Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
Singapore

TWARIT CONSULTANCY SERVICES PRIVATE LIMITED & Anor v GPE (INDIA) LTD & 2 Ors

by the relevant defendant, for a total price in the three SPAs of INR200,00,00,000.10 The plaintiffs were to purchase the shares in 14 tranches on various dates from 30 September 2015 to 30 June 2018.11 10 Secondly, a so-called letter agreement (“the First Letter Agreement”) was entered into betw

300 wpm
0%
Chunk
Theme
Font
"The question is whether there is a ‘Dispute’ within that term in the arbitration clauses in the SPAs and the First Letter Agreement. There plainly is, as a disputed claim (rightly or wrongly made) between the defendants and the plaintiffs as parties thereto (including Twarit), a claim for damages for breach of and so in connection with or arising out of those agreements." — Per Roger Giles IJ, Para 75

Case Information

  • Citation: [2021] SGHC(I) 17 (Para 0)
  • Court: Singapore International Commercial Court — Originating Summons No 10 of 2021 (Para 0)
  • Date of Judgment: 24 December 2021 (Para 0)
  • Coram: Roger Giles IJ (Para 0)
  • Counsel for the Plaintiffs: Mr Joshua Chow (Para 0)
  • Counsel for the Defendants: Mr Prakash Pillai, lead counsel (Para 0)
  • Case Number: Originating Summons No 10 of 2021 (Para 0)
  • Area of Law: International arbitration; setting aside of award; jurisdiction; arbitrability; natural justice; public policy (Paras 1, 93, 102)
  • Judgment Length: Not answerable from the extraction (NOT ANSWERABLE)

Summary

The plaintiffs applied to set aside, in whole or in part, a final arbitral award made on 7 January 2021 in consolidated SIAC arbitrations arising out of share purchase agreements and a First Letter Agreement connected to Haldia Coke and Chemicals Private Ltd. The application invoked multiple grounds under Article 34 of the Model Law and s 24(b) of the International Arbitration Act, including lack of jurisdiction, excess of scope, procedural irregularity, inability to present the case, and public policy. The court’s central conclusion was that the dispute was a “Dispute” within the arbitration clauses in the SPAs and the First Letter Agreement, that the presumption of arbitrability was not rebutted, and that the plaintiffs’ principal jurisdictional and arbitrability challenges failed. (Paras 1, 75, 93, 102)

The factual background was commercially complex but legally focused. The defendants had subscribed to shares in Haldia under earlier agreements, a listing event did not occur by 31 March 2014, and the parties later entered into the SPAs and the First Letter Agreement on 28 September 2015. The plaintiffs paid only the first tranche under the SPAs, Haldia later entered insolvency proceedings, and the defendants commenced SIAC arbitrations on 14 December 2017. The tribunal ultimately ordered payment of INR195,00,00,000 plus simple interest and costs. The court treated the plaintiffs’ attempt to recast the dispute as one arising under the earlier SSHAs as the wrong question, because the claim before the tribunal was for damages for breach of the later agreements. (Paras 8, 14, 15, 33, 75)

The court also dealt with procedural objections. It refused the plaintiffs’ application for a further adjournment of the hearing, declined to allow the plaintiffs to resurrect an abandoned public policy ground, and rejected the complaints about the tribunal’s handling of the evidentiary hearing and the Indian law expert evidence. In doing so, the court emphasised that the plaintiffs’ arguments did not displace the presumption of arbitrability and did not establish any basis for setting aside the award under the Model Law or the IAA. (Paras 53, 64, 93, 100, 102)

What Was the Commercial and Contractual Background That Led to the Award?

The dispute arose from a sequence of agreements concerning Haldia Coke and Chemicals Private Ltd. The defendants subscribed to shares in Haldia under SSHAs in 2010 and 2011, and those SSHAs contained exit mechanisms if a listing event did not occur. A listing event was not procured by 31 March 2014, but the parties did not exercise the exit rights then available. Instead, on 28 September 2015, they entered into a series of later agreements, including the SPAs and the First Letter Agreement, which became the focus of the arbitration. (Paras 8, 9)

"A Listing Event was not procured by 31 March 2014. But none of the exit mechanism rights was exercised; instead, on 28 September 2015, a series of agreements were entered into." — Per Roger Giles IJ, Para 8

The court’s narrative shows that the later agreements were not peripheral. The plaintiffs paid only the first tranche under the SPAs, and the defendants later commenced SIAC arbitrations in respect of the three SPAs and the First Letter Agreement. The tribunal’s award was not framed as a claim under the SSHAs; rather, it was a claim for damages for breach of the later agreements, with the tribunal treating the unpaid amount as the outstanding consideration payable. That contractual framing was decisive to the court’s analysis of scope and jurisdiction. (Paras 15, 33, 42(c), 75)

"On 14 December 2017, the defendants commenced the SIAC arbitral proceedings by filing a Notice of Arbitration in respect of the three SPAs and the First Letter Agreement." — Per Roger Giles IJ, Para 15

The insolvency of Haldia added another layer to the dispute. On 11 July 2017, Haldia was admitted into a voluntary corporate insolvency resolution process under Indian law, which brought a moratorium. The court later considered that moratorium in the context of the plaintiffs’ arguments, but it did not treat the insolvency event as displacing the arbitration clauses or rendering the dispute non-arbitrable. Instead, the court analysed the issue through the lens of Singapore arbitration law and the presumption of arbitrability. (Paras 14, 87, 93)

"On 11 July 2017, Haldia was admitted into a voluntary corporate insolvency resolution process under Indian law. This brought a moratorium (“the moratorium”),17 as to which see later in these reasons (at [87] below)." — Per Roger Giles IJ, Para 14

How Did the Tribunal Frame the Monetary Relief and What Did the Award Require?

The tribunal’s award required the plaintiffs to pay INR195,00,00,000 plus simple interest at 7.25% per annum from 21 July 2017 until payment, and it also awarded party-and-party costs and the costs of the arbitration. The court’s summary of the award is important because it shows the quantum that the plaintiffs sought to resist through the setting-aside application. The award was not merely declaratory; it imposed a substantial monetary obligation and costs consequences. (Para 33)

"The Award obliged the plaintiffs to pay to the defendants INR195,00,00,000 plus simple interest at 7.25% per annum from 21 July 2017 to the date of payment, and gave the defendants party-and-party costs and the costs of the arbitration." — Per Roger Giles IJ, Para 33

The tribunal’s reasoning on quantum, as summarised by the court, was that the defendants were entitled on the alternative claim to INR195,00,00,000 as damages for breach of the SPAs, calculated as the outstanding consideration payable thereunder. The court did not disturb that assessment in the setting-aside proceedings. Instead, it treated the plaintiffs’ challenge as an attempt to recharacterise the claim and to attack the tribunal’s jurisdiction and the arbitrability of the dispute. (Para 42(c))

"The Tribunal held that the defendants were entitled on that alternative claim to INR195,00,00,000 as damages for breach of the SPAs, calculated as the outstanding consideration payable thereunder." — Per Roger Giles IJ, Para 42(c)

The award also rejected the larger INR401,00,00,000 claim under cl 3(c) as a penalty, according to the court’s summary of the tribunal’s treatment of the damages issues. That distinction mattered because it showed that the tribunal had engaged with the contractual structure and had not simply accepted the defendants’ case wholesale. The setting-aside court, however, was not asked to re-try the merits; it was concerned with whether the award fell within the submission to arbitration and whether any statutory ground for setting aside was made out. (Paras 42(c), 1, 102)

What Were the Plaintiffs’ Main Setting-Aside Grounds?

The plaintiffs’ application was framed under several distinct grounds. They invoked Article 34(2)(a)(iii) of the Model Law, contending that the award dealt with a dispute not contemplated by or not falling within the submission to arbitration, or contained decisions beyond the scope of the submission. They also relied on Article 34(2)(a)(ii), Article 34(2)(a)(iv), Article 34(2)(b)(ii), and s 24(b) of the IAA. The court’s treatment of the application shows that the plaintiffs attempted to combine jurisdictional, procedural, and public policy objections in a single setting-aside challenge. (Paras 1, 102)

"In the Originating Summons, they applied on the grounds: (a) that the Award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or contains decisions on matters beyond the scope of the submission to arbitration, within the meaning of Article 34(2)(a)(iii) of the UNCITRAL Model Law on International Commercial Arbitration (“the Model Law”) read with s 3 of the International Arbitration Act (Cap 143A, 2002 Rev Ed) (“the IAA”);" — Per Roger Giles IJ, Para 1

The court later explained that grounds (c) and (d) were dealt with together because they both relied on the refusal of an adjournment of the evidentiary hearing and the refusal to exclude the defendants’ Indian law expert. Ground (d) also included a challenge to the damages award of INR195,00,00,000. The court’s structure matters because it shows that the plaintiffs’ complaints were not treated as isolated procedural grievances, but as part of a broader attempt to undermine the award after the tribunal had ruled against them. (Para 100)

"These grounds are conveniently dealt with together. The plaintiffs relied on two matters for both ground (c) and ground (d), being the refusal of an adjournment of the evidentiary hearing and the refusal to exclude the evidence of the defendants’ Indian law expert (see at [31] above),136 and on a third matter for ground (d) alone, being the Tribunal’s award of a total of INR195,00,00,000 as damages (see at [33] above)." — Per Roger Giles IJ, Para 100

One of the plaintiffs’ central submissions was that the dispute was “within the ambit of” the SSHAs rather than the SPAs and the First Letter Agreement. They also argued that the underlying transaction under the later agreements was illegal and/or void under Indian law because it violated FEMA, the regulations thereunder, and s 67 of the Companies Act 2013. In addition, they contended that the tribunal was improperly constituted because the SSHAs required a three-member tribunal in Mumbai. The court rejected these contentions, largely because they were built on the wrong contractual foundation. (Paras 72, 76, 78, 99)

"The plaintiffs submitted that the dispute was “within the ambit of” the SSHAs, as opposed to the SPAs and the First Letter Agreement." — Per Roger Giles IJ, Para 72
"The plaintiffs submitted in the written submissions that “the underlying transaction” under the SPAs and the First Letter Agreement was illegal and/or void under Indian law, because it violated the FEMA and the regulations thereunder and also violated s 67 of the CA." — Per Roger Giles IJ, Para 76

Why Did the Court Reject the “Revival Argument” and the Jurisdictional Challenge?

The court’s answer to the jurisdictional challenge turned on the contractual source of the claim. It held that the relevant question was whether there was a “Dispute” within the arbitration clauses in the SPAs and the First Letter Agreement, and it answered that question affirmatively. The court reasoned that the defendants’ claim was a disputed claim for damages for breach of and in connection with those agreements, and therefore fell squarely within the arbitration clauses. The plaintiffs’ attempt to argue that the dispute belonged under the SSHAs was, in the court’s words, the wrong question. (Paras 75, 68, 70)

"More fundamentally, the essence of the argument is that the dispute falls within the arbitration clauses in the SSHAs; it does not, for the above reasons, but that answers the wrong question." — Per Roger Giles IJ, Para 75

The court’s reasoning also drew a distinction between an arbitration agreement and the submission to arbitration. It cited authority for the proposition that an arbitration agreement is merely an agreement to submit disputes for arbitration, and that the disputes actually submitted determine the scope of the arbitration. That distinction allowed the court to focus on the claims actually advanced in the SIAC proceedings, rather than on the plaintiffs’ preferred characterisation of the broader commercial relationship. (Paras 68, 70)

"An arbitration agreement is merely an agreement between parties to submit their disputes for arbitration. The disputes submitted for arbitration determine the scope of the arbitration." — Per Roger Giles IJ, Para 68

The court also referred to authority indicating that the phrase “submission to arbitration” in Article 34(2)(a)(iii) of the Model Law is not limited to the submission in the particular arbitral proceeding. That point mattered because the plaintiffs sought to confine the analysis too narrowly. The court’s approach was to examine the substance of the claim and the agreements under which it was brought, and on that basis it concluded that the award did not exceed the submission to arbitration. (Para 70)

"the phrase ‘submission to arbitration’ in Article 34(2)(a)(iii) of the Model Law was not limited to the submission in the particular arbitral proceeding" — Per Roger Giles IJ, Para 70

The court further noted that there may be a separate question whether the plaintiffs were precluded from raising the jurisdictional challenge in the setting-aside application, referring to authority on preclusion. But it did not need to resolve that issue because the challenge failed on the merits. The court’s conclusion was therefore not merely procedural; it was a substantive rejection of the plaintiffs’ attempt to recast the dispute as one outside the arbitration clauses. (Para 71, 75)

"there may be a different question whether the plaintiffs are precluded from taking up the challenge in a setting-aside application" — Per Roger Giles IJ, Para 71

Why Did the Court Hold That the Dispute Was Arbitrable Despite the Insolvency Context and Alleged Illegality?

The plaintiffs’ arbitrability argument was that the dispute was non-arbitrable because it involved illegality under Indian law and because of the insolvency context. The court rejected that submission and held that the presumption of arbitrability was not rebutted. It emphasised that, under Singapore law, there is ordinarily a presumption of arbitrability so long as a dispute falls within the scope of an arbitration clause. Since the dispute here did fall within the relevant clauses, the plaintiffs had not shown any basis to displace that presumption. (Paras 81, 93)

"In our judgment, the effect of s 11 of the IAA is that there will ordinarily be a presumption of arbitrability so long as a dispute falls within the scope of an arbitration clause." — Per Roger Giles IJ, Para 81
"The presumption of arbitrability is not rebutted. The second submission fails." — Per Roger Giles IJ, Para 93

The court’s analysis of arbitrability drew on authority concerning disputes of a public character and disputes affecting persons beyond the immediate disputants. It referred to the proposition that non-arbitrability is tied to public policy concerns, and it contrasted the present dispute with cases where insolvency or public rights issues make arbitration inappropriate. The court did not accept that the Indian insolvency moratorium or the alleged illegality under FEMA and the Companies Act transformed this commercial dispute into a non-arbitrable one. (Paras 84, 85, 87, 93)

"disputes which are of a public character and disputes whose outcome will affect the interests of persons beyond the immediate disputants" — Per Roger Giles IJ, Para 84

The court also distinguished authority dealing with insolvency-related non-arbitrability. It noted that some disputes arise only upon insolvency and are therefore tied to collective insolvency processes, but that was not the character of the present claim. Here, the claim was for damages for breach of the SPAs and the First Letter Agreement, which were pre-insolvency commercial agreements. The insolvency of Haldia did not alter the contractual nature of the dispute or remove it from arbitration. (Paras 85, 87, 93)

"The moratorium was declared on 11 July 2017, as part of the insolvency proceedings, by the National Company Law Tribunal at Chennai." — Per Roger Giles IJ, Para 87

How Did the Court Deal With the Tribunal’s Composition and the Plaintiffs’ Mumbai-Seat Argument?

The plaintiffs argued that the tribunal was improperly constituted because the SSHAs required a three-member tribunal in Mumbai. The court rejected that contention by returning to the same foundational point: the dispute was not one under the SSHAs, but under the SPAs and the First Letter Agreement. Once that was accepted, the plaintiffs’ reliance on the SSHAs to attack the tribunal’s composition could not succeed. The court therefore treated the composition challenge as another manifestation of the “Revival Argument” and dismissed it for the same reason. (Paras 78, 99)

"It is sufficient again to repeat the rejection of the Revival Argument." — Per Roger Giles IJ, Para 99

The court’s treatment of this issue was concise but decisive. It did not engage in a separate exercise of reconstructing the tribunal’s appointment mechanics under the SSHAs because the plaintiffs had not shown that those agreements governed the arbitration actually commenced. The tribunal was constituted for the SIAC proceedings brought in respect of the SPAs and the First Letter Agreement, and the court saw no basis to hold that the tribunal lacked jurisdictional legitimacy on the plaintiffs’ theory. (Paras 15, 75, 99)

In practical terms, the court’s approach meant that the plaintiffs could not use an earlier contractual framework to invalidate the arbitral process chosen for the later agreements. The decision reinforces the principle that a party cannot avoid an award by pointing to a different contract unless that contract actually governed the dispute submitted to arbitration. That is why the court repeatedly described the plaintiffs’ argument as answering the wrong question. (Paras 75, 99)

What Did the Court Say About Adjournment, Expert Evidence, and Natural Justice?

The plaintiffs also relied on procedural complaints, including the refusal of an adjournment of the evidentiary hearing and the refusal to exclude the defendants’ Indian law expert. The court dealt with these matters together under the natural justice-related grounds. It noted that the plaintiffs had sought a further adjournment, but after hearing the parties it refused that application. The court then declined to allow the plaintiffs to revive a public policy argument that had been abandoned, explaining that doing so would be contrary to the refusal of the adjournment. (Paras 53, 64, 100, 102)

"Mr Chow made his application, and after hearing the parties I refused the plaintiffs’ application for a further adjournment of the hearing." — Per Roger Giles IJ, Para 53
"I do not permit the resurrection of ground (e) as that would be contrary to the refusal of the adjournment." — Per Roger Giles IJ, Para 64

The court’s handling of these procedural issues suggests that it was attentive to case management and to the integrity of the hearing process. The defendants argued that further delay would prejudice enforcement of the award and could create a cloud over enforcement depending on the jurisdiction. The court accepted the practical significance of the timing issue sufficiently to refuse the adjournment, and it did not treat the plaintiffs’ procedural complaints as establishing any breach of natural justice. (Paras 55, 53, 64, 100)

"Mr Pillai submitted that the defendants would be prejudiced by further delay in the hearing of the Originating Summons, which “creates a cloud over” enforcement of the Award and, depending on the jurisdiction of enforcement, could restrict doing so." — Per Roger Giles IJ, Para 55

The court also recorded that the plaintiffs’ submissions and the defendants’ responsive submissions were detailed and had been filed. That observation matters because it undercuts any suggestion that the plaintiffs were denied a meaningful opportunity to present their case. The court’s refusal to set aside the award on natural justice grounds therefore rested not on a formalistic rejection of the complaint, but on the absence of a demonstrated prejudice arising from the procedural rulings. (Para 46, 102)

"The plaintiffs’ submissions and the defendants’ responsive submissions, both of which were detailed, were filed." — Per Roger Giles IJ, Para 46

Why Did the Court Refuse to Revive the Public Policy Argument?

The court expressly refused to permit the resurrection of ground (e), which had been abandoned in the context of the adjournment issue. It linked that refusal to the earlier decision not to adjourn the hearing, indicating that it would be inconsistent to allow a party to reintroduce a ground that had effectively been set aside in the course of case management. This was not merely a procedural preference; it was part of the court’s insistence that the setting-aside application be determined on the basis of the issues properly before it. (Paras 64, 53)

The court’s approach also reflects a broader judicial reluctance to allow tactical reconfiguration of setting-aside grounds after hearing management decisions have been made. The plaintiffs could not use the refusal of an adjournment as a springboard to reopen a public policy argument that had been dropped. The court’s statement is brief, but it is a clear procedural holding with practical significance for arbitration litigation strategy. (Para 64)

In the context of the overall judgment, the refusal to revive ground (e) fits with the court’s repeated emphasis on the proper contractual and procedural frame of the dispute. The plaintiffs were not permitted to shift the terrain of the case after the hearing had been fixed and the adjournment refused. That discipline supported the final outcome: the award stood, and the setting-aside application failed on the grounds pursued in the excerpt. (Paras 53, 64, 93, 102)

The court applied a distinction between the arbitration agreement and the submission to arbitration, and it treated the actual claims advanced in the arbitration as determinative of scope. It also applied the presumption of arbitrability under Singapore law, stating that there will ordinarily be such a presumption so long as a dispute falls within the scope of an arbitration clause. These principles were central to the rejection of the plaintiffs’ jurisdictional and non-arbitrability arguments. (Paras 68, 81, 93)

"The disputes submitted for arbitration determine the scope of the arbitration." — Per Roger Giles IJ, Para 68
"there will ordinarily be a presumption of arbitrability so long as a dispute falls within the scope of an arbitration clause" — Per Roger Giles IJ, Para 81

The court also recognised that non-arbitrability is linked to public policy and to disputes of a public character or disputes affecting persons beyond the immediate disputants. But it did not find those features present here. The dispute was a private commercial claim for damages under the SPAs and the First Letter Agreement, and the court therefore held that the presumption of arbitrability was not rebutted. (Paras 84, 93)

"The presumption of arbitrability is not rebutted. The second submission fails." — Per Roger Giles IJ, Para 93

That reasoning is important because it shows the court’s method: identify the contractual source of the claim, determine whether it falls within the arbitration clause, and then ask whether any public policy reason rebuts arbitrability. On the facts as found, the answer to each step favoured the defendants. The court therefore refused to set aside the award on the basis that the dispute was non-arbitrable. (Paras 75, 81, 84, 93)

Why Does This Case Matter?

This case matters because it demonstrates how Singapore courts approach setting-aside applications in complex cross-border commercial arbitrations involving multiple related agreements, insolvency issues, and allegations of illegality. The court’s analysis reinforces that the operative question is the dispute actually submitted to arbitration, not a party’s attempt to recharacterise the commercial history by reference to earlier agreements. That distinction can be decisive where parties have entered into successive contracts with different dispute-resolution provisions. (Paras 68, 75, 99)

The case also strengthens the practical force of the presumption of arbitrability. The court made clear that, where a dispute falls within an arbitration clause, the presumption will ordinarily apply and will not be displaced merely because the dispute is said to involve illegality or insolvency-related concerns. For practitioners, that means jurisdictional and public policy challenges must be anchored in the actual legal character of the claim, not in broad assertions that the underlying transaction is tainted. (Paras 81, 84, 93)

Finally, the decision illustrates the court’s unwillingness to permit tactical delay or procedural reconfiguration in setting-aside proceedings. The refusal of a further adjournment, the refusal to allow resurrection of an abandoned ground, and the rejection of the natural justice complaints together show a firm case-management stance. In commercial arbitration practice, that is a reminder that setting-aside proceedings are not an opportunity to relitigate the merits or to reopen abandoned positions without a proper basis. (Paras 53, 64, 100, 102)

Cases Referred To

Case Name Citation How Used Key Proposition
PT Prima International Development v Kempinski Hotels SA and other appeals [2012] 4 SLR 98 Used to distinguish an arbitration agreement from the submission to arbitration "The disputes submitted for arbitration determine the scope of the arbitration." (Para 68)
Swissbourgh Diamond Mines (Pty) Ltd and others v Kingdom of Lesotho [2019] 1 SLR 263 Used to explain the breadth of “submission to arbitration” in Article 34(2)(a)(iii) The phrase “submission to arbitration” is not limited to the submission in the particular arbitral proceeding. (Para 70)
Rakna Arakshaka Lanka Ltd v Avant Garde Maritime Services (Pte) Ltd [2019] 2 SLR 131 Used on possible preclusion from raising a jurisdictional challenge in setting-aside proceedings There may be a separate question whether a party is precluded from taking up the challenge in a setting-aside application. (Para 71)
PT First Media TBK (formerly known as PT Broadband Multimedia TBK) v Astro Nusantara International BV and others and another appeal [2014] 1 SLR 372 Used on possible preclusion from raising a jurisdictional challenge in setting-aside proceedings Referred to especially at [132] for the preclusion point. (Para 71)
BTY v BUA and other matters [2019] 3 SLR 786 Used on non-arbitrability and public character of disputes Non-arbitrability concerns disputes of a public character and disputes affecting persons beyond the immediate disputants. (Para 84)
Tomolugen Holdings Ltd and another v Silica Investors Ltd and other appeals [2016] 1 SLR 373 Used for the presumption of arbitrability There will ordinarily be a presumption of arbitrability so long as a dispute falls within the scope of an arbitration clause. (Para 81)
Larsen Oil and Gas Pte Ltd v Petroprod Ltd (in official liquidation in the Cayman Islands and in compulsory liquidation in Singapore) [2011] 3 SLR 414 Used as an insolvency-related comparator Distinguished as involving disputes arising only upon insolvency and collective insolvency concerns. (Para 85)
Offshoreworks Global (L) Ltd v POSH Semco Pte Ltd [2021] 1 SLR 27 Used on the procedural point that foreign corporations appear by solicitors Foreign corporations could not appear otherwise than by solicitors. (Para 48)

Legislation Referenced

Source Documents

This article analyses [2021] SGHCI 17 for legal research and educational purposes. It does not constitute legal advice. Readers should consult the full judgment for the Court's complete reasoning.

Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.