Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
uae-difc-cases

THE LIUDEN LLC v LENNA [2020] DIFC SCT 107 — Breach of construction agreement and notice requirements (20 August 2020)

The litigation centered on a contractual disagreement arising from a renovation project for a private villa. The Liuden LLC, a construction firm, was engaged by Lenna to perform renovation works, which were subsequently expanded by the Defendant during the project's lifecycle.

300 wpm
0%
Chunk
Theme
Font

This judgment clarifies the enforceability of contractual notice periods in construction disputes within the Small Claims Tribunal, specifically addressing the consequences of terminating an agreement without providing the mandatory opportunity for rectification.

What was the core dispute between The Liuden LLC and Lenna regarding the renovation of the villa?

The litigation centered on a contractual disagreement arising from a renovation project for a private villa. The Liuden LLC, a construction firm, was engaged by Lenna to perform renovation works, which were subsequently expanded by the Defendant during the project's lifecycle. The dispute escalated when the Defendant terminated the agreement abruptly, leading to a claim for outstanding payments and a counterclaim for alleged poor workmanship.

As noted in the court record:

The underlying dispute arises over a conflict between the parties pursuant to an Agreement dated 24 June 2019 (the “Agreement”), in relation to the renovation of two rooms in the Defendant’s property.

The Claimant sought a total of AED 40,016.75 for work performed, while the Defendant contested this, alleging that the quality of the work was substandard and that she had incurred additional costs to rectify the project. The case highlights the friction often found in residential construction contracts where scope creep and quality expectations collide with formal termination procedures.

Which judge presided over the SCT hearing for The Liuden LLC v Lenna [2020] DIFC SCT 107?

The matter was heard and determined by SCT Judge Maha Al Mehairi. Following an unsuccessful consultation before SCT Judge Delvin Sumo on 28 April 2020, the case proceeded to a formal hearing on 28 June 2020. Judge Al Mehairi issued the final judgment on 20 August 2020, resolving the claims and counterclaims based on the submissions and evidence provided by both parties.

The Claimant, The Liuden LLC, argued that the Defendant had breached the express terms of their agreement by failing to provide the contractually mandated notice period prior to termination. The Claimant maintained that they were entitled to the full outstanding balance of AED 40,016.75, noting that the Defendant had previously acknowledged this liability via messaging.

Conversely, the Defendant, Lenna, argued that the quality of the work was insufficient, justifying her decision to bar the Claimant from the premises. She filed a counterclaim seeking damages for the cost of completing the works, the expense of a third-party "snag and inspect" report totaling AED 2,625.00, and general damages. Her position was that the Claimant’s failure to meet professional standards excused her from further payment and entitled her to compensation for the remedial work required.

What was the precise doctrinal question regarding the breach of the 7-day notice period in The Liuden LLC v Lenna?

The court was tasked with determining whether the Defendant’s unilateral termination of the agreement, without providing the 7-day notice period stipulated in the contract, constituted a breach of contract that precluded her from claiming damages for alleged poor workmanship. The legal issue was whether the Defendant could bypass the contractual rectification mechanism simply by citing dissatisfaction with the work, or if the failure to allow the Claimant to cure the defects rendered the termination wrongful and the counterclaim invalid.

How did Judge Maha Al Mehairi apply the doctrine of contractual notice to the termination of the agreement?

Judge Al Mehairi focused on the procedural requirements set out in the agreement. The court found that the Defendant had failed to adhere to the mandatory notice period, which was intended to provide the contractor with a fair opportunity to rectify any alleged defects before the contract was terminated. By denying this opportunity, the Defendant acted in violation of the agreed terms.

The reasoning is summarized as follows:

On 13 December 2019, the Defendant terminated the Agreement without 7 days’ prior notice, which is the agreed period of time for termination as set out in the Agreement.

The court concluded that because the Defendant did not provide the required notice, she could not subsequently claim damages for the cost of completion or third-party reports. The breach of the notice clause effectively nullified the Defendant's ability to hold the Claimant liable for the alleged deficiencies, as the Claimant was never given the chance to remedy them as required by the contract.

Which statutes and rules were applied by the SCT in The Liuden LLC v Lenna?

The dispute was governed by the DIFC Contract Law No. 6 of 2004. Furthermore, the court relied on the specific terms of the Agreement dated 24 June 2019, specifically Clause 33, which established the exclusive jurisdiction of the DIFC Courts, and Clause 34, which stipulated that the agreement be governed by the laws of the Emirate of Dubai and the UAE. The SCT also operated under its own procedural rules, which govern the conduct of consultations and hearings within the Small Claims Tribunal.

How did the court treat the Defendant’s counterclaim for snagging costs and damages?

The court dismissed the Defendant’s counterclaim in its entirety. By failing to provide the 7-day notice period, the Defendant deprived the Claimant of the contractual right to rectify the works. Consequently, the court found that the Defendant could not recover the costs associated with the third-party snagging report or the costs of completing the works, as these expenses were incurred as a direct result of her own breach of the notice provision. The court determined that the Claimant was entitled to the full amount claimed for the work performed.

What was the final disposition and monetary relief ordered in The Liuden LLC v Lenna?

The SCT ruled in favor of the Claimant, The Liuden LLC. The court ordered the Defendant, Lenna, to pay the full outstanding balance claimed.

As stated in the judgment:

In light of the aforementioned, I find that the Defendant shall pay the Claimant the sum of AED 40,016.75.

Additionally, the court ordered the Defendant to contribute to the legal costs incurred by the Claimant. Specifically:

The Defendant shall pay the Claimant a portion of the Court fee in the sum of AED 2,002.21.

What are the practical implications for construction contractors and clients in the DIFC regarding termination clauses?

This case serves as a reminder that contractual notice periods are not merely administrative formalities but are substantive conditions precedent to valid termination. Practitioners should advise clients that in the absence of strict adherence to notice and rectification clauses, the terminating party risks losing the right to claim damages for defective work. For contractors, the ruling reinforces the protection provided by "right to cure" clauses, ensuring that they cannot be locked out of a site without a fair opportunity to address alleged performance issues.

Where can I read the full judgment in The Liuden LLC v Lenna [2020] DIFC SCT 107?

The full judgment can be accessed via the DIFC Courts website at: https://www.difccourts.ae/rules-decisions/judgments-orders/small-claims-tribunal/the-liuden-llc-v-lenna-2020-difc-sct-107

Cases referred to in this judgment:

Case Citation How used
N/A N/A No external precedents cited in the judgment text.

Legislation referenced:

  • DIFC Contract Law No. 6 of 2004
  • Agreement dated 24 June 2019 (Clause 33, Clause 34)
Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.