Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
uae-difc-cases

DGA PROJECT MANAGEMENT SERVICES v AL REYAMI STEEL CONSTRUCTION [2021] DIFC TCD 002 — Summary assessment of costs following construction litigation (09 September 2021)

The litigation between DGA Project Management Services and Al Reyami Steel Construction originated from a construction-related dispute that necessitated multiple procedural interventions within the Technology and Construction Division (TCD).

300 wpm
0%
Chunk
Theme
Font

This amended order finalizes the cost recovery process in a long-standing construction dispute, establishing the financial liability of the Defendant following the substantive judgment delivered by Justice Sir Richard Field.

What was the specific monetary dispute regarding costs between DGA Project Management Services and Al Reyami Steel Construction in TCD 002/2019?

The litigation between DGA Project Management Services and Al Reyami Steel Construction originated from a construction-related dispute that necessitated multiple procedural interventions within the Technology and Construction Division (TCD). Following the substantive judgment handed down by Justice Sir Richard Field on 16 June 2021, the focus shifted to the quantification of legal costs incurred by the Claimant. The parties engaged in a formal process of cost submission and objection, with the Claimant filing a Statement of Costs on 8 August 2021, which the Defendant subsequently challenged on 18 August 2021.

The dispute at this stage was not about the merits of the underlying construction contract, but rather the reasonableness and proportionality of the legal fees claimed by DGA Project Management Services. The Registrar was tasked with reconciling the Claimant’s requested figures against the Defendant’s objections to arrive at a fair summary assessment. The final determination resulted in the following order:

The Defendant is to pay the Claimant’s costs summarily assessed in the amount of USD 3,000, payable within 14 days from the date of this order, with interest accruing at a rate of 9% p/a annum, from 23 September 2021 until the date of full payment.

This order serves as the final financial resolution regarding the costs associated with the proceedings, as detailed in the DGA PROJECT MANAGEMENT SERVICES v AL REYAMI STEEL CONSTRUCTION [2020] DIFC TCD 002 — Document production order for expired digital assets (19 November 2020) and subsequent procedural orders such as the DGA PROJECT MANAGEMENT SERVICES v AL REYAMI STEEL CONSTRUCTION [2021] DIFC TCD 002 — Pre-trial procedural rigour in construction disputes (25 April 2021).

Which DIFC judge presided over the summary assessment of costs in TCD 002/2019?

The amended order regarding the summary assessment of costs was issued by Registrar Nour Hineidi of the DIFC Courts. The order was signed and issued on 9 September 2021, following the substantive judgment previously delivered by Justice Sir Richard Field on 16 June 2021. The Registrar’s role in this instance was to exercise the court's power to summarily assess costs under the Rules of the DIFC Courts (RDC), ensuring that the litigation concluded with a clear, enforceable financial obligation.

How did the parties approach the summary assessment of costs in TCD 002/2019?

The Claimant, DGA Project Management Services, initiated the cost recovery process by filing a Statement of Costs on 8 August 2021, seeking reimbursement for legal expenses incurred during the TCD proceedings. This filing is a standard procedural step in DIFC litigation, intended to provide the court with a transparent breakdown of professional fees and disbursements.

The Defendant, Al Reyami Steel Construction, exercised its procedural right to challenge the Claimant’s submission by filing a formal objection on 18 August 2021. By filing this objection, the Defendant sought to minimize the cost burden imposed upon it, likely arguing that the claimed amounts were either disproportionate to the complexity of the matter or included items not properly recoverable under the RDC. The Registrar, Nour Hineidi, reviewed both the Claimant’s Statement of Costs and the Defendant’s objections before issuing the final determination.

What was the jurisdictional basis for Registrar Nour Hineidi to issue an amended order for costs in TCD 002/2019?

The legal question before the Registrar was the exercise of the court’s discretion to conduct a summary assessment of costs under the RDC. The court had to determine the appropriate quantum of costs that the Defendant was liable to pay to the Claimant, taking into account the successful outcome of the substantive claim. The doctrinal issue centers on the court's authority to finalize cost awards without the need for a full, detailed assessment hearing, provided that the court has sufficient information to reach a fair and proportionate figure.

The Registrar’s authority is derived from the RDC, which empowers the court to summarily assess costs at the conclusion of proceedings. The court had to balance the Claimant’s right to be indemnified for reasonable legal costs against the Defendant’s right to challenge excessive or unjustified claims. By issuing an amended order, the Registrar ensured that the final judgment was enforceable and that the interest rate and payment timeline were clearly defined for both parties.

What reasoning did Registrar Nour Hineidi apply to reach the USD 3,000 cost award?

In reaching the decision, the Registrar performed a judicial review of the competing filings. The process involved weighing the Claimant’s Statement of Costs against the specific objections raised by the Defendant. The Registrar’s reasoning is rooted in the principle of proportionality, ensuring that the costs awarded reflect the work reasonably performed during the litigation.

The Registrar’s decision-making process is summarized by the final order:

The Defendant is to pay the Claimant’s costs summarily assessed in the amount of USD 3,000, payable within 14 days from the date of this order, with interest accruing at a rate of 9% p/a annum, from 23 September 2021 until the date of full payment.

This reasoning reflects a standard application of the court's discretion to fix costs at a level that avoids the delay and expense of a full taxation process, while still providing a meaningful recovery for the prevailing party.

Which specific Rules of the DIFC Courts (RDC) govern the summary assessment of costs applied in TCD 002/2019?

The summary assessment of costs in the DIFC is governed by Part 38 of the Rules of the DIFC Courts (RDC). Specifically, RDC 38.16 provides the court with the power to make a summary assessment of costs at the conclusion of a trial or hearing. This rule is designed to encourage efficiency and prevent the "costs of the costs" from becoming a disproportionate burden on the parties.

Furthermore, the court’s ability to award interest on costs is governed by the general principles of the DIFC Courts regarding judgment debts. By setting the interest rate at 9% per annum, the Registrar applied the standard approach to ensure that the delay in payment from the date of the order until the date of full satisfaction is compensated, thereby maintaining the value of the award.

How does the TCD 002/2019 order align with the precedent set by Justice Sir Richard Field’s judgment?

The order issued by Registrar Nour Hineidi is a procedural consequence of the substantive judgment delivered by Justice Sir Richard Field on 16 June 2021. In the DIFC, the summary assessment of costs is the final step in the litigation lifecycle, ensuring that the "loser pays" principle is effectively implemented. The Registrar’s order does not revisit the merits of the case; rather, it gives effect to the court’s previous determination that the Claimant was entitled to recover costs.

By referencing the 16 June 2021 judgment, the Registrar ensured that the cost award was tethered to the underlying success of the Claimant. This alignment is critical for maintaining the integrity of the TCD’s procedural framework, as it prevents the Defendant from relitigating the substantive issues under the guise of challenging costs.

What is the final disposition and relief granted in the amended order of 9 September 2021?

The final disposition of the matter is a clear financial order against the Defendant. The Registrar ordered Al Reyami Steel Construction to pay DGA Project Management Services the sum of USD 3,000. This amount is to be paid within 14 days of the order date. Additionally, the order includes a provision for interest, which accrues at a rate of 9% per annum starting from 23 September 2021. This ensures that the Claimant is protected against the time value of money should the Defendant fail to make payment within the prescribed 14-day window.

What are the practical implications for litigants in the DIFC Technology and Construction Division regarding cost assessments?

This case highlights the importance of meticulous record-keeping and the filing of accurate Statements of Costs. Litigants must anticipate that the TCD will rigorously scrutinize cost claims, and that the opposing party will likely file formal objections. The summary assessment process is intended to be efficient, but it requires parties to be prepared to justify every item in their statement.

Practitioners should note that the Registrar’s decision to award a specific, fixed amount (USD 3,000) underscores the court's preference for finality. Parties should be prepared for the court to take a robust approach to summary assessment, often trimming claimed amounts to reflect what the court deems strictly necessary. For further guidance on procedural rigour, see DGA PROJECT MANAGEMENT SERVICES v AL REYAMI STEEL CONSTRUCTION [2021] DIFC TCD 002 — Procedural directions on late evidence (27 May 2021).

Where can I read the full judgment in DGA Project Management Services v Al Reyami Steel Construction [2021] DIFC TCD 002?

The full text of the amended order can be accessed via the official DIFC Courts website: https://www.difccourts.ae/rules-decisions/judgments-orders/technology-and-construction-division/tcd-002-2019-dga-project-management-services-llc-v-al-reyami-steel-construction-4. The document is also available via the CDN link: https://littdb.sfo2.cdn.digitaloceanspaces.com/litt/AE/DIFC/judgments/technology-and-construction-division/DIFC_TCD-002-2019_20210909.txt.

Cases referred to in this judgment:

Case Citation How used
DGA Project Management Services v Al Reyami Steel Construction [2021] DIFC TCD 002 Substantive judgment (16 June 2021)

Legislation referenced:

  • Rules of the DIFC Courts (RDC), Part 38 (Costs)
Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.