Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
Singapore

Viking Airtech Pte Ltd v Foo Teow Keng and Another [2009] SGHC 169

In Viking Airtech Pte Ltd v Foo Teow Keng and Another, the High Court of the Republic of Singapore addressed issues of Damages — Assessment.

300 wpm
0%
Chunk
Theme
Font

Case Details

  • Citation: [2009] SGHC 169
  • Title: Viking Airtech Pte Ltd v Foo Teow Keng and Another
  • Court: High Court of the Republic of Singapore
  • Date of Decision: 23 July 2009
  • Judge: Judith Prakash J
  • Coram: Judith Prakash J
  • Case Number(s): Suit 111/2006, RA 380/2008, 405/2008
  • Tribunal/Proceedings: High Court (Registrar’s appeals against assessment of damages)
  • Legal Area: Damages — Assessment
  • Plaintiff/Applicant: Viking Airtech Pte Ltd
  • Defendants/Respondents: Foo Teow Keng and Another
  • Second Defendant (context): JL Marine & Engineering Pte Ltd (formerly known as Viking HVAC & Automation Pte Ltd)
  • Key Issue on Appeal: Correct measure of damages for breach of fiduciary duty involving diversion of contracts; assessment of costs/overheads and interest
  • Counsel for Plaintiff: Lawrence Lee (Aptus Law Corporation)
  • Counsel for Defendants: Mimi Oh (Mimi Oh & Associates)
  • Judgment Length: 10 pages, 6,143 words
  • Procedural History (as stated): Liability trial completed; damages assessed by Assistant Registrar Teo Guan Siew in August 2008; appeals heard by Judith Prakash J

Summary

Viking Airtech Pte Ltd v Foo Teow Keng and Another [2009] SGHC 169 concerns the assessment of damages following a prior finding that Mr Foo, a former director and general manager of Viking Airtech Pte Ltd (“Viking”), breached fiduciary duties owed to Viking. The High Court (Judith Prakash J) dealt with registrar’s appeals arising from the Assistant Registrar’s (“AR”) assessment of damages for three categories of wrongdoing: (i) diversion of two contracts for the sale, delivery and installation of air-conditioning systems in oil tankers being constructed in Indonesia; (ii) failure to deliver equipment for the “Pelindo II” vessel and diversion of that supply to the second defendant; and (iii) conversion of Viking’s assets located in Viking’s office in Shanghai.

The court’s focus was not liability, which had already been determined in Viking’s favour, but the correct measure of damages and the proper approach to quantifying the loss caused by the breach. In particular, the court had to decide what Viking had to prove to establish a causal connection between the fiduciary breach and the loss claimed, and how to calculate the net amount Viking would have received had the diverted contracts been performed. The High Court also addressed whether overheads and other cost components should be included or excluded, and it considered the appropriate award of interest given Viking’s delay in commencing proceedings.

Ultimately, the High Court upheld the AR’s overall approach to the diverted contracts and the “Pelindo II” claim, while refining aspects of the damages computation and interest. The decision is significant for practitioners because it illustrates how Singapore courts assess damages for fiduciary breach where the plaintiff’s claim is framed as lost income rather than loss of profits, and it demonstrates the evidential and analytical discipline required when dealing with cost items such as overheads, subcontracting, and commissions.

What Were the Facts of This Case?

Viking Airtech Pte Ltd is a company engaged in the manufacturing and supply of heating, ventilation and air-conditioning systems for vessels. Until November 2003, Mr Foo was a director and general manager of Viking. The second defendant, JL Marine & Engineering Pte Ltd (formerly known as Viking HVAC & Automation Pte Ltd), competes with Viking and was owned by Mr Foo and his wife. Critically, the second defendant was established by Mr Foo while he was still employed by Viking, setting the stage for a conflict of interest and the potential diversion of business opportunities.

After liability was tried, the High Court found that Mr Foo breached fiduciary and other duties to Viking by diverting business from Viking to the second defendant. The diversion took concrete form in relation to two contracts for air-conditioning systems in oil tankers being constructed in Indonesia. The first diverted contract was worth US$149,000 with PT Dok Dan Perkapalan Surabaya (Persero) (“PT Dok”). The second diverted contract was worth US$198,000 with PT Pal Indonesia (Persero) (“PT Pal”). The court also found that Mr Foo caused Viking to fail to deliver equipment fabricated pursuant to a contract for the vessel “Pelindo II” between Viking and PT Pal, and that the second defendant supplied the equipment to PT Pal instead.

In addition to the diversion of contractual opportunities, the court found a conversion claim: the defendants converted to their own use Viking’s assets located in Viking’s office in Shanghai. These findings were made at the liability stage, and the present proceedings were confined to the assessment of damages arising from those breaches.

Damages were assessed by Assistant Registrar Teo Guan Siew in August 2008. The parties accepted that the plaintiff bore the burden of proving the causal connection between the established breach of fiduciary duty and the loss asserted. In relation to the diverted contracts, Viking did not claim damages for loss of profits in the strict sense. Instead, Viking claimed the net amounts it would have received if the contracts had not been diverted—namely, contract value less the costs that Viking would have incurred to perform the contracts. Viking’s calculations used cost figures supplied by the second defendant, reasoning that the second defendant had fabricated the systems and had obtained materials from the same suppliers Viking would have used, and therefore Viking would have incurred similar expenses if it had performed the work.

The first key issue was the correct measure of damages for breach of fiduciary duty involving diversion of contracts. While the general principle in fiduciary cases is compensatory—aiming to put the plaintiff in the position it would have been in had the breach not occurred—the court had to determine how that principle translates into a quantification exercise where the plaintiff claims net income from diverted contracts rather than loss of profits. The court also had to consider what evidence is required to establish causation and the counterfactual scenario: what Viking would have earned and what costs it would have borne.

A second issue concerned the treatment of overheads and other cost items. The AR accepted Viking’s approach but addressed objections by the defendants that certain costs were wrongly omitted. The defendants argued that overheads, subcontracting costs, and Indonesian commissions and other expenses should be factored into the computation, and that the AR’s “broad-brush” method for additional labour and subcontracting costs was not justified. Closely related was the question of whether Viking’s overall financial performance in 2003 and 2004 should affect the assessment—essentially, whether Viking could recover damages for diverted contracts if it did not show overall profitability in those years.

A third issue related to interest. Viking sought interest from the respective dates of loss or, alternatively, from the date of filing of the writ. The AR rejected Viking’s request for interest from the dates of breach, citing Viking’s delay in instituting the action and the lack of explanation for the lapse of almost three years. The High Court therefore had to decide whether the AR’s approach to interest was correct in principle and in application.

How Did the Court Analyse the Issues?

The High Court began by reaffirming the compensatory nature of damages in cases of breach of contract or breach of fiduciary duty. The court emphasised that the basis of assessment is to compensate the plaintiff and put it in the position it would have been in had the breach not occurred. In this case, if the contracts had not been diverted, Viking would have received income from both contracts. The defendants’ argument—that Viking could not recover because it did not make net profits overall in the relevant years—was rejected as conceptually incorrect. The court held that the plaintiff was not limited to recovering only if it could show overall profitability for the year; rather, the assessment question was how much Viking would have received in income from the diverted contracts, taking into account that Viking would have had to incur expenses to fulfil them.

On the diverted contracts, the court scrutinised the AR’s approach to costs. Viking’s methodology was to take the contract value (converted into Singapore dollars at the agreed exchange rate) and deduct direct costs of fabrication and other direct expenses. Viking did not include overheads as a separate deduction, and it relied on cost figures from the second defendant to estimate fabrication costs. The AR accepted this approach but recognised that some additional labour and subcontracting costs would have been incurred beyond materials. The AR therefore adopted a broad-brush estimate: 15% of the contract value as additional labour and subcontracting costs necessary to perform the contracts.

The defendants challenged this, arguing that Viking’s profit margins were nominal and that the AR’s computation produced damages inconsistent with Viking’s actual financial performance. The High Court addressed this by examining the evidence of Viking’s gross and net profit margins across 2002, 2003 and 2004. The court noted that Viking’s gross profit margins were in the range of 17% to 27%, but net profit margins were much lower, even negative in some years, due to high costs of sales. The court also observed that Viking had initially estimated loss of profits at 30% of the contract value, which aligned with its gross earnings in 2004, but that Viking had been selective in its costing during discovery by omitting certain cost items such as Indonesian commissions and other expenses, and additional labour and subcontracting costs.

In this context, the High Court endorsed the AR’s reasoning that overheads could not be ignored entirely, but also that overheads included both fixed costs that would have been incurred regardless of whether the contracts were performed and variable components that would have increased with additional work. The court accepted that while the bulk of overheads might be fixed, there would be some additional labour and subcontracting costs. The AR’s 15% estimate was therefore treated as a pragmatic and evidentially grounded solution to the problem of quantifying counterfactual costs where the parties’ evidence was imperfect and where the plaintiff’s costing approach did not fully capture all relevant cost categories.

With respect to the “Pelindo II” claim, the AR had accepted Viking’s calculation of damages based on the amount Viking would have been paid for the fabricated system, less the salvage value obtained when the system was scrapped due to the failure to deliver. The High Court did not disturb the AR’s acceptance of this method. The logic was straightforward: Viking fabricated the system, would have received the contract price had delivery occurred, but received no payment because of Mr Foo’s breach; Viking then mitigated by scrapping the system and recovering salvage value. The resulting net loss was therefore the difference between the contract sum and the salvage value.

On the conversion claim, the AR assessed damages as the net book value of the equipment converted, based on the values appearing in Viking’s accounts as at 2003. The High Court’s analysis treated this as an appropriate measure given the nature of the claim and the availability of accounting records to quantify value.

Finally, on interest, the High Court considered the AR’s rejection of interest from the dates of loss. The AR had accepted that Viking delayed instituting the action and had not explained the almost three-year lapse. The High Court therefore upheld the AR’s decision to award interest at 5.33% per annum from the date the judgment in the suit was issued (12 October 2007). This reflects a judicial approach that interest is not purely automatic; it is discretionary and may be adjusted to account for delay and fairness considerations.

What Was the Outcome?

The High Court dismissed the defendants’ appeals seeking reductions to the awards for the diverted contracts and the “Pelindo II” claim. It accepted that the AR’s approach to causation and quantification was correct in principle and sufficiently supported on the evidence. The court also rejected the defendants’ attempt to import Viking’s overall profitability in 2003 and 2004 as a bar to recovery, holding that the relevant counterfactual was the income Viking would have received from the diverted contracts, less the costs it would have incurred to perform them.

On Viking’s appeal, the court did not grant the full relief sought regarding the removal of the 15% deduction for additional labour and subcontracting costs. The court maintained the AR’s broad-brush adjustment as a reasonable reflection of costs that would have been incurred. The court also upheld the AR’s interest award, confirming that interest would run from the date of judgment rather than from the dates of breach or filing of the writ, due to Viking’s delay and lack of explanation.

Why Does This Case Matter?

Viking Airtech [2009] SGHC 169 is a useful authority for lawyers dealing with damages assessment in fiduciary breach cases involving diversion of business opportunities. It clarifies that damages are compensatory and counterfactual in nature: the plaintiff must be placed in the position it would have been in had the breach not occurred. Importantly, the decision rejects an overly restrictive approach that would require the plaintiff to prove overall profitability for the relevant year as a prerequisite to recovering damages for diverted contracts.

The case also provides practical guidance on how courts may handle evidential gaps in cost quantification. Where the plaintiff’s costing methodology is incomplete or selective, the court may adopt a broad-brush estimate for certain cost components, particularly where some additional labour or subcontracting would inevitably be incurred. For practitioners, this underscores the need to present comprehensive and internally consistent evidence of costs, including overheads and commissions, and to explain why certain costs are fixed or variable in the counterfactual scenario.

Finally, the decision is relevant to interest claims in delayed litigation. It demonstrates that courts may refuse interest from the dates of loss where the plaintiff delayed commencing proceedings without adequate explanation. This has direct implications for litigation strategy and for advising clients on the timing of claims and the evidential record needed to justify interest from earlier dates.

Legislation Referenced

  • None specified in the provided judgment extract.

Cases Cited

  • Ohm Pacific Sdn Bhd v Ng Hwee Cheng Doreen [1994] 2 SLR 576
  • [2009] SGHC 169 (the present case)

Source Documents

This article analyses [2009] SGHC 169 for legal research and educational purposes. It does not constitute legal advice. Readers should consult the full judgment for the Court's complete reasoning.

Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.