Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
uae-difc-cases

RADA TRADING LLC FZC v ARYA PETROLEUM FZE [2020] DIFC CFI 112 — Breach of storage lease and demurrage liability (29 April 2022)

The lawsuit centered on a Storage Lease Agreement for an oil tank in the Hamriyah Free Zone. The Claimant, RADA TRADING LLC FZC ("RaDa"), sought significant damages from the Defendant, ARYA PETROLEUM FZE ("Arya"), alleging that Arya breached the contract by failing to provide the designated storage…

300 wpm
0%
Chunk
Theme
Font

The DIFC Court of First Instance clarifies the limits of consequential loss recovery in oil storage disputes, ruling that a proven breach of contract does not guarantee damages when external factors, such as port congestion, serve as the primary cause of delay.

What were the specific claims and the total monetary stakes in the dispute between RADA TRADING LLC FZC and ARYA PETROLEUM FZE in [2020] DIFC CFI 112?

The lawsuit centered on a Storage Lease Agreement for an oil tank in the Hamriyah Free Zone. The Claimant, RADA TRADING LLC FZC ("RaDa"), sought significant damages from the Defendant, ARYA PETROLEUM FZE ("Arya"), alleging that Arya breached the contract by failing to provide the designated storage tank (Tank No ST-06) by the agreed start date of 30 August 2020. As a result of this unavailability, RaDa’s vessel, the M/T PV OIL JUPITER, was unable to discharge its cargo of Fuel Oil 380 CST, leading to substantial financial losses.

RaDa claimed US$239,367 in demurrage payments made to its sellers, alongside additional claims for loss of profit resulting from the delay. Conversely, Arya brought a counterclaim for unpaid rent under the Agreement. The dispute effectively became a battle over whether the Defendant’s failure to clear the tank constituted the proximate cause of the vessel's berthing delays, or whether those delays were inevitable due to broader port congestion. The court ultimately resolved the counterclaim in favor of the Defendant, ordering the Claimant to pay AED 220,901. As noted in the judgment:

The Defendant’s counterclaim succeeds to the extent that the Claimant must pay the Defendant the sum of AED 220,901, plus interest thereon at the rate of 9% a year from the date of this Order.

[Source: https://www.difccourts.ae/rules-decisions/judgments-orders/court-first-instance/rada-trading-llc-fzc-v-arya-petroleum-fze-2020-difc-cfi-112]

Which judge presided over the trial of RADA TRADING LLC FZC v ARYA PETROLEUM FZE in the DIFC Court of First Instance?

The trial was presided over by Justice Lord Angus Glennie in the DIFC Court of First Instance. The hearing took place on 23 and 24 February 2022, with the final judgment issued on 29 April 2022.

Stephen Stamboulieh, representing RaDa, argued that Arya was in clear breach of the Agreement by failing to provide the facility as promised. He contended that the unavailability of the tank directly prevented the M/T PV OIL JUPITER from discharging its cargo, thereby triggering the demurrage liability RaDa owed to its suppliers. The Claimant’s position was that the breach was the operative cause of the financial losses incurred during the period the vessel sat idle at the port.

Asha Bejoy, representing Arya, countered that while there may have been a delay in the tank’s availability, the vessel’s inability to berth was primarily caused by severe port congestion and the presence of other vessels, rather than the specific status of the tank. Arya argued that even if the tank had been cleared on time, the vessel would still have faced significant berthing delays. Furthermore, Arya maintained its counterclaim for unpaid rent, asserting that RaDa remained contractually obligated to pay for the facility regardless of the alleged breach, as the contract terms were clear regarding the nature of the service provided.

The court was tasked with determining whether the Defendant’s breach of contract—specifically the failure to provide the storage tank by the agreed date—was the effective cause of the Claimant's losses. The doctrinal issue was whether the Claimant could satisfy the burden of proof for causation in a claim for consequential damages (demurrage and lost profits) when the evidence suggested that the vessel would have been delayed regardless of the breach due to external port conditions. The court had to decide if the "but for" test for causation was met, or if the port congestion constituted an intervening factor that severed the link between the Defendant’s breach and the specific financial harm claimed by the Claimant.

How did Justice Lord Angus Glennie apply the test of causation to the evidence presented in RADA TRADING LLC FZC v ARYA PETROLEUM FZE?

Justice Glennie applied a strict causation analysis, examining whether the Claimant could prove that the vessel would have berthed earlier had the tank been available. Upon reviewing the evidence, the court found that the port was experiencing significant congestion and that other vessels were also waiting. The judge concluded that the Claimant’s evidence was insufficient to establish that the breach was the decisive factor in the delay.

The judge noted that while the Defendant was indeed in breach of the Agreement, the Claimant failed to demonstrate that this breach was the "but for" cause of the demurrage. The court found that the vessel's delay was largely attributable to the port's operational constraints. As stated in the judgment:

I have no reason to suppose that the M/T PV OIL JUPITER would have berthed any sooner had the tank been clear of cargo and available to RaDa in accordance with the Agreement.

The court also scrutinized the credibility of the witnesses, noting that the Claimant's representative, Mr. Animesh, tended to exaggerate the warnings given regarding the port risks, further undermining the Claimant's narrative of causation.

Which specific provisions of the Storage Lease Agreement and DIFC laws were central to the court's interpretation of the parties' obligations?

The court focused heavily on the definitions provided in Section 1 of the Agreement, which clarified that the "Lease Rent" was actually a fee for "handling, management and dealing with liquid storage" rather than a traditional lease of real property. This distinction was critical in determining the nature of the Defendant's obligations. The court also referenced the following:

  • Section 2 (Lease Period): Defined the start date of 30 August 2020 and the duration of the service.
  • Section 3 (Facility Charges): Established the payment terms of US$5,700 per cubic metre per month.
  • The court also relied on general principles of contract law regarding the assessment of damages and the burden of proof required to recover consequential losses.

How did the court utilize the evidence of discussions between the parties to interpret the Agreement?

The court looked to the pre-contractual discussions to contextualize the parties' understanding of the risks associated with the port. Justice Glennie emphasized that understanding the context of the Agreement was necessary to interpret the parties' intentions regarding the tank's availability. As noted in the judgment:

Accordingly, it is necessary to look briefly at the discussions between the parties at the time the Agreement was concluded.

The court specifically analyzed a discussion that took place on 25 August 2020. The judge accepted that the Defendant had warned the Claimant about potential delays in the tank becoming available, which served to mitigate the Claimant's argument that they were blindsided by the unavailability of the facility. This evidence was used to demonstrate that the Claimant was aware of the operational risks inherent in the port environment at the time they entered into the Agreement.

What was the final disposition of the case and the specific relief granted to the parties?

The court dismissed the Claimant's claim in its entirety, finding that while a breach occurred, the Claimant failed to prove that the breach caused the claimed damages. The Defendant’s counterclaim was successful, resulting in a monetary award for unpaid rent. The court ordered:

The Defendant’s counterclaim succeeds to the extent that the Claimant must pay to the Defendant the sum of AED 220,901 plus interest on that sum at the rate of 9% a year from the date of this order.

Additionally, the court ordered the Claimant to bear the legal costs of the action. As specified in the order:

The Claimant must pay the Defendant’s costs of the action, to be assessed by the Registrar on the standard basis if not agreed.

What are the wider implications of this judgment for practitioners handling oil trading and storage disputes in the DIFC?

This judgment serves as a cautionary tale for practitioners regarding the difficulty of recovering consequential damages in commercial disputes involving complex logistics. It underscores that even when a clear breach of contract is established, the Claimant faces a high evidentiary burden to prove that the breach was the proximate cause of the loss. In sectors like oil trading, where external factors such as port congestion, vessel scheduling, and third-party delays are common, litigants must be prepared to provide robust evidence that the loss would not have occurred "but for" the specific breach. Practitioners should advise clients that the existence of a breach does not automatically entitle them to recover demurrage or lost profits if the defendant can show that the loss was inevitable due to market or operational conditions beyond their control.

Where can I read the full judgment in RADA TRADING LLC FZC v ARYA PETROLEUM FZE [2020] DIFC CFI 112?

The full judgment is available on the official DIFC Courts website: https://www.difccourts.ae/rules-decisions/judgments-orders/court-first-instance/rada-trading-llc-fzc-v-arya-petroleum-fze-2020-difc-cfi-112

Cases referred to in this judgment:

Case Citation How used
N/A N/A No external case law was cited in the final judgment.

Legislation referenced:

  • Storage Lease Agreement (Sections 1, 2, and 3)
  • DIFC Court Rules (RDC) regarding costs and assessment by the Registrar
Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.