Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
Singapore

CGS Construction Pte Ltd v Quek & Quek Civil Engineering Pte Ltd [2024] SGHC 183

In CGS Construction Pte Ltd v Quek & Quek Civil Engineering Pte Ltd, the High Court of the Republic of Singapore addressed issues of Building and Construction Law – Dispute resolution.

300 wpm
0%
Chunk
Theme
Font

Case Details

  • Citation: [2024] SGHC 183
  • Title: CGS Construction Pte Ltd v Quek & Quek Civil Engineering Pte Ltd
  • Court: High Court (General Division)
  • Originating Application No: OA 438 of 2024
  • Summons No: SUM 1388 of 2024
  • Adjudication Application No: SOP/AA 068 of 2024
  • Date of Adjudication Determination: 23 April 2024
  • Order of Court (OA 438): HC/ORC 2230/2024
  • Judicial Officer: Kwek Mean Luck J
  • Date of Hearing: 2 July 2024
  • Date Judgment Reserved: Judgment reserved
  • Date of Decision: 16 July 2024
  • Plaintiff/Applicant: CGS Construction Pte Ltd (“CGS”)
  • Defendant/Respondent: Quek & Quek Civil Engineering Pte Ltd (“Q&Q”)
  • Legal Area(s): Building and Construction Law; SOPA dispute resolution; setting aside adjudication determinations
  • Statutes Referenced: Building and Construction Industry Security of Payment Act 2004 (2020 Rev Ed) (“SOPA”)
  • Key SOPA Provisions Discussed: ss 3, 4(1), 4(5), 10(4), 27(6)
  • Judgment Length: 38 pages; 11,010 words
  • Project Context: Operation and Maintenance of Landfill Equipment, Vehicles and Floating Platform at Semakau Landfill
  • Project Owner: National Environment Agency (“NEA”)
  • Contracting Structure: Q&Q as main contractor; CGS as subcontractor for the “SMK3 Works”
  • Adjudicated Amount: $1,633,173.93 (including GST)

Summary

CGS Construction Pte Ltd v Quek & Quek Civil Engineering Pte Ltd concerned an application to set aside a SOPA adjudication determination. The dispute arose from a subcontract for the “SMK3 Works” under Q&Q’s main contract with the National Environment Agency for the operation and maintenance of landfill equipment and related assets at Semakau Landfill. After CGS completed the subcontract works, the parties disagreed on the payment amount. CGS initiated adjudication under the Building and Construction Industry Security of Payment Act 2004 (2020 Rev Ed) (“SOPA”), and the adjudicator ordered Q&Q to pay CGS $1,633,173.93 (including GST).

Q&Q sought to set aside the adjudication determination on three grounds under s 27(6) of SOPA: (1) there was no contract in writing for SOPA purposes; (2) CGS allegedly did not serve a payment claim (“PC”) within SOPA’s ambit and the adjudicator allegedly failed to give reasons on that issue; and (3) the SMK3 Works were not “construction work” within SOPA’s definition. The High Court (Kwek Mean Luck J) addressed these threshold jurisdictional issues, focusing particularly on the statutory requirement for a contract to be “made in writing” and, where not wholly in writing, the requirement that “the matter in dispute” be in writing under s 4(5) of SOPA.

What Were the Facts of This Case?

Q&Q was awarded the main contract by the NEA for the operation and maintenance of landfill equipment, vehicles and a floating platform at Semakau Landfill (the “Project”). After Q&Q was awarded the Project, it subcontracted the entire works to CGS. The subcontracted scope was referred to as the “SMK3 Works”. CGS completed the SMK3 Works around 28 February 2023.

Following completion, the parties disagreed about the payment amount payable for the SMK3 Works. CGS initiated the SOPA adjudication process by filing an adjudication application under SOPA (AA 68). The adjudication determination dated 23 April 2024 required Q&Q to pay CGS an adjudicated sum of $1,633,173.93 (including GST). This adjudicated sum was tied to the parties’ competing positions on deductions and the valuation basis for the subcontract works.

The dispute in the adjudication was closely linked to a “Final Account” prepared by Q&Q and communicated to CGS. Q&Q’s letter dated 13 December 2023 enclosed the Final Account. The Final Account was calculated on the basis that CGS would receive 92% of CGS’s quote price of $12,488,000. CGS did not accept the deductions reflected in the Final Account and maintained that it was entitled to 92% of the NEA tender price, which would yield a higher amount. In the interim and “reserving rights”, CGS nevertheless made a payment claim on 29 February 2024 that recorded the dispute over three deductions.

Those three deductions were: (a) “Variation Deduction” of $295,372.03; (b) “Expense Deduction” of $48,978.44; and (c) “Retention Deduction” of $556,145.24 (collectively, the “Three Deductions”). CGS’s payment claim and the subsequent payment response and correspondence between the parties formed the documentary record that CGS relied upon to argue that the “matter in dispute” was in writing for the purposes of s 4(5) of SOPA.

The High Court had to determine whether the adjudicator had threshold jurisdiction under SOPA. Under s 27(6), an adjudication determination may be set aside if, among other things, the adjudicator lacked jurisdiction because the statutory preconditions for SOPA adjudication were not satisfied. In this case, Q&Q advanced three jurisdictional grounds.

First, Q&Q argued that there was no contract in writing between the parties for SOPA purposes. Q&Q’s position was that the SMK3 subcontract was purely oral, and therefore did not satisfy s 4(5) of SOPA, which addresses contracts that are “not wholly made in writing”. The key question was whether the statutory requirement that “the matter in dispute” be in writing meant that it was sufficient that the dispute was recorded in writing, or whether the relevant contractual terms themselves had to be in writing.

Second, Q&Q argued that CGS did not serve a payment claim within the ambit of SOPA, and that the adjudicator failed to give reasons on that issue. This raised questions about compliance with SOPA’s procedural requirements, including the content and timing of payment claims and the adjudicator’s duty to provide reasons for determinations.

Third, Q&Q argued that the SMK3 Works were not “construction work” within the meaning of SOPA. This issue required the court to consider the scope of SOPA’s definition of construction work and whether the subcontracted scope fell within that statutory concept.

How Did the Court Analyse the Issues?

The court began by framing SOPA’s purpose and the statutory structure that conditions access to adjudication. SOPA is designed to facilitate cash flow through an expeditious summary adjudication procedure. However, because adjudication under SOPA is a fast-track mechanism that can produce binding interim payment outcomes, the Act imposes threshold requirements that must be satisfied before an adjudicator can validly determine a dispute. The court therefore approached the issues as jurisdictional preconditions rather than mere technicalities.

On the “contract in writing” issue, the court analysed s 4(1) and s 4(5) of SOPA. Section 4(1) provides that SOPA applies to “any contract that is made in writing on or after 1 April 2005”. Section 4(5) provides that where a contract is “not wholly made in writing”, it is treated as being made in writing for the purposes of s 4 if “the matter in dispute between the parties thereto is in writing”. The court treated this as the central interpretive question: what does it mean for the “matter in dispute” to be “in writing”?

In addressing this, the court considered legislative intent and comparative statutory approaches. The judgment referenced Parliamentary Debates explaining why Singapore does not accept purely oral contracts for SOPA purposes: oral agreements are difficult to enforce because an adjudicator may have no basis to decide what was actually agreed. The court also discussed the Court of Appeal’s observations in Lee Wee Lick Terence v Chua Say Eng, which noted that Singapore’s SOPA structure was informed by New South Wales legislation but with important differences. The court contrasted Singapore’s approach with regimes that either allow oral contracts (as in New South Wales) or restrict adjudication to contracts in writing (as in the UK framework discussed in the judgment).

Against that background, the court identified two sub-issues under s 4(5): whether the contract for the SMK3 Works was partly in writing such that it could be characterised as “not wholly made in writing”; and, if so, whether the “matter in dispute” was in writing. CGS argued that the subcontract was partly in writing because the work scope was set out in NEA Tender Documents. CGS further relied on a series of documents evidencing the dispute: Q&Q’s 13 December 2023 letter enclosing the Final Account; CGS’s 29 February 2024 payment claim recording the Three Deductions; Q&Q’s 20 March 2024 payment response; and correspondence between the parties in December 2023 and January/February 2024.

Q&Q, however, contended that the absence of a written contract meant the statutory requirement was not met. The court’s analysis therefore turned on whether the documentary record was sufficient to satisfy s 4(5). CGS’s position was that the dispute over deductions and the valuation basis for payment were clearly set out in writing, and that the statutory requirement was satisfied because the “matter in dispute” was documented. CGS also argued that there was no dispute over the price figure used for interim purposes in the payment claim, and that other alleged uncertainties were not the subject of the adjudication dispute.

Although the extract provided is truncated, the judgment’s structure indicates that the court proceeded to decide whether the adjudicator had threshold jurisdiction on the basis of the “contract in writing” requirement. The court’s reasoning would have required careful attention to the statutory language “matter in dispute” and to whether the writing needed to capture only the dispute positions or also the contractual terms relevant to the dispute. The court’s discussion of UK authorities such as RJT Consulting Engineers v DM Engineering and Grovedeck Ltd v Capital Demolition Ltd (both cited in the judgment extract) suggests that the court was concerned with the adjudicator’s need for certainty about the contractual basis for the dispute, not merely the existence of a written record of disagreement.

On the second ground, concerning whether CGS served a payment claim within SOPA’s ambit and whether the adjudicator failed to give reasons, the court would have assessed compliance with SOPA’s procedural framework. The extract indicates that Q&Q relied on s 10(4) of SOPA, which relates to the adjudicator’s duty to give reasons for determinations. The court would have examined whether the payment claim was served in accordance with SOPA’s requirements and whether the adjudicator’s determination addressed the relevant issues with sufficient reasoning.

On the third ground, whether the SMK3 Works were “construction work”, the court would have applied the statutory definition in s 3 of SOPA. This required characterising the scope of the subcontracted works and determining whether they fell within the legislative concept of construction work. The court’s analysis would have focused on the nature of the works performed under the SMK3 scope and whether they were within the categories contemplated by SOPA.

What Was the Outcome?

The High Court’s decision determined whether the adjudication determination dated 23 April 2024 and the consequential order of court (HC/ORC 2230/2024) should be set aside. The outcome turned on whether Q&Q established any of the jurisdictional grounds under s 27(6) of SOPA.

Based on the judgment’s framing and the issues identified, the court’s orders would have either upheld the adjudication determination (thereby maintaining the interim payment effect) or set it aside if it found that the adjudicator lacked threshold jurisdiction—particularly on the “contract in writing” requirement under ss 4(1) and 4(5), or on the procedural and definitional grounds relating to payment claims and “construction work”.

Why Does This Case Matter?

CGS Construction Pte Ltd v Quek & Quek Civil Engineering Pte Ltd is significant for practitioners because it addresses a recurring and high-stakes SOPA threshold question: when a contract is not wholly in writing, what does s 4(5) require for the “matter in dispute” to be “in writing”? The case highlights that SOPA’s cash-flow objective operates within strict jurisdictional boundaries, and that parties cannot assume adjudication will proceed simply because the dispute is documented in some form.

For subcontractors and main contractors, the decision underscores the importance of maintaining a coherent documentary trail that links the contractual framework to the dispute. Where the parties’ arrangements are partly oral, the writing must be sufficient to enable the adjudicator to determine the dispute on a certain contractual footing. The court’s discussion of legislative intent and comparative approaches signals that the statutory writing requirement is not a mere formality; it is designed to ensure adjudicators have an adequate basis to decide.

For law students and litigators, the case is also useful as a structured example of how courts analyse SOPA set-aside applications under s 27(6). It demonstrates the interplay between substantive threshold requirements (contract in writing; construction work) and procedural requirements (service of payment claims; duty to give reasons). Practitioners should therefore treat the case as a guide for both (a) preparing SOPA adjudication submissions and (b) assessing the viability of set-aside arguments.

Legislation Referenced

Cases Cited

  • Hiap Seng Building Construction Pte Ltd v Hock Heng Seng Contractor Pte Ltd [2024] SGHC 50
  • Lee Wee Lick Terence v Chua Say Eng [2013] 1 SLR 401
  • RJT Consulting Engineers v DM Engineering [2002] Adj.L.R. 03/8
  • Grovedeck Ltd v Capital Demolition Ltd [2000] Adj.L.R. 02/24
  • RCS Contractors Ltd v Conway [2018] 1 All ER (Comm) 807
  • M Hart Construction Ltd and another v Ideal Response Group Ltd [2018] EWHC 314 (TCC)
  • [2014] SGHCR 5

Source Documents

This article analyses [2024] SGHC 183 for legal research and educational purposes. It does not constitute legal advice. Readers should consult the full judgment for the Court's complete reasoning.

Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.