Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
uae-difc-cases

NS INVESTMENTS v AJAY SETHI [2025] DIFC CFI 055 — Interim costs payment order (07 February 2025)

The underlying litigation, initiated by a Part 7 Claim in June 2020, reached a critical juncture regarding the recovery of legal fees incurred by the Defendant, Ajay Sethi. Following the conclusion of the substantive proceedings and subsequent failed appeals by the Claimant, NS Investments, the…

300 wpm
0%
Chunk
Theme
Font

The DIFC Court of First Instance has issued a decisive order compelling the Claimant to pay USD 445,450.00 in interim legal costs, underscoring the Court's intolerance for procedural delays following a successful defense.

What was the specific nature of the dispute in NS Investments v Ajay Sethi and the amount at stake in the Costs Application?

The underlying litigation, initiated by a Part 7 Claim in June 2020, reached a critical juncture regarding the recovery of legal fees incurred by the Defendant, Ajay Sethi. Following the conclusion of the substantive proceedings and subsequent failed appeals by the Claimant, NS Investments, the Defendant sought an order to recover a portion of the legal fees paid to his counsel, M.B. Kemp LLP. The dispute centered on the Claimant’s refusal to settle these costs amicably, necessitating formal judicial intervention.

As detailed in the Court’s order:

The Defendant of the Part 7 Claim has submitted this Costs Application seeking an order for the Claimant of the Part 7 Claim to pay 50% of the Defendant’s costs on account within 7 days of issue of the sought order, pursuant to Rule 38.14 of the Rules of the DIFC Courts (the “RDC”).

The amount at stake was significant, totaling USD 445,450.00, which represented exactly half of the total legal fees submitted by the Defendant’s legal representatives. The Court viewed this as a necessary step to ensure the successful party was not unfairly burdened by the Claimant's refusal to engage in reasonable settlement discussions.

Which judge presided over the Costs Application in CFI 055/2020 and in which division of the DIFC Courts was it heard?

The Costs Application was heard by H.E. Deputy Chief Justice Ali Al Madhani, sitting in the DIFC Court of First Instance. The order was issued on 7 February 2025, following the Defendant’s application filed on 12 December 2024. This decision follows a series of previous rulings in the same case, including the original judgment of 27 September 2023 and subsequent refusals of the Claimant's appeal notices by both H.E. Deputy Chief Justice Ali Al Madhani and H.E. Chief Justice Zaki Azmi.

The Defendant, Ajay Sethi, argued that he was the prevailing party in every application throughout the proceedings, including those heard at the Court of Appeal level. His counsel emphasized that the Claimant had been obstructive, refusing multiple attempts to reach an amicable resolution regarding the payment of costs in August and September 2024. The Defendant relied on the witness statement of Salah Mattoo to demonstrate these failed efforts.

As noted in the Court's reasoning:

In support of engaging RDC 38, the Defendant submits that as it has been successful in every application within these proceedings up to and including in the Court of Appeal, and it is the entitled party in proceedings, and the Claimant has failed to cover the costs as directed, the Court should permit the Costs Application.

The Claimant, NS Investments, offered no successful rebuttal to these points, leading the Court to conclude that the Claimant had facilitated unnecessary delay. The Defendant’s position was that the interim payment was not only justified by his success on the merits but also by the Claimant’s conduct in avoiding payment obligations.

The Court was tasked with determining whether it was appropriate to exercise its discretionary power under RDC 38.14 to order an interim payment of costs before a final assessment had taken place. The doctrinal issue was whether the Defendant had sufficiently demonstrated that the quantum sought—USD 445,450.00—was fair, reasonable, and proportionate, and whether the Claimant’s conduct warranted such an order prior to the final taxation or agreement of the total costs.

How did H.E. Deputy Chief Justice Ali Al Madhani apply the test for interim costs payments?

The Court applied a two-fold test: first, confirming the procedural authority to order costs on account, and second, evaluating the proportionality of the requested amount. The judge noted that the Claimant’s refusal to engage in amicable resolution necessitated the application.

Regarding the Court's authority, the judge stated:

It is also within the Court’s power to order costs on account to be paid before assessment, as per RDC 38.14, on which the Defendant relies.

The judge further reasoned that the breakdown of fees provided by M.B. Kemp LLP was consistent with the complexity of the case, the number of applications defended, and standard market rates for legal counsel. By finding that the Claimant had facilitated "unnecessary delay," the Court justified the 50% interim payment as a proportionate measure to protect the successful party's interests.

The primary authority for the order was Rule 38.14 of the Rules of the DIFC Courts (RDC), which grants the Court the discretion to order an amount to be paid on account before costs are formally assessed. The Court also relied on the evidentiary support provided by the witness statement of Salah Mattoo, which documented the Claimant's refusal to settle costs in August and September 2024.

How did the Court utilize the precedent set in China State Construction Engineering Corporation (Middle East) et al [2024] CA 009 2024?

The Court cited China State Construction Engineering Corporation (Middle East) et al [2024] CA 009 2024 to establish the standard for assessing the quantum of legal fees. H.E. Deputy Chief Justice Ali Al Madhani utilized this precedent to confirm that the fees sought were "fair, reasonable and proportionate." Specifically, the Court adopted the principle that quantum amounts must be balanced against the work performed for the relevant applications and the overall case processes, ensuring that the interim payment did not exceed what would likely be awarded upon final assessment.

What was the final disposition of the Costs Application and the specific relief granted to Ajay Sethi?

The Court granted the Costs Application in its entirety. The order mandated that the Claimant pay 50% of the Defendant’s legal costs on account within 7 days of the order's issuance.

As specified in the order:

Therefore, I order that the Claimant in the Claim must pay 50% of the Defendant's costs on account within 7 days from the date of issue of this Order, amounting to USD 445,450.00 only, pursuant to RDC 38.14 by way of interim payment.

Additionally, the Court ordered that the Claimant pay the costs of the Costs Application itself, to be assessed by the Registrar if the parties could not reach an agreement.

What are the wider implications of this ruling for DIFC practitioners regarding interim costs?

This decision reinforces the DIFC Court’s proactive stance in ensuring that successful parties are not kept out of pocket due to the dilatory tactics of an unsuccessful opponent. Practitioners should note that the Court is increasingly willing to utilize RDC 38.14 to compel interim payments when there is clear evidence of a refusal to engage in amicable settlement discussions. Litigants must anticipate that failure to cooperate on costs post-judgment will likely result in an adverse order for interim payment, potentially including the costs of the application itself.

Where can I read the full judgment in NS Investments Ltd v Ajay Sethi [2025] DIFC CFI 055?

The full order can be accessed via the official DIFC Courts website: https://www.difccourts.ae/rules-decisions/judgments-orders/court-first-instance/cfi-0552020-ns-investments-ltd-v-ajay-sethi-2. The text is also available via the CDN link: https://littdb.sfo2.cdn.digitaloceanspaces.com/litt/AE/DIFC/judgments/court-first-instance/DIFC_CFI-055-2020_20250207.txt.

Cases referred to in this judgment:

Case Citation How used
China State Construction Engineering Corporation (Middle East) et al [2024] CA 009 2024 Used to establish the standard for proportionality and reasonableness of legal fee quantum.

Legislation referenced:

  • Rules of the DIFC Courts (RDC) — Rule 38.14
Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.