Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
uae-difc-cases

KALIOPE v KARAM CONSTRUCTION [2019] DIFC SCT 404 — Enforcement of sub-contractor payment obligations (29 October 2019)

The dispute arose from a sub-contracting arrangement initiated on 2 May 2018, wherein Kaliope LLC was engaged by Karam Construction LLC to supply materials and perform construction services for the "OJ-138 Showroom & Offices" project located in Al Barsha.

300 wpm
0%
Chunk
Theme
Font

The Small Claims Tribunal confirms the liability of a main contractor to pay outstanding invoices to a sub-contractor, emphasizing the necessity of evidentiary support when alleging defective performance in construction disputes.

What was the nature of the contractual dispute between Kaliope and Karam Construction regarding the OJ-138 Showroom & Offices project?

The dispute arose from a sub-contracting arrangement initiated on 2 May 2018, wherein Kaliope LLC was engaged by Karam Construction LLC to supply materials and perform construction services for the "OJ-138 Showroom & Offices" project located in Al Barsha. Kaliope alleged that it had fully performed its contractual obligations, yet Karam Construction refused to settle the outstanding balance reflected in the statement of accounts. The total amount sought by the Claimant was AED 54,724.58, which included the court filing fees.

The factual disagreement centered on the completion status of the project. While the Claimant maintained that all services were rendered in accordance with the Local Purchase Order (LPO), the Defendant contended that the work was incomplete and had been rejected by its project consultant. As noted in the judgment:

The Claimant completed the work for the Project and the Defendant refused to pay the amount pending as per the Claimant’s complete statement of accounts. The total amount claimed is AED 54,724.58 which includes the 5% court filing fee.

How did SCT Judge Maha Al Mehairi manage the hearing in Kaliope v Karam Construction [2019] DIFC SCT 404?

The matter was presided over by SCT Judge Maha Al Mehairi. Following an unsuccessful consultation on 19 September 2019 before SCT Judge Hayley Norton, the case proceeded to a hearing on 9 October 2019. The Defendant failed to appear at the hearing despite having been duly served with notice. Consequently, the court proceeded in the Defendant's absence, relying on the evidence presented by the Claimant. As recorded in the judgment:

The matter was called before me on 9 October 2019, with the Claimant’s representative in attendance and the Defendant absent though served notice of the hearing date.

Kaliope argued that it had fulfilled its contractual duties as a sub-contractor and was therefore entitled to payment for the pre-agreed services rendered. The Claimant emphasized that the evidence provided by the Defendant—specifically photographs purportedly showing defective work—actually predated the completion of the project, thereby failing to reflect the final state of the work.

Conversely, Karam Construction argued that the Claimant failed to meet the requirements set out in the LPO. The Defendant asserted that the project consultant had disqualified the work, leading to the rejection of the Claimant’s final invoice. The Defendant’s position was summarized as follows:

The Defendant also provided pictures of the Project arguing that the project was disqualified by the consultant and accordingly the Claimant’s last invoice was rejected.

What was the jurisdictional question the SCT had to resolve regarding the agreement between Kaliope and Karam Construction?

The court had to determine whether it possessed the requisite jurisdiction to adjudicate the claim based on the contractual terms agreed upon by the parties. The Claimant relied on a specific jurisdiction clause contained within the agreement, which stipulated that any disputes arising out of or in connection with the agreement—including questions regarding validity, performance, and applicable remedies—would be subject to the exclusive jurisdiction of the DIFC Courts. The court affirmed its authority to hear the matter based on this express declaration, confirming that the dispute fell squarely within the scope of the parties' chosen forum.

How did Judge Maha Al Mehairi apply the burden of proof to the Defendant’s claims of non-performance?

Judge Al Mehairi applied a standard of evidence that required the Defendant to substantiate its allegations of defective work. Because the Defendant failed to provide evidence of third-party remediation costs or documentation proving that the work was unacceptable, the court found the Claimant’s evidence of completion to be persuasive. The judge concluded that the Claimant had indeed finished the project as presented.

The reasoning focused on the lack of objective evidence from the Defendant to counter the Claimant’s statement of accounts. As stated in the judgment:

I am satisfied that the Claimant completed the work of the Project as presented by the Claimant in its final state

Which DIFC Rules of Court were applied to the procedural conduct of the hearing in this matter?

The court relied on Rule 53.61 of the Rules of the DIFC Courts (RDC), which governs the procedure when a party fails to attend a hearing. Under this rule, because the Claimant attended and the Defendant did not, the SCT was empowered to decide the claim based solely on the evidence provided by the Claimant. Additionally, the court invoked RDC Rule 36.40 to facilitate the issuance of an amended judgment to correct the final order, ensuring the monetary relief was accurately reflected.

How did the court utilize the evidence of the LPO and the statement of accounts in determining the breach?

The court treated the LPO dated 2 May 2018 as the primary instrument defining the scope of the sub-contracting work. The Claimant’s statement of accounts served as the evidentiary basis for the outstanding debt. The court noted that the Defendant had previously paid invoices in accordance with the work completed, which established a pattern of performance. The court rejected the Defendant’s reliance on consultant rejections because the Defendant failed to produce any formal documentation or third-party invoices proving that the work required fixing or was objectively substandard.

What was the final disposition and the specific monetary relief ordered by the SCT?

The court allowed the claim in its entirety, finding that the Claimant had fulfilled its contractual obligations. The Defendant was ordered to pay the principal sum of AED 52,118.65 for the pending invoices. Furthermore, the Defendant was ordered to reimburse the Claimant for the court filing fees. The final order was:

As such it is hereby ordered that the Defendant shall pay the Claimant the amount of AED 52,118.65 for the pending invoices. The Defendant shall pay the Claimant the DIFC Court filing fee in the amount of AED 2,605.93.

What are the practical implications for construction sub-contractors and main contractors appearing before the SCT?

This case serves as a reminder that the SCT will not accept unsubstantiated claims of "defective work" or "consultant rejection" in the absence of documentary evidence. For defendants, the failure to attend a hearing or provide concrete proof—such as third-party invoices for remedial work—is fatal to their defense. For claimants, maintaining a clear statement of accounts and being prepared to demonstrate the timeline of work completion is essential to securing a favorable judgment in construction disputes.

Where can I read the full judgment in Kaliope LLC v Karam Construction LLC [2019] DIFC SCT 404?

The full judgment is available on the DIFC Courts website: https://www.difccourts.ae/rules-decisions/judgments-orders/small-claims-tribunal/kaliope-llc-v-karam-construction-llc-2019-difc-sct-404

Cases referred to in this judgment:

Case Citation How used
N/A N/A No external case law cited in the judgment.

Legislation referenced:

  • Rules of the DIFC Courts (RDC), Rule 53.61
  • Rules of the DIFC Courts (RDC), Rule 36.40
  • DIFC Contract Law
Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.