Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
uae-difc-cases

DAS REAL ESTATE v NATIONAL BANK OF ABU DHABI [2016] DIFC CFI 002 — Mandatory injunctions and facility agreement enforcement (08 February 2016)

The litigation arises from a long-standing commercial relationship between the Claimant, DAS Real Estate (owned by Mr. Mussabeh Salem Mussabeh Humaid Al Muhairi), and the Defendant, National Bank of Abu Dhabi (NBAD).

300 wpm
0%
Chunk
Theme
Font

The DIFC Court of First Instance addresses the high threshold for interim mandatory injunctive relief in the context of a complex real estate facility agreement, emphasizing the necessity of demonstrating a strong case on the merits when seeking to compel a bank to release funds.

What was the nature of the dispute between DAS Real Estate and National Bank of Abu Dhabi regarding the AED 225 million facility?

The litigation arises from a long-standing commercial relationship between the Claimant, DAS Real Estate (owned by Mr. Mussabeh Salem Mussabeh Humaid Al Muhairi), and the Defendant, National Bank of Abu Dhabi (NBAD). The core of the dispute concerns a 2008 facility agreement originally valued at AED 708 million, intended for the construction of a hotel project on the Palm Jumeirah. Over several years, the agreement underwent multiple amendments, including a 2010 revival and a 2014 restructuring.

The immediate controversy involves the Claimant's attempt to secure an interim mandatory injunction to force the bank to release the remaining balance of "Facility B," a component of the restated agreement worth AED 225 million. The Claimant sought to use these funds to continue construction, while simultaneously requesting a prohibitory injunction to prevent the bank from enforcing its mortgage security following a "Legal Warning" issued by the bank in January 2016. As noted in the court's schedule of reasons:

The dispute goes back predictably to a contract dated 2008 whereby the Claimant entered into a facility agreement with the Defendant for the provision of funding totalling AED 708 million.

The Claimant’s request for relief was driven by the bank's refusal to allow further drawdowns, citing the Claimant's failure to meet specific conditions subsequent. For further context on the procedural history of this dispute, see DAS REAL ESTATE v FIRST ABU DHABI BANK [2017] DIFC CA 002 — Permission to appeal granted (07 November 2017).

Which judge presided over the CFI 002/2016 application and when was the order issued?

The application was heard by Justice Sir David Steel in the DIFC Court of First Instance. The hearing took place on 2 February 2016, and the formal order, which refused the Claimant's application for injunctive relief, was issued on 8 February 2016.

The Claimant argued that the bank was contractually obligated to release the funds under Facility B and that the bank’s refusal to do so threatened the viability of the hotel project. They sought a mandatory injunction to compel the release of funds and a prohibitory injunction to halt mortgage enforcement proceedings.

The Defendant, NBAD, countered by asserting that the Claimant had failed to satisfy the "conditions subsequent" stipulated in the Amended and Restated Agreement dated 28 September 2014. The bank argued that this failure constituted an Event of Default, thereby justifying their refusal to release further funds and their subsequent move to enforce security. The bank also raised jurisdictional challenges, suggesting that the court lacked the power to grant a mandatory injunction in these circumstances. As the court noted regarding the bank's position:

What has to be set importantly at the outset is that one of the major complaints raised by the Defendant is that there was no compliance with the conditions subsequent let alone before the deadline of 30 February 2014.

What was the specific doctrinal question the court had to answer regarding the grant of mandatory injunctions and in personam jurisdiction?

The court was required to determine whether the Claimant had established a sufficiently "strong case" to justify the extraordinary remedy of a mandatory injunction. Beyond the merits of the construction project, the court had to address the Defendant's jurisdictional challenge. The bank contended that the court lacked the authority to grant a mandatory injunction because there was no in personam jurisdiction over the Defendant in the context of the specific relief sought. Furthermore, the court had to decide whether the Claimant’s request for a stay of enforcement proceedings was procedurally sound, or if it should have been pursued through the specific mechanisms provided under the relevant mortgage law.

How did Justice Sir David Steel apply the test for mandatory injunctive relief to the facts of the DAS Real Estate application?

Justice Sir David Steel applied a rigorous standard to the Claimant's request, emphasizing that mandatory injunctions are not granted lightly. The court found that the Claimant failed to demonstrate a strong case on the merits, particularly given the clear evidence of non-compliance with the conditions subsequent required for the drawdown of Facility B.

The judge highlighted that the court must be fully satisfied of the merits before interfering with the contractual rights of a lender. Furthermore, the court determined that damages would be an adequate remedy if the Claimant were ultimately successful at trial, thereby negating the need for interim injunctive relief. Regarding the necessity of caution, the court stated:

This emphasises the need for where there is an application for a mandatory injunction for the court to be reluctant to grant any such relief unless it is fully satisfied that the chances of the court "

The court referenced the Amended and Restated Agreement dated 28 September 2014, specifically Clause 5.3, which governed "conditions subsequent." The court also considered the implications of Law 16 of 2004 (the DIFC Law) regarding the court's jurisdiction. The Defendant’s jurisdictional arguments were addressed by reference to the exclusive jurisdiction clause contained within the facility agreement. Additionally, the court relied on the principles established in National Commercial Bank Jamaica v Olint to evaluate the appropriateness of the requested injunctions.

How did the court address the jurisdictional arguments raised by the Defendant?

The court rejected the Defendant’s argument that it lacked in personam jurisdiction to grant the requested relief. Justice Sir David Steel clarified that the presence of an exclusive jurisdiction clause in the facility agreement provided a clear basis for the court to exercise its authority over the parties. The court dismissed the notion that the absence of such jurisdiction could be used to shield the bank from the court's oversight in this dispute. As the court noted:

This in my judgment is a complete misapprehension given the exclusive jurisdiction clause that we have in this agreement whereby the parties have agreed to accord exclusive jurisdiction to this court.

What was the final disposition of the application and the court's order regarding costs?

The court refused the Claimant's application for both mandatory and prohibitory injunctions. Consequently, the bank remained free to proceed with its enforcement actions under the mortgage. The Claimant was ordered to pay 80 percent of the Defendant's costs of the application, to be assessed by the Registrar if not agreed upon by the parties. Furthermore, the court explicitly refused the Claimant permission to appeal the order.

What are the wider implications of this decision for practitioners handling facility agreement disputes in the DIFC?

This decision reinforces the high threshold required to obtain mandatory injunctive relief in the DIFC Courts. Practitioners must anticipate that the court will be highly reluctant to interfere with a bank's decision to withhold funding if there is a colorable argument that "conditions subsequent" have not been met. The case serves as a reminder that the court will prioritize contractual compliance and the adequacy of damages as a remedy over the granting of interim relief. Litigants should be prepared to demonstrate a "strong case" rather than merely a "serious issue to be tried" when seeking to compel performance under a facility agreement.

Where can I read the full judgment in DAS Real Estate v National Bank of Abu Dhabi [2016] DIFC CFI 002?

The full judgment is available on the DIFC Courts website: https://www.difccourts.ae/rules-decisions/judgments-orders/court-first-instance/cfi-0022016-das-real-estate-owned-and-represented-mussabeh-salem-mussabeh-humaid-al-muhairi-v-national-bank-abu-dhabi-pjsc or via the CDN link: https://littdb.sfo2.cdn.digitaloceanspaces.com/litt/AE/DIFC/judgments/court-first-instance/DIFC_CFI-002-2016_20160208.txt

Cases referred to in this judgment:

Case Citation How used
National Commercial Bank Jamaica v Olint [2009] UKPC 16 Applied for principles governing interim injunctions

Legislation referenced:

  • Law 16 of 2004 (DIFC Law)
  • Amended and Restated Agreement (28 September 2014)
  • Facility Agreement (2008, as amended)
Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.