Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
uae-difc-cases

Lucina v Lindae Solutions [2020] DIFC SCT 091 — Breach of contract and refund of management fees (23 April 2020)

The dispute centered on the alleged failure of Lindae Solutions to perform obligations under a Pre-Opening Management Service Agreement intended to launch a café concept in Saudi Arabia.

300 wpm
0%
Chunk
Theme
Font

This judgment addresses the boundaries of service delivery in a pre-opening management agreement, specifically clarifying the legal weight of signed completion certificates versus subsequent claims of non-performance in the DIFC Small Claims Tribunal.

What was the nature of the contractual dispute between Lucina and Lindae Solutions regarding the SAR 97,645 claim?

The dispute centered on the alleged failure of Lindae Solutions to perform obligations under a Pre-Opening Management Service Agreement intended to launch a café concept in Saudi Arabia. Lucina, the Claimant, sought a refund of fees paid for services that were allegedly never rendered or performed to an unsatisfactory standard. The core of the disagreement involved the division of project phases and whether the Defendant had fulfilled its contractual duties regarding menu engineering and project management.

As noted in the court record:

The underlying dispute arises over an alleged breach of the Pre-Opening Management Service Agreement (the “Agreement”) signed by the Claimant and the Defendant.

The Claimant argued that while the initial phase was signed off, the subsequent phase—involving menu development and recipe trials—was marred by poor communication and a failure to incorporate specific client feedback. Lucina claimed that despite transferring SAR 39,900 for the second phase, the Defendant failed to provide the promised deliverables, leading to a total claim of AED 97,645.

How did SCT Judge Nassir Al Nasser establish the jurisdiction of the DIFC Small Claims Tribunal in Lucina v Lindae Solutions?

The jurisdictional challenge was addressed by Judge Nassir Al Nasser during the hearing held on 12 April 2020. The court relied on the statutory authority granted by the Judicial Authority Law to determine whether the claim fell within the ambit of the DIFC Courts. The judge confirmed that the existence of a written agreement between the parties provided the necessary nexus for the tribunal to adjudicate the matter.

As stated in the judgment:

Therefore, pursuant to Article (5)(A) of the Judicial Authority Law, Dubai Law No. 12 of 2004, as amended, I am of the view that the DIFC Courts have the authority to hear and determine this claim.

What specific arguments did Lucina and Lindae Solutions advance regarding the performance of the Pre-Opening Management Service Agreement?

Lucina argued that the Defendant failed to meet the requirements of Clause 3 of the Agreement, specifically regarding menu engineering and recipe development. The Claimant contended that he was forced to perform the work himself, such as creating the menu skeleton, because the Defendant was unresponsive and failed to follow instructions. Lucina highlighted a specific incident where he informed the Defendant of his availability for trials in Dubai, only for the Defendant to ignore the schedule and repeat queries that had already been addressed.

Conversely, Lindae Solutions maintained that they had fulfilled their obligations to the extent possible given the Claimant's input. The Defendant argued that they had adjusted their deliverables based on the feedback provided by the Claimant. They pointed to the feasibility study and concept adjustments submitted in September 2019 as evidence of their active participation and adherence to the project scope.

What was the primary doctrinal issue the court had to resolve regarding the completion of project phases?

The court was tasked with determining whether a party can retroactively claim a breach of contract for a project phase that has already been formally signed off as "completed." The legal question was whether the Claimant’s email confirmation and signed completion certificate for Phase 1 precluded him from later seeking a refund for that phase, even if he later alleged that the work was not fully executed as originally envisioned. This required the court to balance the sanctity of signed contractual milestones against the Claimant's assertion that the work was "postponed" rather than finalized.

How did Judge Nassir Al Nasser apply the doctrine of contractual acceptance to the Phase 1 deliverables?

The judge applied a strict interpretation of the parties' prior conduct and written acknowledgments. He found that because the Claimant had explicitly signed a completion certificate and confirmed via email that the services for Phase 1 were accepted, he could not later claim a refund for that portion of the work. The judge emphasized that the Claimant’s own documentation served as a bar to his claim for the first phase.

As the judgment explains:

as per the completion Certificate signed, and as per the above email within which the Claimant acknowledges the services completed in respect of phase 1, and following the Claimant’s termination of th

Regarding Phase 2, however, the judge found that the Defendant’s failure to incorporate feedback and their inability to provide the agreed-upon services constituted a material breach. The judge noted:

Due to the miscommunication between the parties and the Defendant’s failure to fulfil the Claimant’s request in relation to phase 2, I find that the Defendant is liable to pay the Claimant a refund in

Which specific statutes and rules did the court rely upon to reach its decision?

The court primarily relied on Article 5(A) of the Judicial Authority Law, Dubai Law No. 12 of 2004 (as amended), to establish its jurisdiction. The court also referenced the specific clauses of the Pre-Opening Management Service Agreement, particularly Clause 3, which defined the scope of work for the various phases, and Clause 4.1, which governed the payment schedule. The court’s analysis was grounded in the contractual obligations defined by these clauses and the evidentiary weight of the correspondence exchanged between the parties.

How did the court treat the evidence of the "menu skeleton" and the draft menu in determining the breach of Phase 2?

The court treated the evidence of the menu skeleton as proof of the Defendant's failure to provide the professional services contracted for. By reviewing the timeline—specifically the Claimant’s submission of the menu skeleton on 16 September 2019 and the Defendant’s subsequent draft on 5 January 2020—the judge determined that the Defendant had not met the professional standard required by the Agreement. The court viewed the Defendant’s failure to respond to the Claimant’s comments on the draft menu as a failure to fulfill the "menu engineering" obligations stipulated in Clause 3.1(d) through (g).

What was the final disposition and the specific monetary relief ordered by the Small Claims Tribunal?

The court partially allowed the claim. It ordered the Defendant, Lindae Solutions, to refund the Claimant the sum of SAR 39,900, which corresponded to the payment made for the unfulfilled Phase 2 of the project. The Claimant’s other claims, specifically those related to Phase 1, were dismissed. Additionally, the court ordered the Defendant to pay the Claimant the court fee in the sum of AED 1,995.

How does this ruling impact the management of service agreements for practitioners in the DIFC?

This case serves as a reminder of the binding nature of project sign-offs. Practitioners must advise clients that signing a completion certificate or acknowledging work via email effectively waives the right to claim a refund for that specific phase, regardless of later regrets or allegations of "postponement." Furthermore, the case highlights that in service agreements, "poor communication" and failure to incorporate client feedback can be successfully argued as a breach of contract, provided the claimant can document the specific instructions given and the subsequent failure of the service provider to adhere to those instructions.

Where can I read the full judgment in Lucina v Lindae Solutions [2020] DIFC SCT 091?

The full judgment is available on the DIFC Courts website: https://www.difccourts.ae/rules-decisions/judgments-orders/small-claims-tribunal/lucina-v-lindae-solutions-2020-difc-sct-091

Legislation referenced:

  • Judicial Authority Law, Dubai Law No. 12 of 2004, as amended, Article 5(A)
Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.