Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Singapore

Sin Herh Construction Pte Ltd v Hyundai Engineering & Construction Co Ltd and another [2017] SGHC 3

In Sin Herh Construction Pte Ltd v Hyundai Engineering & Construction Co Ltd and another, the High Court of the Republic of Singapore addressed issues of Civil procedure — Injunctions, Civil procedure — Judgments and orders.

Case Details

  • Citation: [2017] SGHC 3
  • Case Title: Sin Herh Construction Pte Ltd v Hyundai Engineering & Construction Co Ltd and another
  • Court: High Court of the Republic of Singapore
  • Date of Decision: 09 January 2017
  • Judge: Kan Ting Chiu SJ
  • Coram: Kan Ting Chiu SJ
  • Case Number: Originating Summons No 14 of 2016
  • Procedural Posture: Application for an interim injunction restraining a call on a performance bond and for an Erinford Order; appeal dismissed
  • Parties: Sin Herh Construction Pte Ltd (Plaintiff/Applicant); Hyundai Engineering & Construction Co Ltd (1st Defendant/Respondent); China Taiping Insurance (Singapore) Pte Ltd (2nd Defendant)
  • Legal Areas: Civil procedure — Injunctions; Civil procedure — Judgments and orders; Credit and security — Bonds
  • Relief Sought: Interim injunction to restrain the holder of the performance bond from making a call and to restrain the insurer from paying; Erinford Order
  • Bond Type: Performance bond
  • Bond Amount: S$404,035.01
  • Bond Expiry and Extension: Initially 9 July 2015; extended to 9 October 2015; demand allowed up to 90 days after expiry (latest demand date: 7 January 2016)
  • Underlying Contract: Agreement dated 8 April 2013 for reinforced concrete works at “Punggol Central/Punggol Walk – Waterway Point 2 Watertown”
  • Demand Date: 5 January 2016
  • Application Date: 8 January 2016
  • Key Allegations by Applicant: The call was unconscionable because (a) there was an alleged understanding not to call the bond; and (b) the 1st Defendant imposed back-charges that were allegedly not entitled to or grossly inflated
  • Supplementary Sub-Contract Agreement: Dated 30 June 2015
  • 2nd Defendant’s Role: Issuer of the bond; did not participate in the proceedings
  • Counsel: Lee Mun Hooi, Goh Teck Wee and Wong Tze Roy (Lee Mun Hooi & Co) for the Plaintiff; Chan Kah Keen Melvin and Tan Pei Qian Rachel (TSMP Law Corporation) for the First Defendant
  • Appeal Note: The appeal to this decision in Civil Appeal No 97 of 2016 was dismissed by the Court of Appeal on 27 July 2017 with no written grounds of decision rendered
  • Judgment Length: 8 pages, 3,869 words

Summary

In Sin Herh Construction Pte Ltd v Hyundai Engineering & Construction Co Ltd and another [2017] SGHC 3, the High Court refused to grant an interim injunction to restrain the holder of a performance bond from calling on it, and also refused to grant an Erinford Order. The applicant, Sin Herh Construction Pte Ltd (“Sin Herh”), sought to stop Hyundai Engineering & Construction Co Ltd (“Hyundai”) from receiving payment under a performance bond issued by China Taiping Insurance (Singapore) Pte Ltd (“China Taiping”).

The court’s central focus was whether Hyundai’s call on the performance bond was “unconscionable” such that the court should intervene notwithstanding the general principle that performance bonds are intended to be cash-like and are payable on demand. Sin Herh advanced two main grounds: first, that there was an alleged understanding between the parties that Hyundai would not call the bond pending finalisation of accounts; and second, that Hyundai’s back-charges were unreasonable, inflated, and therefore the demand was unconscionable.

Kan Ting Chiu SJ held that Sin Herh failed to establish the necessary evidential basis for unconscionability. The alleged “understanding” was not reflected in the written Supplementary Sub-Contract Agreement and was undermined by the parties’ subsequent conduct and correspondence. The back-charge dispute, on the evidence available, did not clearly negate Hyundai’s contractual entitlement to impose or recover such costs. Accordingly, the court refused both the interim injunction and the Erinford Order.

What Were the Facts of This Case?

Sin Herh and Hyundai were parties to an agreement dated 8 April 2013 under which Sin Herh was engaged to carry out reinforced concrete works for a construction project known as “Punggol Central/Punggol Walk – Waterway Point 2 Watertown”. As security for due performance, Sin Herh provided a performance bond. The bond was issued by China Taiping in the sum of S$404,035.01. The bond was initially due to expire on 9 July 2015 and was later extended to 9 October 2015. Importantly, the bond allowed demand to be made at any time up to 90 days after expiry, meaning the latest demand date was 7 January 2016.

It was common ground that Sin Herh did not carry out the contracted works in compliance with the agreement. Sin Herh missed set deadlines for the works and withdrew a substantial number of workers from the worksite. These performance issues caused concern for Hyundai and led to two meetings between senior officials on 29 and 30 June 2015. The meetings culminated in a written Supplementary Sub-Contract Agreement dated 30 June 2015 (“the Supplementary Agreement”).

The Supplementary Agreement addressed both completion of outstanding works and a revised payment schedule. It provided that Sin Herh would complete remaining works, including dismantling formwork, material clearance and defect clearance, in accordance with specified schedules and manpower plans. It also set out payment commitments by Hyundai: Hyundai would make a payment of S$550,000 (inclusive of GST) certified under a payment certificate for April 2015 work, and would issue a further payment certificate for S$300,000 (inclusive of GST) for the remaining RC works, with payment due within a defined window. The Supplementary Agreement further stated that a prior payment certificate would be withdrawn by mutual consent and that, apart from the specified payments, Hyundai would not be obliged to make further payments and Sin Herh would not be entitled to further claims until a final payment certificate was issued after the final account agreement.

Sin Herh’s case was that, alongside the Supplementary Agreement, there was an additional “understanding” that Hyundai would not call on the performance bond pending finalisation of accounts. Sin Herh alleged that this understanding was reached during the meetings and was not recorded in the Supplementary Agreement. In contrast, Hyundai’s position was that the meetings were primarily to address Sin Herh’s delay and threats to stop work unless more monies were paid, and that the Supplementary Agreement embodied the parties’ agreed payment and completion arrangements.

After the bond’s extension period, Hyundai made a demand on 5 January 2016. Sin Herh applied for an interim injunction on 8 January 2016 to restrain Hyundai from receiving payment and China Taiping from making payment. Sin Herh’s application was premised on the allegation that Hyundai’s call was unconscionable.

The key legal issue was whether the court should grant an interim injunction to restrain the holder of a performance bond from calling on it. This required the court to consider whether the call was “unconscionable” in the relevant legal sense. Performance bonds are generally enforceable according to their terms, and the court’s intervention is exceptional. The applicant therefore bore a heavy evidential burden to show that the demand fell within the narrow category warranting injunctive relief.

A second related issue was whether the court should grant an Erinford Order. Erinford Orders are a procedural mechanism in which the court may require the defendant to provide security or disclose information in circumstances where the court is concerned about the risk of irreparable harm or where the injunction is refused but the court still seeks to manage the risk of injustice. The applicant sought such an order in addition to the injunction.

Underlying both issues was the factual dispute about the alleged “understanding” not to call the bond and the dispute about back-charges. The court had to assess whether these disputes, on the evidence, demonstrated unconscionability rather than merely showing that there was a contractual disagreement between the parties.

How Did the Court Analyse the Issues?

Kan Ting Chiu SJ began by addressing the alleged understanding. The judge noted that it was common ground that Sin Herh had not complied with the contract. Against that background, the court examined the meetings and the Supplementary Agreement. The Supplementary Agreement, on its face, set out detailed terms on completion obligations and a revised payment schedule. It also contained provisions that limited further payments and claims until the final account agreement and final payment certificate were issued.

Sin Herh’s director, Pan Zhengwen (“Pan”), deposed that there was an understanding reached with Hyundai’s representative that there would be no call on the performance bond pending finalisation of accounts. Pan’s first affidavit described this as an understanding that “pending the finalisation of the accounts for the Final Accounts Agreement, there shall be no call on the Performance Bond”. In a second affidavit, Pan stated that the understanding was reached between himself and Hyundai’s Mr J.H. Park and that he would have refused to renew the bond if Hyundai did not agree. Pan further suggested that the understanding was implicit in the arrangement and that he did not query why it was not reflected in Hyundai’s letter dated 30 June 2015.

The court found this narrative problematic. The judge emphasised that the term “understanding” was not precise: it did not specify whether it was unilateral or bilateral, nor whether it was intended to be binding. More importantly, if the suspension of demands on the bond was sufficiently important to be agreed, it would have been expected to appear in the Supplementary Agreement. The judge observed that the Supplementary Agreement did not include any term suspending Hyundai’s right to call on the bond.

Hyundai’s evidence, through its project manager Park Ji Hong (“Park”), was that the meetings’ main purpose was to address Sin Herh’s delay, threats to stop work, and Sin Herh’s request for more payment. Park stated that the agreement reached concerned the construction program, manpower mobilisation plan, and payment schedule, and that the Supplementary Agreement embodied those matters. The judge accepted that the Supplementary Agreement’s detailed terms were consistent with Hyundai’s account of the meetings’ purpose.

Crucially, the judge noted that Sin Herh had never written to record the alleged understanding or to object that it was not embodied in the Supplementary Agreement. This absence of contemporaneous documentation and the lack of recorded objection undermined Sin Herh’s reliance on the alleged understanding. The judge therefore concluded that the description of an “understanding”, the absence of any such term in the Supplementary Agreement, and the subsequent correspondence between the parties collectively weakened Sin Herh’s assertion and reliance.

Turning to the back-charges, Sin Herh argued that Hyundai imposed back-charges that were unreasonable and/or inflated, and that these back-charges were not entitled to or were grossly inflated. Sin Herh pointed to a purported spike in back-charges from about S$413,601.96 in June 2015 to about S$4,241,305.93 in December 2015, and itemised categories such as concrete wastage, rebar wastage, labour backcharges and material supply. Sin Herh’s submissions framed this as unconscionable conduct by Hyundai.

The court, however, treated the back-charge dispute with caution. The judge observed that Sin Herh’s unconscionability argument was ambiguous: it could mean that Hyundai had no right to impose any back-charges, or that Hyundai had fabricated or falsely inflated them. Yet the evidence did not clearly establish that Hyundai had no contractual basis for back-charges. The judge noted that Pan’s affidavits repeatedly referred to “unjustifiable back-charges” in connection with quantum, rather than providing a direct assertion that no back-charges could be made at all.

In assessing contractual entitlement, the judge referred to the agreement’s clause on back-charges. The extracted portion indicates that Clause 21.3 provided that Hyundai could, in lieu of termination notice, take whole or part of the works out of Sin Herh’s hands and recover reasonable costs of so doing from Sin Herh, or deduct such costs from monies otherwise due. This contractual framework suggested that back-charges were contemplated by the contract and were not inherently unlawful or unconscionable.

Accordingly, the judge’s analysis implied that the dispute was, at its core, a disagreement about the reasonableness or quantum of costs—an issue that could be litigated but did not automatically equate to unconscionability for the purpose of restraining a bond call. The court was not persuaded that the evidence showed a level of impropriety that would justify injunctive intervention in the bond’s cash-like function.

Finally, because the court did not find unconscionability established on the evidence, it followed that there was no basis to grant an Erinford Order. The judge’s refusal of the injunction and the Erinford Order reflected the same underlying conclusion: Sin Herh had not demonstrated the exceptional circumstances required to interfere with the performance bond mechanism.

What Was the Outcome?

The High Court refused to restrain Hyundai, as the holder of the performance bond, from making a call on the bond. The court also refused to grant an Erinford Order. Practically, this meant that Hyundai was not prevented from receiving payment under the performance bond, and China Taiping was not restrained from making payment pursuant to the bond terms.

The decision therefore reinforced the principle that courts will not readily interfere with performance bonds on demand. Where the applicant’s case rests on disputed contractual matters—such as alleged understandings not reflected in written terms or disputes over back-charges—the court will require clear evidence of unconscionability before granting exceptional relief.

Why Does This Case Matter?

This case is significant for practitioners dealing with performance bonds and interim injunctions in Singapore. It illustrates the high threshold for obtaining injunctive relief to restrain a bond call. Even where there is a serious dispute between the parties about performance, payments, and back-charges, the court will not treat those disputes as sufficient to show unconscionability unless the evidence clearly demonstrates conduct that is sufficiently egregious to warrant intervention.

Sin Herh’s reliance on an alleged “understanding” not to call the bond is a particularly instructive aspect. The court’s reasoning underscores the evidential importance of contemporaneous documentation and consistency with the written contractual instruments. Where parties have a detailed supplementary agreement governing payment and completion, the absence of any term suspending bond calls will be a powerful factor against claims that such a suspension was agreed but omitted.

For law students and litigators, the case also provides a practical reminder about the interaction between substantive contractual disputes and procedural remedies. Unconscionability is not established merely by showing that a demand is disputed or that the underlying quantification is contested. Instead, the applicant must show more—something that goes beyond a “triable issue” and reaches the exceptional level required to restrain a bond call.

Legislation Referenced

  • No specific statutory provisions were identified in the provided judgment extract.

Cases Cited

  • [2017] SGHC 3 (the decision itself)

Source Documents

This article analyses [2017] SGHC 3 for legal research and educational purposes. It does not constitute legal advice. Readers should consult the full judgment for the Court's complete reasoning.

Written by Sushant Shukla

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.