"The plaintiff was thus entitled to damages amounting to $720,960.84 with interest at the usual rate of 5.33% from the date of the OS to judgment." — Per See Kee Oon J, Para 71
Case Information
- Citation: [2023] SGHC 1 (Para heading)
- Court: General Division of the High Court of the Republic of Singapore (Para heading)
- Date of judgment: 3 January 2023 (Para heading)
- Hearing dates: 19 July and 27 October 2022 (Para heading)
- Coram: See Kee Oon J (Para heading)
- Case number: Originating Summons No 1092 of 2021 (Para heading)
- Area of law: Damages — Assessment (Para heading)
- Counsel for the plaintiff: Ng Hui Min and Mok Zi Cong (Dentons Rodyk & Davidson LLP) (Para heading)
- Counsel for the defendant: Kishan Pratap and Jasmine Yan (Kishan Law Chambers LLC) (Para heading)
- Judgment length: Not answerable from the extraction (not stated in the provided material)
What Was This Damages Assessment About?
This judgment concerned the assessment of damages arising from a failed sale and purchase of a condominium unit, together with the defendant’s continued occupation of the property after the contractual relationship had broken down. The court made clear that the hearing before it was confined to damages assessment, following an earlier declaration that the sale and purchase agreement had been validly terminated. The dispute therefore turned not on liability in the abstract, but on the proper quantification of the plaintiff’s recoverable losses under the SPA and related contractual conditions. (Para 1) (Para 2) (Para 3)
"The hearing before me was concerned solely with the issue of how damages were to be assessed (“the AD hearing”)." — Per See Kee Oon J, Para 2
The court ultimately accepted most of the plaintiff’s heads of claim, including legal costs, reinstatement costs, financing-related losses, and certain unnecessary expenses, but it rejected the plaintiff’s attempt to recover Wrotham Park damages as part of the delayed-sale claim. The result was a substantial award of damages, but one that was carefully trimmed where the court considered the plaintiff had not satisfied the requirements for the exceptional remedy it sought. (Para 3) (Para 50) (Para 71)
"I assessed that the plaintiff was entitled to damages amounting to $720,960.84." — Per See Kee Oon J, Para 3
In practical terms, the case is a detailed example of how Singapore courts approach contractual damages in a property transaction where completion fails, possession continues, and the seller incurs a range of downstream costs. It also shows the court’s willingness to enforce clear contractual indemnity language, while insisting on proof and legal justification for each item claimed. (Para 27) (Para 28) (Para 64) (Para 68)
How Did the Dispute Arise and What Were the Key Facts?
The dispute arose from a sale and purchase agreement dated 2 July 2018 between the plaintiff and the defendant concerning a condominium unit at 105 Prince Charles Crescent, The Crest, Singapore 159019. Completion was scheduled for 4 June 2020 under cl 1 of the SPA, but the defendant did not complete as required. The chronology matters because the court’s damages analysis depended on the contractual timetable, the extensions that were granted, and the period during which the defendant remained in possession. (Para 1) (Para 6)
"The plaintiff’s claim in HC/OS 1092/2021 (“the OS”) was brought in relation to a sale and purchase agreement dated 2 July 2018 (“the SPA”) that was entered into between the parties in respect of a condominium unit (“the Property”) at 105 Prince Charles Crescent, The Crest, Singapore 159019 (“the Development”)." — Per See Kee Oon J, Para 1
The defendant’s failure to complete was not a short-lived default. The plaintiff had already obtained a declaration on 18 January 2022 that the SPA had been validly terminated on 17 August 2021, and the defendant only delivered up possession of the property on 27 February 2022. The plaintiff then proceeded to issue a new option to purchase to a replacement purchaser on 31 May 2022. Those dates were central to the court’s assessment of delay-related losses and the period for which the plaintiff could claim compensation. (Para 9) (Para 12) (Para 13)
"On 18 January 2022, the General Division of the High Court declared that the SPA was validly terminated on 17 August 2021." — Per See Kee Oon J, Para 9
"The defendant delivered up possession of the Property to the plaintiff on 27 February 2022." — Per See Kee Oon J, Para 12
"On 31 May 2022, the plaintiff issued another purchaser (the “Replacement Purchaser”) an Option to Purchase (the “New OTP”)." — Per See Kee Oon J, Para 13
The court also noted the earlier procedural orders that shaped the damages hearing. In the earlier application, the court had ordered possession, payment of outstanding maintenance charges, damages to be assessed, interest, and costs. Those earlier orders framed the present hearing as a quantification exercise rather than a liability trial. (Para 9)
What Issues Did the Court Identify for Determination?
The court expressly identified the disputed heads of claim that required proof and legal analysis. These were legal costs, reinstatement works, damages for the delayed sale and purchase of the property, interest on shareholders’ loan, and unnecessary expenses. The court’s structure is important because it shows that each item was treated as a distinct head of loss, with its own contractual or legal basis. (Para 19)
"The issues to be determined therefore pertained to whether the plaintiff had proved its entitlement to the sums in the disputed claims, viz:" — Per See Kee Oon J, Para 19
"(a) legal costs quantified at $100,268.37; (b) costs of reinstatement work quantified at $103,915.48; (c) damages for the delayed sale and purchase of the Property quantified at $286,962.27; (d) interest on shareholders’ loan quantified at $168,709.33; and (e) unnecessary expenses quantified at $100,981.64." — Per See Kee Oon J, Para 19
That framing also reveals the defendant’s broad resistance. He did not merely dispute quantum; he challenged entitlement, causation, remoteness, contractual interpretation, and the sufficiency of the plaintiff’s evidence. The court therefore had to work through each head systematically, asking whether the SPA, the LSS Conditions, or general principles of damages supported recovery. (Para 22) (Para 38) (Para 52) (Para 59)
Why Did the Court Allow the Legal Costs Claim?
The plaintiff’s legal costs claim was grounded in cl 5A.2.3 of the SPA, which the court described as clear and unambiguous. The defendant initially argued that the claim for legal costs on an indemnity basis was baseless, and later shifted to an argument that the claim was abusive because costs had already been awarded in earlier proceedings. The court rejected that challenge and accepted that the contractual indemnity clause supported recovery of the plaintiff’s legal costs incurred in relation to the dispute. (Para 22) (Para 23) (Para 27)
"The plaintiff’s claim was premised on its contractual entitlement pursuant to cl 5A.2.3 of the SPA. The provision is worded in clear and unambiguous terms." — Per See Kee Oon J, Para 27
The court’s reasoning was anchored in the contractual text and the actual costs evidence. It was satisfied that the quantum of $100,268.37 was supported by the invoices from Dentons produced through Mr Koh. The court also addressed the defendant’s attempt to rely on earlier costs orders, noting that the plaintiff had already been awarded costs of $7,500 in OS 1092 and $1,500 in SUM 740, and that those sums had been deducted from the legal costs claim. This meant the plaintiff was not seeking to recover the same costs twice. (Para 28) (Para 29)
"I was satisfied that the quantum of $100,268.37 claimed by the plaintiff was supported by the invoices from Dentons that the plaintiff had adduced through Mr Koh." — Per See Kee Oon J, Para 28
On the abuse-of-process point, the court did not accept that the earlier costs orders barred the contractual claim. The judgment indicates that the court treated the earlier awards as part of the accounting exercise, not as a complete answer to the plaintiff’s entitlement under the SPA. The result was that the legal costs claim succeeded, subject to the deductions already reflected in the figure claimed. (Para 23) (Para 29) (Para 68)
How Did the Court Deal with the Reinstatement Works Claim?
The reinstatement claim concerned the cost of restoring the property to its original state and condition as at the Vacant Possession Date. The defendant argued that he had not been given sufficient opportunity or time to carry out the works. The court rejected that submission, finding that the documentary evidence showed he had at least three opportunities from August 2021 to February 2022 to do so. The court therefore treated the defendant as having had ample opportunity to comply but failing to take it. (Para 31) (Para 32) (Para 33)
"The documentary evidence showed that he was given at least three opportunities from August 2021 to February 2022 to carry out the reinstatement works." — Per See Kee Oon J, Para 32
The court’s conclusion was that the defendant could not avoid liability by asserting lack of time. It expressly stated that it did not accept the defendant’s contention on insufficient opportunity. The claim was therefore allowed because the plaintiff had shown that the reinstatement works were necessary and that the defendant had been given repeated chances to perform them before the plaintiff had to step in. (Para 33) (Para 34)
"I did not accept that the defendant did not have sufficient opportunity or time to carry out the reinstatement works to restore the Property to its original state and condition as at the Vacant Possession Date." — Per See Kee Oon J, Para 33
The court also accepted the plaintiff’s evidence on the condition of the property and the need for the works. Mr Koh’s testimony and the supporting documents were sufficient to establish the claim. The reinstatement head was therefore treated as a recoverable consequence of the defendant’s continued occupation and failure to restore the property as required. (Para 14) (Para 32) (Para 68)
Why Were Delayed-Sale Damages Allowed, But Wrotham Park Damages Excluded?
The delayed-sale claim was the most legally nuanced part of the judgment. The plaintiff sought damages for the delay in being able to resell the property, and the court accepted that the plaintiff was entitled to compensation for the delay and purchase process. However, the plaintiff also sought a Wrotham Park component of $51,761.80, which the court excluded. The court’s approach was to allow ordinary compensatory damages for the delay, but not the exceptional gain-based or negotiating-damages element the plaintiff attempted to add. (Para 45) (Para 50) (Para 68)
"On basic compensatory principles, the plaintiff should be placed in a position as if the contract had been performed, and be compensated for its expectation loss." — Per See Kee Oon J, Para 45
"Wrotham Park damages are a limited and exceptional remedy." — Per See Kee Oon J, Para 46
The court expressly stated that it was not persuaded that the case was suitable for Wrotham Park damages. It therefore allowed the plaintiff’s claim for damages for the delayed sale and purchase of the property, but excluded the sum of $51,761.80 claimed under that rubric. The court’s reasoning indicates that the plaintiff had not shown the exceptional circumstances required for that remedy, even though it had shown that delay itself caused compensable loss. (Para 46) (Para 50)
"I was not persuaded that this is a suitable case for the award of Wrotham Park damages." — Per See Kee Oon J, Para 46
"I therefore allowed the plaintiff’s claim for damages for the delayed sale and purchase of the Property but excluded the sum of $51,761.80 claimed as Wrotham Park damages." — Per See Kee Oon J, Para 50
The court’s treatment of this issue is significant because it distinguishes between ordinary expectation loss and an exceptional remedy that is not available merely because a plaintiff has suffered delay or inconvenience. The judgment thus reinforces that Wrotham Park damages are not a default measure for property-related delay claims. (Para 45) (Para 46) (Para 50)
How Did the Court Approach the Interest on Shareholders’ Loan Claim?
The plaintiff claimed interest on a shareholders’ loan as part of the financial consequences of the defendant’s failure to complete. The defendant did not challenge the quantum, but argued that the loss was too remote. The court rejected that objection, holding that financing costs of this kind were within the reasonable contemplation of the parties and therefore recoverable under the first limb of Hadley v Baxendale. (Para 52) (Para 55)
"The defendant did not challenge the quantum claimed but contended that the loss was too remote." — Per See Kee Oon J, Para 52
"Financing costs which the plaintiff might have had to incur for the construction of the Development should be within the objective reasonable contemplation of the parties, and would fall within the first limb of the well-settled remoteness principle in Hadley v Baxendale (1854) 9 Exch 341." — Per See Kee Oon J, Para 55
The court also relied on the defendant’s own concession in cross-examination that the need for such financing would not have come as a surprise to him. That concession supported the conclusion that the financing-related loss was not only foreseeable in the abstract, but actually within the defendant’s contemplation as a commercial matter. The court therefore accepted the claim for interest on the shareholders’ loan. (Para 55)
"the defendant conceded in cross-examination that the need for such financing would not have come as a surprise to him." — Per See Kee Oon J, Para 55
This part of the judgment is important because it shows the court applying orthodox remoteness principles to a property transaction involving financing costs. The court did not treat the claim as speculative or too indirect; instead, it viewed financing as a foreseeable consequence of delayed completion in a development project. (Para 55)
Why Were the Unnecessary Expenses Recoverable?
The plaintiff also claimed unnecessary expenses, and the defendant argued that these costs and expenses did not arise out of the resale of the property and were therefore not claimable having regard to Condition 15.10(b) of the LSS Conditions. The court rejected that submission and allowed the claim, finding that there was sufficient evidence that the expenses were reasonably incurred and paid. (Para 59) (Para 64)
"The defendant suggested that these costs and expenses did not arise out of the resale of the Property and thus were not claimable having regard to Condition 15.10(b) of the LSS Conditions" — Per See Kee Oon J, Para 59
"I allowed this head of claim as there was sufficient evidence adduced by the plaintiff to show that the expenses were reasonably incurred and paid." — Per See Kee Oon J, Para 64
The court’s reasoning was evidence-driven. It did not accept a bare objection that the expenses were outside the contractual framework. Instead, it looked to whether the plaintiff had shown that the expenses were actually incurred, were reasonable, and were connected to the consequences of the defendant’s default. On that basis, the claim succeeded. (Para 64)
This head of claim illustrates the court’s willingness to allow practical, transaction-related expenses where the plaintiff can prove them with sufficient documentary support. It also shows that the court was prepared to read the SPA and the LSS Conditions together, but not in a way that would defeat recovery where the contractual and evidential basis for the claim was established. (Para 59) (Para 64) (Para 67)
How Did the Court Interpret the SPA and the LSS Conditions on Deposit Forfeiture and Remedies?
The court addressed the relationship between cl 5.4 and cl 2.1 of the SPA on the one hand, and Condition 15.10(b) of the LSS Conditions on the other. It held that the SPA provisions would override Condition 15.10(b) and expressly permit forfeiture of the deposit while preserving the plaintiff’s other available rights or remedies. This was important because it confirmed that the plaintiff could forfeit the deposit and still pursue further damages. (Para 67)
"Clause 5.4 read with cl 2.1 of the SPA would override Condition 15.10(b) of the LSS Conditions, and expressly permit forfeiture of the deposit while preserving the plaintiff’s other available rights or remedies." — Per See Kee Oon J, Para 67
The court also referred to the statutory and contractual framework governing the defendant’s continued occupation. It noted that, notwithstanding temporary relief under the COVID-19 (Temporary Measures) Act 2020, the plaintiff’s rights continued to accrue during the prescribed period of temporary relief from 20 April 2020 to 30 June 2021, by virtue of s 7A(2). The court further held that the defendant would be liable to double rent under s 28(4) of the Civil Law Act 1909 (2020 Rev Ed). These points mattered because they supported the plaintiff’s entitlement to compensation for continued occupation and detention of the property. (Para 40) (Para 41)
"notwithstanding that s 5 of the COVID-19 (Temporary Measures) Act 2020 (“the COVID-19 Act”) provided temporary relief in respect of the performance of certain prescribed contracts, the plaintiff’s rights would continue to accrue during the prescribed period of temporary relief, from 20 April 2020 to 30 June 2021. This is clear from s 7A(2) of the COVID-19 Act." — Per See Kee Oon J, Para 40
"Every tenant holding over after the determination of his tenancy shall be chargeable, at the option of his landlord, with double the amount of his rent until possession is given up by him or with double the value during the period of detention of the land or premises so detained, whether notice to that effect has been given or not." — Per See Kee Oon J, Para 41
Although the defendant argued that he was never a tenant, the court’s analysis shows that the statutory language and the contractual framework were used to support the plaintiff’s claim for occupation-related damages. The court treated the defendant’s continued possession as legally significant and compensable, even in the face of the defendant’s attempt to deny a landlord-tenant relationship. (Para 38) (Para 41)
What Evidence Did the Court Rely On in Assessing the Claims?
The court heard from one witness on each side: the defendant and Mr Koh Chin Beng for the plaintiff. The judgment indicates that the court relied heavily on documentary evidence, including invoices, quotations, and correspondence, as well as the oral evidence of the witnesses. This was not a case where the court had to resolve a large number of factual disputes through extensive witness credibility findings; rather, the court used the documents to test whether each claimed head of loss was proved. (Para 14)
"The parties relied on the evidence of one witness each in the AD hearing, namely the defendant and Mr Koh Chin Beng (“Mr Koh”), who testified as the plaintiff’s sole witness." — Per See Kee Oon J, Para 14
For the legal costs claim, the invoices from Dentons were decisive. For the reinstatement claim, the documentary record showed repeated opportunities given to the defendant. For the financing claim, the defendant’s own concession in cross-examination supported foreseeability. For the unnecessary expenses claim, the court was satisfied that the expenses were reasonably incurred and paid. The judgment therefore demonstrates a classic damages-assessment approach: entitlement is established by contract and law, but proof is established by documents and targeted testimony. (Para 28) (Para 32) (Para 55) (Para 64)
The court’s treatment of the evidence also explains why the final award was not a rough estimate. Instead, the court assessed the damages item by item, accepted some claims in full, and reduced one claim by excluding the Wrotham Park component. That method produced a final figure that was both detailed and transparent. (Para 68) (Para 71)
How Did the Court Calculate the Final Damages Award?
The court set out the damages in a structured schedule and then arrived at the final total. The plaintiff’s damages were assessed as follows: legal costs of $100,268.37; reinstatement costs of $103,915.48; delayed-sale damages of $286,962.27, less $51,761.80; interest on shareholders’ loan of $168,709.33; and unnecessary expenses of $100,981.64. The court then concluded that the plaintiff was entitled to damages amounting to $720,960.84. (Para 68) (Para 71)
"The plaintiff’s damages were therefore assessed as follows:" — Per See Kee Oon J, Para 68
"Damages for the delayed sale and purchase of the Property $286,962.27 (less $51,761.80)" — Per See Kee Oon J, Para 68
The reduction in the delayed-sale head is the only express downward adjustment identified in the extraction. The court’s final figure therefore reflects a largely successful claim by the plaintiff, but one that was moderated by the court’s refusal to award Wrotham Park damages. The award also carried interest at the usual rate of 5.33% from the date of the OS to judgment. (Para 50) (Para 71)
"The plaintiff was thus entitled to damages amounting to $720,960.84 with interest at the usual rate of 5.33% from the date of the OS to judgment." — Per See Kee Oon J, Para 71
What Did the Court Say About Costs of the Proceedings?
The court ordered that costs of the OS be fixed on the indemnity basis at $45,000 to the plaintiff, with reasonable disbursements in addition. This was a separate costs order from the damages award itself, and it reflects the court’s view that the plaintiff had succeeded substantially in the proceedings. The judgment also records that earlier costs awards of $7,500 and $1,500 had already been made in prior applications and deducted from the legal costs claim. (Para 70) (Para 29)
"I ordered that costs of the OS be fixed on the indemnity basis at $45,000 to the plaintiff, with reasonable disbursements in addition." — Per See Kee Oon J, Para 70
The earlier costs awards mattered because they were part of the defendant’s argument that the legal costs claim was abusive or duplicative. The court’s treatment of the issue shows that it was attentive to avoiding double recovery while still enforcing the contractual indemnity. The result was a damages award and a separate costs order, each supported by its own reasoning. (Para 23) (Para 29) (Para 70)
Why Does This Case Matter?
This case matters because it is a detailed Singapore High Court example of damages assessment in a failed property sale where the purchaser remained in possession after termination. It confirms that a plaintiff can recover a range of losses flowing from the default, including contractual legal costs, reinstatement expenses, financing-related losses, and reasonable transaction expenses, provided the claims are properly grounded and proved. (Para 27) (Para 28) (Para 33) (Para 55) (Para 64)
It also matters because the court drew a clear line around Wrotham Park damages. Even where a plaintiff suffers delay and inconvenience, the court will not award that exceptional remedy unless the legal requirements are met. The judgment therefore serves as a caution against over-pleading gain-based or negotiating damages in ordinary contractual disputes. (Para 46) (Para 50)
Finally, the case is useful for practitioners because it shows how the SPA, the LSS Conditions, the Civil Law Act, and the COVID-19 temporary relief regime can interact in a single property dispute. The court’s analysis of deposit forfeiture, continued occupation, and remoteness provides a practical roadmap for future disputes involving failed completion and post-termination possession. (Para 40) (Para 41) (Para 67)
Cases Referred To
| Case Name | Citation | How Used | Key Proposition |
|---|---|---|---|
| CDM and another v CDP | [2021] 2 SLR 235 | Cited by the defendant on the legal costs issue; the court rejected the reliance placed on it. | Used in argument to suggest the indemnity claim was baseless, but not accepted by the court. (Para 22) (Para 23) |
| CGG v CGH | [2021] 2 SLR 1091 | Cited by the defendant on the legal costs issue; the court distinguished or rejected the argument. | Used by the defendant to support an estoppel/res judicata style objection to the costs claim. (Para 23) |
| Maryani Sadeli v Arjun Permanand Samtani and another and other appeals | [2015] 1 SLR 496 | Referred to through CGG in the defendant’s argument on prior costs and double recovery. | Invoked for the proposition that unrecovered costs in prior proceedings could not be claimed again as damages. (Para 23) |
| Brown v Davies | (1958) 1 QB 117 | Used on the reinstatement works issue. | Supports the burden on the defendant/tenant to show that damage was fair wear and tear. (Para 31) |
| Wrotham Park Estate Co Ltd v Parkside Homes Ltd | [1974] 1 WLR 798 | Relied on by the plaintiff for the delayed-sale claim; the court declined to award damages on that basis. | Associated with damages protecting the performance interest. (Para 45) (Para 46) |
| Turf Club Auto Emporium Pte Ltd and others v Yeo Boong Hua and others and another appeal | [2018] 2 SLR 655 | Used to reject the Wrotham Park component. | Wrotham Park damages are a limited and exceptional remedy. (Para 46) |
| Robertson Quay Investment Pte Ltd v Steen Consultants Pte Ltd and another | [2008] 2 SLR(R) 623 | Used on remoteness and financing costs. | Third-party financing costs in large commercial projects may be foreseeable. (Para 55) |
| Bauer, Adam Godfrey and another v Wee Tien Liang, deceased | [2021] SGHCR 8 | Used on unnecessary expenses and financing-related damages. | Damages for aborted sale and purchase can include commission and legal fees supported by invoices. (Para 59) (Para 64) |
| Essex v Daniell | (1875) LR 10 CP 538 | Used on recoverability of wasted sale expenses. | A seller may recover expenses incurred in preparing for sale and loss on resale. (Para 59) |
| Hadley v Baxendale | (1854) 9 Exch 341 | Used on remoteness for financing costs. | Losses recoverable if within the reasonable contemplation of the parties. (Para 55) |
Legislation Referenced
- Civil Law Act 1909 (2020 Rev Ed), s 28(4) (Para 41)
- COVID-19 (Temporary Measures) Act 2020, s 5 (Para 40)
- COVID-19 (Temporary Measures) Act 2020, s 7A(2) (Para 40)
"Every tenant holding over after the determination of his tenancy shall be chargeable, at the option of his landlord, with double the amount of his rent until possession is given up by him or with double the value during the period of detention of the land or premises so detained, whether notice to that effect has been given or not." — Per See Kee Oon J, Para 41
"The defendant’s primary contention was that he was not liable for this head of damages as he was “never a tenant, and tenant-landlord relationship did not exist”." — Per See Kee Oon J, Para 38
"The plaintiff’s claim was premised on its contractual entitlement pursuant to cl 5A.2.3 of the SPA. The provision is worded in clear and unambiguous terms." — Per See Kee Oon J, Para 27
"I was satisfied that the quantum of $100,268.37 claimed by the plaintiff was supported by the invoices from Dentons that the plaintiff had adduced through Mr Koh." — Per See Kee Oon J, Para 28
"The documentary evidence showed that he was given at least three opportunities from August 2021 to February 2022 to carry out the reinstatement works." — Per See Kee Oon J, Para 32
"I did not accept that the defendant did not have sufficient opportunity or time to carry out the reinstatement works to restore the Property to its original state and condition as at the Vacant Possession Date." — Per See Kee Oon J, Para 33
"I was not persuaded that this is a suitable case for the award of Wrotham Park damages." — Per See Kee Oon J, Para 46
"I allowed this head of claim as there was sufficient evidence adduced by the plaintiff to show that the expenses were reasonably incurred and paid." — Per See Kee Oon J, Para 64
"Clause 5.4 read with cl 2.1 of the SPA would override Condition 15.10(b) of the LSS Conditions, and expressly permit forfeiture of the deposit while preserving the plaintiff’s other available rights or remedies." — Per See Kee Oon J, Para 67
"The plaintiff was thus entitled to damages amounting to $720,960.84 with interest at the usual rate of 5.33% from the date of the OS to judgment." — Per See Kee Oon J, Para 71
Source Documents
- Original Judgment — Singapore Courts
- Archived Copy (PDF) — Litt Law CDN
- View in judgment: "I assessed that the plaintiff was..."
- View in judgment: "Wrotham Park damages are a limited..."
- View in judgment: "The plaintiff’s damages were therefore assessed..."
- View in judgment: "The plaintiff was thus entitled to..."
- View in judgment: "The plaintiff was awarded costs of..."
This article analyses [2023] SGHC 1 for legal research and educational purposes. It does not constitute legal advice. Readers should consult the full judgment for the Court's complete reasoning.