Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
Singapore

SOH CHUAN SWEE & Anor v L.S. CONSTRUCTION PTE LTD

In SOH CHUAN SWEE & Anor v L.S. CONSTRUCTION PTE LTD, the district_court addressed issues of .

300 wpm
0%
Chunk
Theme
Font

Case Details

  • Citation: [2025] SGDC 253
  • Title: SOH CHUAN SWEE & Anor v L.S. CONSTRUCTION PTE LTD
  • Court: District Court (State Courts of the Republic of Singapore)
  • Case/Originating process: District Court Originating Claim No 248 of 2022
  • Judgment date: 1 October 2025
  • Judgment reserved: Yes
  • Hearing dates: 6 May 2025, 3 July 2025, 11 September 2025
  • Judge: District Judge Samuel Wee Choong Sian
  • Plaintiffs/Claimants: (1) Soh Chuan Swee; (2) Tok Beng Kee
  • Defendant/Respondent: L.S. Construction Pte Ltd
  • Legal area: Building and Construction Law — construction torts — negligence; torts affecting adjoining land
  • Core allegations: Negligence in (a) vibration-causing works (demolition, concrete piling, and I-beam extraction) and (b) initial repair works
  • Procedural posture: Claimants sued in negligence; nuisance claim was abandoned after AEICs
  • Judgment length: 19 pages, 3,905 words
  • Statutes referenced: Not stated in the provided extract
  • Cases cited: Not stated in the provided extract

Summary

This District Court decision concerns a claim by adjoining owners against a main contractor for alleged property damage said to have been caused by construction activities at a site across the road. The Claimants, Soh Chuan Swee and Tok Beng Kee, alleged that demolition works, concrete piling, and later I-beam extraction (“Vibration Causing Works”) performed by L.S. Construction Pte Ltd between November 2018 and April 2021 caused damage to their house. They also alleged that the Defendant’s “Initial Repair Works” performed in January 2020 were carried out negligently.

The court approached the claim as a negligence case requiring proof of the standard elements: duty of care, breach, causation, and remoteness. On the facts, the court found that the Claimants failed to establish breach of duty and causation in relation to the Vibration Causing Works. In particular, the court accepted that vibrations are expected from the relevant works and that the Claimants’ evidence did not overcome the Defendant’s monitoring data and the timing of the alleged damage. The court also found that the Claimants did not prove negligence in the Initial Repair Works.

Practically, the decision illustrates the evidential burden on adjoining owners in construction tort claims, especially where (i) there is pre-condition documentation showing the adjoining property was generally defect-free at the outset, (ii) the alleged damage manifests at times that do not align neatly with the vibration works, and (iii) the defendant can point to monitoring reports and industry expectations. It also underscores that offers to repair may be made without admission of liability, and that such conduct does not automatically establish negligence.

What Were the Facts of This Case?

The Defendant, L.S. Construction Pte Ltd, was the main contractor for a residential development known as “Affinity at Serangoon”, comprising apartments and strata landed houses, located at Serangoon North Avenue 1. The Claimants lived across the road from the Construction Site, separated by a distance of approximately 12 metres. The Claimants alleged that their house suffered damage as a result of construction activities at the site, particularly works that involved demolition, piling, and the extraction of I-beams from the ground.

Before the works began, a pre-condition survey of the Claimants’ house was conducted in October 2018. The results were recorded in a photographic survey report dated 8 October 2018. The report indicated that the house was generally defect-free at that time, although there were various cracks observed in walls and tiles. This pre-condition documentation became important in assessing whether the alleged damage could have been caused by the Defendant’s later works.

The construction programme proceeded in phases. Demolition works were carried out from November 2018 to April 2019. Piling works were carried out from April 2019 to August 2019. I-beam installation and extraction works occurred from sometime in 2020 to April 2021. The Claimants’ case focused on the vibration effects said to arise during the demolition and piling phases, and more particularly during I-beam extraction.

The first notice of damage occurred in October 2019, approximately two months after the piling period ended and before the I-beam period began. The damage concerned cracks in the common party wall, glass blocks, and floor tiles at the front porch, which led to water seepage during rain. The Claimants also pointed to dust during the demolition period and alleged inadequacies in barriers and netting. However, the court’s narrative indicates that these complaints were not directly tied to the specific damage the Claimants later attributed to vibration-causing works.

The court identified two main issues. First, whether the Defendant performed the Vibration Causing Works negligently. This required the Claimants to establish that the Defendant owed a duty of care in performing those works, that the Defendant breached that duty, that the breach caused the damage to the Claimants’ house, and that the damage was not too remote.

Second, the court considered whether the Defendant performed the Initial Repair Works negligently. The Initial Repair Works were carried out in January 2020 after the Defendant received complaints from the Claimants. The Claimants alleged that these repairs were not carried out with reasonable care, thereby contributing to or failing to properly address the damage.

Although the Claimants initially relied on a nuisance claim, they abandoned it after the affidavits of evidence-in-chief were filed. As a result, the case proceeded on negligence principles, with the court focusing on duty, breach, causation, and remoteness.

How Did the Court Analyse the Issues?

On the Vibration Causing Works, the court examined the negligence framework and the evidence relevant to each element. The Claimants contended that they had proven the requisite elements: duty of care, breach, causation, and remoteness. The Defendant’s response was two-fold. Its primary position was that the Claimants had not proven breach of duty and causation, seeking to dispose of the claim without addressing whether a duty of care existed. Its alternative position was that it did not owe a duty of care in relation to the performance of the vibration works because those works were undertaken by independent subcontractors.

In analysing breach, the court emphasised that vibrations are expected from the relevant construction activities. The First Claimant, who had extensive experience in the construction industry, accepted during cross-examination that vibrations are expected from the Vibration Causing Works. This acceptance mattered because it shaped the court’s view of what reasonable care required: not the elimination of all vibration, but the taking of reasonable precautions to manage vibration within acceptable limits and in accordance with industry practice.

The court found that the Claimants failed to prove that the Defendant breached its duty of care by failing to act in accordance with industry practices when performing the Vibration Causing Works. While the extract does not reproduce the full reasoning, it indicates that the court considered the nature of the works, the expected presence of vibration, and the evidence offered by the Claimants to show that the Defendant fell below the required standard.

Turning to causation, the court considered the timing and the evidential quality of the Claimants’ allegations. The Claimants first noticed damage in October 2019, before the I-beam extraction period began. This timing undermined the proposition that the later I-beam extraction was the cause of the initial damage. The court also considered that before October 2019 there were no complaints tied to the Vibration Causing Works, and that complaints about dust and barriers during demolition were not shown to relate to the alleged vibration-caused damage.

The Claimants then relied on two episodes of alleged vibration. In March 2020, the First Claimant experienced vibrations said to have caused cracks in the granite floor. The alleged vibrations were said to occur when I-beams were being extracted. The First Claimant testified that the vibrations were strong enough to cause a lighting fixture to sway vigorously on 5, 6, and 16 March 2020, and he submitted video footage. The court found the video footage not particularly helpful because it merely showed swaying of the lighting fixture, which could have been caused by various factors given the design of the fixture.

Further, the court relied on monitoring reports produced by the Defendant. These reports indicated that vibrations at the perimeter of the construction site were lower than 2mm/s and within a limit of 5mm/s. This monitoring evidence was significant because it provided an objective measure of vibration levels, which the Claimants’ lay observations and video evidence did not displace. The court also noted that due to the Covid-19 Circuit Breaker, the Defendant did not inspect the alleged damage until September 2020, but that delay did not, on the evidence, establish that the vibration caused the damage.

In March 2021, the First Claimant again alleged vibrations on 29 March 2021 during I-beam extraction. Again, the Defendant’s monitoring reports showed vibration levels at the perimeter below 2mm/s and within the 5mm/s limit. The court therefore treated both alleged vibration episodes as not sufficiently supported by evidence that vibration levels exceeded reasonable limits or that the alleged damage was causally linked to the vibration works.

The court also dealt with the Claimants’ dissatisfaction with the Defendant’s proposed further repairs. In April 2021, the Defendant provided a draft method statement for further repair works, including repairs to cracks, painting, and waterproofing chemicals, but excluding works for cracks in floor tiles. The First Claimant did not agree to the draft scope. The Defendant later withdrew assistance because it disputed the cause and extent of damage relied on by the Claimants. Importantly, the Defendant’s offer to perform repairs was made on a “goodwill” basis and, in at least one letter, on a “without prejudice and without admission of liability” basis. This supported the court’s view that the repair offers did not amount to admissions of negligence.

On the Initial Repair Works, the court considered whether the Defendant’s repairs were carried out negligently. The extract indicates that the Defendant performed minor repairs in January 2020 to patch cracks and address water seepage after inspection by its staff. The court’s conclusion (as reflected in the summary) was that the Claimants did not prove negligence in these initial repairs. The practical implication is that even if damage existed, the Claimants still had to show that the Defendant’s repair work fell below the required standard and that such failure caused or worsened the damage.

What Was the Outcome?

Having considered the evidence on breach and causation, the court dismissed the Claimants’ claim. The court held that the Claimants failed to prove that the Defendant negligently performed the Vibration Causing Works. The Claimants also failed to prove that the Defendant negligently performed the Initial Repair Works.

As a result, the Defendant was not found liable in negligence for the alleged damage to the Claimants’ house. The decision leaves adjoining owners with a clear message: where objective monitoring data and pre-condition surveys exist, and where the timing of damage does not align with the alleged vibration episodes, negligence claims will require robust, causally persuasive evidence.

Why Does This Case Matter?

This case is useful for practitioners because it demonstrates how Singapore courts evaluate construction tort claims involving adjoining land. The court’s reasoning reflects a structured approach: it does not treat vibration as inherently wrongful, but instead examines whether the contractor acted in accordance with industry practice and whether the claimant can prove causation beyond temporal association.

For claimants, the decision highlights evidential pitfalls. Pre-condition surveys can significantly affect the analysis of whether damage existed before the works. Monitoring reports that quantify vibration levels can be decisive, particularly where claimants rely on subjective observations or non-specific visual evidence. The court’s treatment of the lighting fixture video footage illustrates that evidence must be capable of supporting a causal inference, not merely showing an effect that could have multiple causes.

For defendants, the case reinforces the value of contemporaneous documentation and careful communications. The “without prejudice and without admission of liability” framing of repair offers, and the presentation of vibration monitoring data, can help rebut negligence allegations. More broadly, the decision supports the proposition that contractors are not insurers of adjoining property; liability in negligence requires proof of breach and causation on the balance of probabilities.

Legislation Referenced

  • Not stated in the provided extract.

Cases Cited

  • Not stated in the provided extract.

Source Documents

This article analyses [2025] SGDC 253 for legal research and educational purposes. It does not constitute legal advice. Readers should consult the full judgment for the Court's complete reasoning.

Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.