid arbitration by litigating threshold contractual questions in court.

For law students and litigators, the decision reinforces the prima facie nature of the stay inquiry. The court does not conduct a full merits analysis of whether ST 3.3 applies; instead, it asks whether the applicant has shown a credible basis that the dispute belongs in arbitration. This approach supports arbitration’s efficiency and respects party autonomy, consistent with Singapore’s arbitration-friendly legislative framework.

Legislation Referenced

  • International Arbitration Act (2020 Rev Ed), s 6

Cases Cited

  • Tomolugen Holdings Ltd and another v Silica Investors Ltd and other appeals [2016] 1 SLR 373
  • [2023] SGHC 71 (cited in the judgment as per metadata)
  • [2023] SGHC 185 (this case)

Source Documents

This article analyses [2023] SGHC 185 for legal research and educational purposes. It does not constitute legal advice. Readers should consult the full judgment for the Court's complete reasoning.

Written by Sushant Shukla

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.