Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
uae-difc-cases

MRUTTI v MIKARTIL [2023] DIFC SCT 223 — Breach of settlement agreement and mutual performance obligations (11 August 2023)

The Small Claims Tribunal clarifies the limits of recovery for breach of settlement agreements, emphasizing that a claimant cannot seek damages for non-performance when their own failure to act contributed to the breach.

300 wpm
0%
Chunk
Theme
Font

What was the specific monetary value and nature of the dispute in Mrutti v Mikartil [2023] DIFC SCT 223?

The dispute centered on an alleged breach of a Settlement Agreement and a subsequent Consent Order arising from the sale of two companies, Murp and Mepil. The Claimant, Mrutti, sought a total of AED 403,429.45 in damages, alleging that the Defendants failed to replace landlord cheques and update company records as required by the underlying Sale and Purchase Agreement (SPA) and the subsequent settlement terms.

On 12 June 2023, the Claimant filed a claim seeking damages due to an alleged breach of a Settlement Agreement dated 31 March 2023 (the “Settlement Agreement”) and a Consent Order dated 1 April 2023 (issued in Claim No. SCT-076-2022) in the sum of AED 403,429.45 (the “Consent Order”).

The Claimant argued that the Defendants' failure to comply with these obligations led to significant financial consequences, including a travel ban and the initiation of rental dispute proceedings by third-party landlords. The Claimant also sought to recover legal expenses totaling AED 150,000 incurred during the protracted enforcement efforts.

Which judge presided over the SCT hearing in Mrutti v Mikartil [2023] DIFC SCT 223?

The matter was heard before H.E. Justice Nassir Al Nasser in the Small Claims Tribunal (SCT) of the DIFC Courts. Following a failed consultation with SCT Judge Hayley Norton on 29 June 2023, the case proceeded to a hearing on 12 July 2023, with the final judgment issued on 11 August 2023.

The Claimant, Mrutti, argued that the Defendants’ persistent failure to replace landlord cheques and update trade licenses—despite multiple enforcement orders—constituted a material breach of the Settlement Agreement. The Claimant contended that this non-compliance directly caused the Claimant to incur substantial legal costs and financial losses, including the loss of a previously waived amount of AED 45,484.

The Claimant filed its claim against the Defendants to recover damages arising out of an alleged breach of the Settlement Agreement.

Conversely, the Defendants contested the extent of their liability, pointing to the Claimant’s own failures in the transition process. The Defendants argued that the Claimant failed to transfer the company bank account, which hindered their ability to perform their contractual obligations. The defense maintained that the Claimant’s own omissions were a significant factor in the operational failures that led to the landlord disputes and the subsequent legal actions.

The Court was tasked with determining whether the Claimant was entitled to damages for breach of contract under the Settlement Agreement when the Claimant had also failed to perform interdependent obligations. Specifically, the Court had to decide if the Claimant could recover losses—including legal fees and waived debt—when the Defendants’ non-performance was partially attributable to the Claimant’s own failure to facilitate the transfer of company assets, such as the bank account.

How did H.E. Justice Nassir Al Nasser apply the doctrine of non-performance in Mrutti v Mikartil?

Justice Al Nasser applied the principle that a party cannot claim damages for a breach if their own conduct contributed to that breach. The Court found that while the Defendants were indeed in default regarding certain obligations, the Claimant’s failure to transfer the company bank account prevented the Defendants from fulfilling their duties.

Therefore, I dismiss the Claimant’s claims for damages in accordance with Article 78 of the DIFC Contract Law.

The Court reasoned that the obligations were interdependent. By failing to complete the necessary administrative transfers, the Claimant could not hold the Defendants solely liable for the resulting operational failures. Consequently, the Court limited the award to a specific, undisputed utility payment (Du payment) and dismissed the broader claims for damages and legal costs.

Which specific provisions of the DIFC Contract Law were applied to the facts of this case?

The Court relied on Article 77 and Article 78 of the DIFC Contract Law. Article 78, in particular, served as the primary basis for the dismissal of the majority of the Claimant’s damages. This article addresses the non-performance of a party and the extent to which a claimant's own actions or omissions preclude them from seeking relief. The Court utilized this to balance the mutual failures of the parties, effectively neutralizing the Claimant's request for substantial damages.

The Claimant specifically sought to recover legal fees incurred during the enforcement proceedings.

(j) The Claimant had to incur legal expenses in the sum of AED 150,000 in seeking legal advice which he now seeks to recover.

The Court rejected this claim. Consistent with the SCT’s general approach to costs and the finding that the Claimant was partially responsible for the breakdown of the agreement, the Court ordered that each party bear its own costs. The request for the recovery of the "waived amount" of AED 45,484 was similarly dismissed, as the Court found no basis to reinstate a debt that had been explicitly waived in the Settlement Agreement.

What was the final disposition and the specific relief granted by the SCT?

The Court partially allowed the claim. The Second Defendant was ordered to pay the Claimant AED 1,599.19, representing a specific Du utility payment. All other claims for damages, including the recovery of legal fees and the previously waived debt, were dismissed. The Court ordered that each party bear its own costs, reflecting the finding that both parties failed to meet their respective contractual obligations.

What are the practical implications of Mrutti v Mikartil for DIFC practitioners drafting settlement agreements?

This judgment serves as a reminder that the DIFC Courts will strictly scrutinize the conduct of both parties in breach of contract claims. Practitioners must ensure that settlement agreements clearly define the sequence of obligations and provide mechanisms for dealing with non-performance that do not rely on the other party's cooperation. Litigants should anticipate that if they seek damages for a counterparty's breach, the Court will examine their own compliance with the agreement. Failure to demonstrate full performance of one's own obligations—especially in interdependent contracts—will likely result in the dismissal of claims for damages, regardless of the counterparty's failure to perform.

Where can I read the full judgment in Mrutti v Mikartil [2023] DIFC SCT 223?

The full judgment is available on the DIFC Courts website: https://www.difccourts.ae/rules-decisions/judgments-orders/small-claims-tribunal/mrutti-v-1-mikartil-2-muhar-2023-difc-sct-223

Cases referred to in this judgment:

Case Citation How used
N/A N/A No external precedents cited in the judgment text.

Legislation referenced:

  • DIFC Contract Law, Article 77
  • DIFC Contract Law, Article 78
  • Rules of the Small Claims Tribunal (SCT)
Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.