Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
uae-difc-cases

DIFC Investments v Mohammed Akbar Mohammed Zia [2017] DIFC CFI 001 — Declaration of contract termination for non-performance (15 May 2017)

The dispute arose from the failed sale of 72 residential units in the "Newbridge Hill 2" development located in Motor City, Dubai. The Claimant, DIFC Investments LLC, entered into 72 substantively identical contracts with the Defendant, Mohammed Akbar Mohammed Zia, on 3 May 2015.

300 wpm
0%
Chunk
Theme
Font

The Court of First Instance confirms the validity of contract termination under DIFC Law for non-payment in a high-value real estate dispute, affirming the suitability of Part 8 proceedings where no substantial factual dispute exists.

What was the nature of the dispute between DIFC Investments and Mohammed Akbar Mohammed Zia regarding the AED 105,134,400 property contracts?

The dispute arose from the failed sale of 72 residential units in the "Newbridge Hill 2" development located in Motor City, Dubai. The Claimant, DIFC Investments LLC, entered into 72 substantively identical contracts with the Defendant, Mohammed Akbar Mohammed Zia, on 3 May 2015. The total purchase price for these units was AED 105,134,400. Under the terms of the agreements, the Defendant was required to provide a 10% security deposit and arrange for an irrevocable Stand By Letter of Credit (SBLC) to cover the total purchase price.

The Claimant alleged that the Defendant failed to fulfill these payment obligations, leading to the purported termination of the contracts on 8 July 2015. The Defendant contested this, asserting that he had made significant efforts to perform his obligations and that the matter was too complex for summary determination. As noted in the court record:

The Defendant seeks dismissal of the Claim under Part 8 as there is a substantial dispute regarding the facts of the case, an award of damages to the Defendant for the filing of frivolous proceedings before the DIFC Courts and deliberately concealing information relevant to the case, an award of all legal costs and expenses incurred by the Defendant in defending this claim and an award for any other relief that the Court shall deem fit.

The Claimant sought a formal declaration from the Court to confirm the termination of these agreements. The case can be reviewed at the DIFC Courts website.

Which judge presided over the DIFC Investments v Mohammed Akbar Mohammed Zia hearing in the Court of First Instance?

The matter was heard before H.E. Justice Omar Al Muhairi in the DIFC Court of First Instance. The hearing took place on 17 April 2017, with the final judgment issued on 15 May 2017.

The Claimant, represented by Sharon Lakhan of Global Advocacy and Legal Counsel, argued that the DIFC Courts held jurisdiction under Article 5(A)(1)(a) of the Judicial Authority Law because the Claimant is a DIFC Establishment. The Claimant maintained that the Defendant’s failure to provide the required SBLC and security deposit constituted clear non-performance under the DIFC Contract Law, justifying the termination of the 72 contracts.

The Defendant, represented by Syed Mujtaba Hussain of Emirates Legal FZE, argued that the case involved substantial factual disputes regarding his efforts to secure payment, which necessitated a full trial under Part 7 of the Rules of the DIFC Courts (RDC) rather than the summary Part 8 procedure. Furthermore, the Defendant challenged the court's jurisdiction, suggesting that because the underlying property was located in Motor City (outside the DIFC), the court might lack the authority to adjudicate the matter. The Defendant also attempted to frame the issue as a lack of "fault" rather than "non-performance."

The central legal question was whether the Defendant’s failure to pay the purchase price constituted "non-performance" sufficient to trigger the termination clauses of the contracts under the DIFC Contract Law. The court had to decide if the terminology of "breach" was the correct standard or if the statutory language of "non-performance" governed the outcome. As the court clarified:

The Defendant argues that “mere non-performance without any fault on part of the Defendant does not amount to a ‘breach’ within the meaning of the DIFC Contract Law” however, the DIFC Contract Law is written in terms of “non-performance” rather than “breach.” There is no need to determine whether there is a breach, only whether there is non-performance as defined by Article 77.

How did H.E. Justice Omar Al Muhairi apply the test for the appropriateness of Part 8 proceedings in this dispute?

Justice Al Muhairi evaluated whether the Defendant’s claims of "efforts to pay" created a "substantial dispute of fact" that would preclude the use of the Part 8 procedure. Under the RDC, Part 8 is reserved for cases where there is no substantial dispute of fact. The judge determined that the Defendant’s arguments did not meet this threshold, as the failure to pay the purchase price was an objective, undisputed fact.

As to the issue of the appropriate use of Part 8, the Court ruled that the Claimant need not file under Part 7 as there is no substantial dispute of fact relevant to this specific Claim.

The court further addressed the procedural mechanics of the claim, noting that the Defendant had failed to utilize the available mechanisms to challenge the Claimant's position formally.

RDC 8.37 states that “Where Part 8 procedure is used, Part 21 (counterclaims and other additional claims) applies except that a party may not make an additional claim (as defined by Rule 21.2) without the Court’s permission.” The Defendant is therefore not prevented from bringing a Counterclaim in a Part 8 Claim and has not attempted to do so.

Which specific DIFC statutes and RDC rules were applied to resolve the dispute?

The court relied heavily on the DIFC Contract Law No. 6 of 2004, specifically Articles 77, 80, 81, 82, 83, 86, 87, and 89, to define the parameters of non-performance and the right to terminate. Jurisdiction was established under Article 5(A)(1)(a) of the Judicial Authority Law (DIFC Law No. 12 of 2004). Procedurally, the court applied RDC 8.4, 8.6(1), and 8.37 to validate the use of the Part 8 claim form. Additionally, the court referenced DIFC Law No. 7 of 2005 (Article 37) regarding the application of DIFC laws to the contracts.

How did the court utilize the cited authorities to determine the governing law and the validity of the termination?

The court utilized the "DIFC Law Relating to the Application of DIFC Laws" in conjunction with Clause 17 of the contracts to confirm that DIFC Law was the exclusive governing law, regardless of the physical location of the property in Motor City. By applying Article 77 of the DIFC Contract Law, the court bypassed the Defendant's attempt to introduce a "fault" requirement, focusing instead on the objective failure to perform the payment obligations. This allowed the court to conclude that the contracts were validly terminated as of 8 July 2015.

The court granted the Claimant’s request in full. It issued a formal declaration that the 72 contracts were terminated effective 8 July 2015.

The 72 Contracts executed by the Claimant and the Defendant dated 3 May 2015 were terminated with effect from 8 July 2015 pursuant to the DIFC Contract Law.

The court also ordered the Defendant to pay the Claimant’s legal costs. The parties were instructed to furnish details of their costs and written submissions within 21 days of the judgment if they could not reach an agreement on the quantum.

What are the wider implications of this judgment for practitioners filing Part 8 claims in the DIFC?

This judgment serves as a critical reminder that the DIFC Courts will strictly enforce the distinction between "non-performance" and "breach" as defined by the DIFC Contract Law, prioritizing the former in contractual disputes. It also clarifies that parties cannot defeat a Part 8 claim simply by asserting that a "substantial dispute of fact" exists; the dispute must be genuine and relevant to the core legal issues. Furthermore, the case reinforces that the DIFC Courts will uphold their jurisdiction over contracts where the parties have explicitly chosen DIFC Law, even if the subject matter (such as real estate) is located outside the DIFC jurisdiction.

Where can I read the full judgment in DIFC Investments v Mohammed Akbar Mohammed Zia [2017] DIFC CFI 001?

The full judgment is available on the DIFC Courts website: https://www.difccourts.ae/rules-decisions/judgments-orders/court-first-instance/difc-investments-llc-v-mohammed-akbar-mohammed-zia-2017-difc-cfi-001.
The document can also be accessed via the CDN: https://littdb.sfo2.cdn.digitaloceanspaces.com/litt/AE/DIFC/judgments/court-first-instance/DIFC_CFI-001-2017_20170515.txt.

Legislation referenced:

  • DIFC Contract Law No. 6 of 2004 (Articles 77, 80, 81, 82, 83, 86, 87, 89)
  • DIFC Law No. 10 of 2005
  • DIFC Law No. 3 of 2004
  • DIFC Law No. 7 of 2005 (Article 37)
  • Judicial Authority Law (DIFC Law No. 12 of 2004) (Article 5(A)(1)(a))
  • Rules of the DIFC Courts (RDC 8.4, 8.6(1), 8.37, Part 21)
Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.