Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Singapore

Thian Sung Construction Pte Ltd v International Elements Pte Ltd [2015] SGHC 319

In Thian Sung Construction Pte Ltd v International Elements Pte Ltd, the High Court of the Republic of Singapore addressed issues of Building and Construction Law — Statutes and regulations.

Case Details

  • Citation: [2015] SGHC 319
  • Title: Thian Sung Construction Pte Ltd v International Elements Pte Ltd
  • Court: High Court of the Republic of Singapore
  • Date of Decision: 17 December 2015
  • Coram: Lee Seiu Kin J
  • Case Number: Originating Summons No 683 of 2015
  • Decision Type: Application to set aside an adjudication determination under the Building and Construction Industry Security of Payment Act
  • Plaintiff/Applicant: Thian Sung Construction Pte Ltd
  • Defendant/Respondent: International Elements Pte Ltd
  • Counsel for Plaintiff/Applicant: Lim Wee Teck (W T Lim & Partners)
  • Counsel for Defendant/Respondent: Raymond Chan (Chan Neo LLP)
  • Legal Area: Building and Construction Law — Statutes and regulations
  • Statutes Referenced (as provided): Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed); Building and Construction Industry Payments Act; Building and Construction Industry Security of Payment Act; Civil Law Act (Cap 43, 1999 Rev Ed); Queensland Act; Queensland Act (as provided)
  • Key Procedural Posture: Supervisory review of an adjudication determination; unusual ground asserted: service of a payment claim by a party allegedly not entitled to do so
  • Judgment Length (metadata): 4 pages, 2,318 words

Summary

In Thian Sung Construction Pte Ltd v International Elements Pte Ltd [2015] SGHC 319, the High Court considered whether an adjudication determination under Singapore’s Building and Construction Industry Security of Payment Act (“the Act”) should be set aside because the payment claim was served by a party that, according to the applicant, had lost the statutory right to make such a claim. The applicant’s argument was novel and tightly framed: it contended that the subcontractor (the respondent) had assigned its trade debts to a bank under a factoring arrangement, and that this assignment divested the subcontractor of the right to serve a payment claim and commence adjudication. If correct, the payment claim would be served in breach of s 10(1) of the Act, depriving the adjudicator of jurisdiction.

The court accepted that the Act’s supervisory jurisdiction can be engaged where a payment claim is “non-existent or inoperative”, and it was prepared to accept the broader proposition that a payment claim served by a party not entitled to do so falls outside the Act. However, the court ultimately rejected the applicant’s core submission that the respondent had divested itself of its rights under the Act. The court held that, although the respondent could not assign the statutory entitlement to progress payments to the bank such that the bank became the “claimant” under the Act, the respondent did not thereby lose its own status as the statutory claimant for the purposes of serving a payment claim. The adjudication determination was therefore not set aside.

What Were the Facts of This Case?

The plaintiff, Thian Sung Construction Pte Ltd, was the main contractor for a condominium development project at Lot 715N TS 25 at Ardmore Park Singapore. Under a letter of award dated 8 November 2011, the plaintiff engaged the defendant, International Elements Pte Ltd, as a subcontractor for the supply and delivery of stone works. The relationship between the parties thus fell squarely within the construction industry context that the Act is designed to regulate.

In May 2013, the defendant entered into a factoring arrangement with United Overseas Bank (“UOB”). Under the agreement, UOB provided credit facilities to the defendant in exchange for the assignment of the defendant’s debts. The factoring arrangement required the defendant to assign all its “present and future trade debts” to UOB. Importantly, the plaintiff was given notice of this assignment on 5 July 2013 by both UOB and the defendant. As a practical matter, the plaintiff thereafter paid amounts due under the defendant’s invoices to UOB for numerous progress payments.

Despite the factoring arrangement, on 24 April 2015 the defendant served Progress Claim No 25 (“PC25”) on the plaintiff for $1,396,259.21. No payment was received in response to PC25. The defendant then commenced adjudication proceedings by filing Adjudication Application No 231 of 2015 on 11 June 2015. The adjudication determination dated 14 July 2015 was in the defendant’s favour.

The plaintiff sought to set aside the adjudication determination. The plaintiff’s case was premised on the unusual contention that because the defendant had assigned its trade debts to UOB, it had lost the right to make a claim under the Act. The plaintiff therefore argued that the defendant’s service of PC25 was invalid and that the adjudicator lacked jurisdiction. The parties agreed that the factual background was undisputed; the dispute was legal in nature.

The first legal issue was whether the alleged breach of s 10(1) of the Act—namely, service of a payment claim by a party not entitled to do so—would render the payment claim “non-existent or inoperative”. This mattered because the court’s supervisory function in the context of security of payment adjudications is limited. The court had to determine whether the asserted defect went to jurisdiction in the relevant sense, as opposed to being a matter that would not justify setting aside the adjudication determination.

The second issue was whether the defendant’s factoring arrangement with UOB divested the defendant of its statutory rights under the Act. The plaintiff’s argument relied on the concept that an assignment of a chose in action carries with it the right to enforce that chose in action. From this, the plaintiff inferred that the right to serve a payment claim and commence adjudication under the Act must have passed to UOB, leaving the defendant without standing to serve PC25.

Related to these issues was a further question of statutory construction: even if the debts were assigned, did the Act permit the statutory entitlement to progress payments to be exercised by an assignee such as a bank? The court had to interpret the definitions of “claimant” and “progress payment” in the Act, and consider whether the factoring arrangement could alter the identity of the statutory claimant.

How Did the Court Analyse the Issues?

Lee Seiu Kin J began by identifying the threshold supervisory principle. The court referred to authority indicating that only certain defects—those that render a payment claim “non-existent or inoperative”—permit the court to intervene. The plaintiff relied on Lee Wee Lick Terence (alias Li Weili Terence) v Chua Say Eng (formerly trading as Weng Fatt Construction Engineering) and another appeal [2013] 1 SLR 401, particularly at [39] and [66], to support the proposition that jurisdictional defects can arise where the payment claim is not properly within the Act.

To support the broader proposition that a payment claim served by an ineligible party falls outside the Act, the plaintiff relied on Gemini Nominees Pty Ltd v Queensland Property Partners Pty Ltd [2008] 1 Qd R 139. That case concerned the Queensland statutory scheme (modelled on the Australian/NSW lineage of security of payment legislation). The Supreme Court of Queensland had declared the claim outside the statutory purview because the claimant was statutorily prohibited from making progress payment claims. The High Court in Singapore indicated it was prepared to accept the general proposition for present purposes, but the real dispute remained whether the defendant’s rights under the Act had actually been divested by the factoring arrangement.

The court then addressed the plaintiff’s argument through the lens of the Civil Law Act. The plaintiff invoked s 4(8) of the Civil Law Act, which provides that an absolute assignment by writing of a debt or other legal chose in action, with notice given to the debtor, is effectual to pass the legal right and remedies to the assignee. The plaintiff’s reasoning was that, once UOB became the assignee of the debts owed by the plaintiff to the defendant, UOB acquired the remedies available to recover those debts, including the statutory remedy of filing a payment claim under s 10(1) of the Act.

However, the court rejected the plaintiff’s attempt to translate the assignment of debts into an assignment of the statutory right to serve payment claims. The judge accepted that the factoring agreement was a legal assignment under s 4(8) of the Civil Law Act, but held that the defendant’s right to avail itself of the Act was not something that could be assigned in the way the plaintiff suggested. This conclusion turned on statutory construction of the Act’s definitions and scheme. Section 10(1) provides that the “claimant” may serve a payment claim. “Claimant” is defined in s 2 as any person who is or claims to be entitled to a progress payment under s 5. Section 5 entitles “any person who has carried out any construction work, or supplied any goods or services” under a contract to a progress payment. The court therefore reasoned that the statutory entitlement is tied to the party that actually performed the work or supplied the goods/services, not merely a party that is owed money under an invoice.

The court also considered the policy objective of the Act: to facilitate cash flow for the parties who actually carry out construction work or supply goods and services. The judge cited commentary (including from Chow Kok Fong, Security of Payments and Construction Adjudication) to reinforce the point that while an assignee such as a bank may assert contractual rights to unpaid progress payments, it cannot make a payment claim under the Act. The court further reasoned that certain procedural mechanisms under the Act would be ill-suited to a third-party assignee who did not actually supply the goods or services. For example, an assignee would not be in a position to dispute a payment response on the merits in the same way, and rights such as suspension of work or supply under s 26 would not apply because the assignee is neither the provider of services nor the supplier of goods.

Having concluded that the defendant could not have assigned its statutory rights under the Act to UOB, the court then addressed the plaintiff’s alternative argument: even if the statutory rights could not be assigned to UOB, did the defendant nonetheless divest itself of those rights by entering into the factoring arrangement? The plaintiff relied on Cottage Club Estates, Limited v Woodside Estates Company (Amersham), Limited (1928) 2 KB 463, where an arbitration award was set aside because giving effect to it would render the owner liable both to the contractor and to the bank under the assignment. The plaintiff argued that, similarly, the defendant’s statutory right to claim under the Act should have passed away such that the defendant could not serve PC25.

Lee Seiu Kin J declined to follow Cottage Club in a way that would divest the defendant of its statutory status. The judge noted that Cottage Club had been criticised by the English Court of Appeal in Shayler v Woolf [1946] Ch 320, particularly regarding its treatment of an arbitration clause as a personal covenant not assignable. More importantly, the court treated the question as one of statutory construction rather than a general common law rule about assignments. The Act had to be construed with its objective in mind: facilitating cash flow in the construction industry. It was not plausible, the court reasoned, that factoring agreements—common in the industry—would disentitle contractors or subcontractors from making payment claims once they assign debts to banks as part of financing arrangements.

The court also distinguished the cases relied upon by the defendant and those cited by the plaintiff. It found Admin Construction Pte Ltd v Vivaldi (S) Pte Ltd [2013] 3 SLR 609, Cant Contracting Pty Ltd v Casella [2006] 2 Qd R 13, and Gemini Nominees to be less relevant because those cases concerned extinguishment or non-existence of the right to the progress payment itself. In contrast, in the present case there was no question that the plaintiff’s obligation to make the progress payment subsisted at the time PC25 was filed and continued thereafter. The factoring arrangement affected who received payment, but did not extinguish the underlying entitlement that the Act is designed to secure.

In essence, the court’s analysis reconciled two ideas: (1) the Act’s statutory claimant identity is anchored in performance/supply under the contract; and (2) assignments of debts for financing should not be treated as a mechanism to defeat the Act’s cash-flow purpose. The court therefore concluded that the defendant remained entitled to serve the payment claim and that the adjudicator’s jurisdiction was not undermined by the factoring arrangement.

What Was the Outcome?

The High Court dismissed the plaintiff’s application to set aside the adjudication determination. The court held that the defendant’s service of PC25 was not invalid on the ground asserted, and that the adjudicator had jurisdiction to determine the payment dispute under the Act.

Practically, the decision meant that the adjudication determination in favour of the defendant stood, and the plaintiff remained liable to satisfy the adjudicated amount (subject to any further procedural steps that might be available under the Act or general civil procedure). The court’s reasoning also clarified that factoring arrangements do not automatically displace the statutory right to serve payment claims under the Act.

Why Does This Case Matter?

Thian Sung Construction is significant because it addresses an “unusual ground” for setting aside an adjudication determination: whether a payment claim is invalid because it was served by a party allegedly not entitled to do so after assigning debts to a bank. The court’s approach provides guidance on the boundary between (a) the assignment of contractual debts and (b) the statutory entitlement to serve payment claims under the Act.

For practitioners, the case is particularly useful in the context of construction financing. Factoring is common in the industry, and banks often require notice of assignment and direct payment. This judgment confirms that, while the bank may receive the proceeds of invoices by virtue of the assignment, the statutory claimant under the Act remains the party that actually carried out the work or supplied the goods/services. Accordingly, contractors and subcontractors should not assume that debt assignment arrangements will deprive them of their ability to invoke the Act if payment is not made.

The decision also reinforces the limited nature of court intervention in security of payment adjudications. Even where a payment claim is challenged on a technical basis, the court will focus on whether the defect truly renders the claim non-existent or inoperative, and whether the statutory scheme supports the asserted jurisdictional consequence. This has implications for how respondents frame set-aside applications and how claimants structure their financing arrangements.

Legislation Referenced

  • Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed)
  • Building and Construction Industry Payments Act (as referenced in the judgment’s discussion of comparative schemes)
  • Civil Law Act (Cap 43, 1999 Rev Ed), s 4(8)
  • Queensland Act (as referenced in comparative authority, including Gemini Nominees)

Cases Cited

  • [2015] SGHC 319 (the present case)
  • Lee Wee Lick Terence (alias Li Weili Terence) v Chua Say Eng (formerly trading as Weng Fatt Construction Engineering) and another appeal [2013] 1 SLR 401
  • Gemini Nominees Pty Ltd v Queensland Property Partners Pty Ltd [2008] 1 Qd R 139
  • Chow Kok Fong, Security of Payments and Construction Adjudication (2nd Ed, 2013) (text cited for commentary)
  • Cottage Club Estates, Limited v Woodside Estates Company (Amersham), Limited (1928) 2 KB 463
  • Shayler v Woolf [1946] Ch 320
  • Admin Construction Pte Ltd v Vivaldi (S) Pte Ltd [2013] 3 SLR 609
  • Cant Contracting Pty Ltd v Casella [2006] 2 Qd R 13

Source Documents

This article analyses [2015] SGHC 319 for legal research and educational purposes. It does not constitute legal advice. Readers should consult the full judgment for the Court's complete reasoning.

Written by Sushant Shukla

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.