Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
uae-difc-cases

NASHTAR v NASIRUDDIN [2024] DIFC SCT 351 — Maintenance contract dispute and delay penalty enforcement (11 October 2024)

The Small Claims Tribunal clarifies the enforceability of delay penalties in construction contracts where both parties contribute to project timelines, while affirming the validity of signed agreements despite allegations of forgery.

300 wpm
0%
Chunk
Theme
Font

What was the specific nature of the contractual dispute between Nashtar and Nasiruddin regarding the AED 425,000 maintenance agreement?

The dispute arose from a maintenance contract dated 20 February 2024, under which Nashtar (the Claimant) agreed to perform maintenance works on five warehouses for Nasiruddin (the Defendant) for a lump sum of AED 425,000. The Claimant alleged that the Defendant breached the contract by failing to pay invoices and by unilaterally descoping one of the warehouses, which caused the Claimant to incur unrecovered labor costs. Furthermore, the Claimant argued that the Defendant’s failure to issue gate passes for workers caused significant project delays, for which the Claimant sought compensation.

The Defendant contested the claim, arguing that the work was incomplete and that the Claimant had failed to secure proper approval for invoices from the Defendant’s engineer. The Defendant further alleged that the contract document relied upon by the Claimant was forged, a defense the Court ultimately rejected due to a lack of supporting evidence. The scope of the project, as defined in the contract, was central to the dispute:

As per the Contract, the Claimant’s scope of work comprises of five warehouses as shown below: (a) Maintenance of Warehouse 1 at a cost of AED 48,750.

The Claimant maintained that the contract was a lump sum agreement and that no specific quantities or measurements were required beyond the agreed scope. The total amount claimed by Nashtar reached AED 168,920, covering unpaid works and accommodation costs, while the Defendant counterclaimed for delay penalties and back charges.

Which judge presided over Nashtar v Nasiruddin and in which DIFC division was the matter heard?

The matter was heard before SCT Judge Maitha AlShehhi in the Small Claims Tribunal (SCT) of the DIFC Courts. The hearing took place on 26 September 2024, with the final judgment issued on 11 October 2024.

The Claimant argued that the contract was valid and binding, asserting that the Defendant had signed the final version after multiple exchanges. The Claimant sought compensation for delays caused by the Defendant’s failure to facilitate site access, specifically citing the contract clause providing for a penalty of AED 200 per person per day for delays in starting work.

Conversely, the Defendant argued that the contract was forged and that the Claimant had failed to complete the works to the required standard. The Defendant sought to deduct AED 48,163.38 from the contract price due to incomplete work and lack of engineer-approved invoices. Regarding the delay penalties, the Defendant invoked the contract’s liquidated damages clause, which capped penalties at 10% of the project value. The competing positions on penalties were summarized by the Court:

In respect of penalty, the Claimant is requesting the Defendant pay penalty of AED 200 per person for delay in start of work while the Defendant is requesting the Claimant to pay AED 410 for failure to submit project on time (capped at 10% of project value).

The Claimant’s position was weakened by its failure to provide concrete evidence or quantification for the damages it sought, whereas the Defendant provided a payment certificate that the Court ultimately used to determine the actual amount owed for completed works.

What was the jurisdictional basis for the DIFC Court to hear a maintenance contract dispute between two UAE-registered entities?

The primary legal question concerned the Court’s jurisdiction under the Judicial Authority Law (JAL) and the parties' express choice of forum. Despite both parties being registered in the UAE (Sharjah and Dubai, respectively), the contract contained a specific jurisdiction clause designating the DIFC Courts. The Court addressed this by confirming its authority to hear the matter based on the parties' clear intent:

Further to the above, the DIFC Courts have jurisdiction to hear and determine the Claim in accordance with Article 5(A)(1)(2) of the JAL on the basis that the jurisdiction clause mentioned in the Contract is clear on the parties’ intention to resort to the DIFC Courts in case of any dispute and is the appropriate forum to hear the Claim.

The Court had to determine whether this clause was sufficient to establish jurisdiction in the absence of a direct DIFC nexus, ultimately concluding that the contractual agreement to submit to the DIFC Courts was binding and satisfied the requirements of Article 5(A) of the JAL.

How did Judge Maitha AlShehhi apply the doctrine of contractual validity and the principle of payment for performance in the face of mutual delays?

Judge AlShehhi employed a two-fold test: first, assessing the evidentiary burden regarding the alleged forgery, and second, evaluating the entitlement to payment for work performed despite project delays. Regarding the forgery claim, the Judge found that the Defendant failed to provide sufficient evidence to invalidate the signed agreement.

Regarding the payment for works, the Court applied the principle that a contractor is entitled to be paid for completed work even if the project timeline is not strictly adhered to, provided the work has been performed. The Court noted that both parties contributed to the delays, and therefore, the Claimant’s failure to meet the 60-day deadline did not forfeit its right to payment for the work actually delivered. The Court’s reasoning for the final award was based on the Defendant’s own payment certificate:

Therefore, I shall rely on the Defendant’s payment certificate in which it provides that the Claimant is entitled to the amount of AED 27,366.63 as opposed to the Claimant’s proforma invoice.

This approach ensured that the Claimant was compensated for the value of the work performed, while the Defendant was protected by the penalty clause for the delays that occurred.

Which specific DIFC statutes and RDC rules were applied by the SCT in determining the outcome of the maintenance contract dispute?

The Court relied primarily on Article 5(A) of the Judicial Authority Law (JAL), which governs the jurisdiction of the DIFC Courts. Procedurally, the matter was governed by the Rules of the DIFC Courts (RDC), specifically RDC 53.2, which outlines the simplified procedures for the Small Claims Tribunal. These rules allow the SCT to adopt a less formal approach to evidence and procedure, which was essential given the nature of the documentation provided by the parties, including the proforma invoices and the Defendant’s payment certificate.

How did the Court utilize the contract’s penalty clause and the Defendant’s payment certificate as authoritative evidence?

The Court utilized the contract’s penalty clause as a mechanism to balance the competing claims of delay. The Claimant’s argument for penalties was rejected because the Claimant failed to quantify the damages or the number of personnel affected by the Defendant’s failure to issue gate passes.

In contrast, the Defendant’s counterclaim for delay penalties was successful because the contract clearly stipulated a penalty of AED 410 per day for delays beyond the 60-day completion period, capped at 10% of the contract value. The Court used the Defendant’s payment certificate as the definitive record of the amount owed to the Claimant, effectively overriding the Claimant’s own proforma invoice. This reliance on the Defendant’s internal documentation served as a check against the Claimant’s potentially inflated claims, while simultaneously acknowledging the Defendant’s obligation to pay for the work that had been certified as completed.

What was the final disposition of the claim and counterclaim, and how were the costs allocated?

The Court ordered a partial success for both parties. The Claimant was awarded AED 39,366.63 for works performed and accommodation costs. The Defendant’s counterclaim for delay penalties was also partially successful, resulting in an award of AED 31,250 to the Defendant. The Court’s order regarding the penalty was explicit:

The Counterclaim in respect of the penalty shall succeed and the Claimant shall pay the Defendant the amount of AED 31,250. 94.

Regarding costs, the Court ordered that the Claimant pay the Defendant’s filing fee of AED 1,562.50, while the Defendant was ordered to pay the Claimant’s filing fee of AED 1,968.33. This split reflects the Court’s determination that both parties were partially responsible for the contractual failures.

What are the practical implications for contractors and employers in the DIFC regarding the enforcement of delay penalties?

This case reinforces that delay penalties in construction contracts are strictly enforceable in the SCT, provided the contract terms are clear and the penalty is quantifiable. Practitioners should note that the SCT will not award penalties if the claimant fails to quantify the damages or the specific impact of the delay. Furthermore, the case highlights that the SCT will prioritize signed contracts over allegations of forgery unless substantial evidence is provided to support such claims.

For future litigants, the case emphasizes the importance of maintaining accurate payment certificates and project documentation. The Court’s willingness to rely on the Defendant’s own payment certificate as a benchmark for the amount due suggests that such internal records carry significant weight in the absence of other corroborating evidence. Parties should anticipate that the SCT will look for evidence of cooperation—or lack thereof—when determining whether to enforce delay penalties, particularly in projects where both parties contribute to the timeline slippage.

Where can I read the full judgment in Nashtar v Nasiruddin [2024] DIFC SCT 351?

The full judgment is available on the DIFC Courts website: https://www.difccourts.ae/rules-decisions/judgments-orders/small-claims-tribunal/nashtar-v-nasiruddin-2024-difc-sct-351

CDN link: https://littdb.sfo2.cdn.digitaloceanspaces.com/litt/AE/DIFC/judgments/small-claims-tribunal/DIFC_SCT-351-2024_20241011.txt

Cases referred to in this judgment:

Case Citation How used
N/A N/A No external case law cited in the judgment.

Legislation referenced:

  • Judicial Authority Law (JAL), Article 5(A)(1)(2)
  • Rules of the DIFC Courts (RDC), Rule 53.2
Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.