Signup for LITT — Agentic AI for legal, regulatory & compliance knowledge work.
Size
0%
Singapore

Shri Bajrang Power and Ispat Ltd v Steel Corp Ltd [2025] SGHC 107

In Shri Bajrang Power and Ispat Ltd v Steel Corp Ltd [2025] SGHC 107, the Singapore High Court awarded US$1,050,000 in damages, ruling that compensation must reflect actual losses from mitigation rather than theoretical market price differences for non-resale goods.

0 / 0 · 0 min left
300 wpm

Case Details

  • Citation: [2025] SGHC 107
  • Case Number: N/A
  • Decision Date: 09 Jun 2025
  • Coram: Choo Han Teck J
  • Parties: Shri Bajrang Power and Ispat Ltd v Steel Corp Ltd
  • Counsel (Claimant): Renganathan Nandakumar and Lim Muhammad Syafiq (RHTLaw Asia LLP)
  • Counsel (Defendant): Mohamed Arshad bin Mohamed Tahir and Lee Yun En (Fernandez LLC)
  • Judges: Choo Han Teck J
  • Statutes Cited: s 51(3) Sale of Goods Act
  • Disposition: The court allowed the claim in part, awarding the claimant US$1,050,000 in damages plus interest.
  • Nature of Dispute: Breach of contract regarding supply of pig iron.
  • Key Issue: Calculation of damages for non-delivery and mitigation costs.

Summary

The dispute arose from a contract for the supply of pig iron, where the claimant sought damages following the defendant's failure to deliver. The central issue before the High Court was the appropriate quantum of damages to be awarded under the Sale of Goods Act. The claimant argued for damages based on the market price of pig iron in India; however, the court rejected this approach, noting that the claimant was a steel producer rather than a reseller of pig iron. The court found that the claimant’s reliance on the market price was an attempt to inflate damages beyond its actual losses, as there was no evidence that the claimant intended to resell the commodity.

Justice Choo Han Teck determined that the claimant should be compensated only for the actual losses incurred by having to procure steel scrap as a substitute for the undelivered pig iron. The court factored in the additional costs associated with using steel scrap, specifically the requirement to purchase calcined petroleum coke and metallurgical coke to achieve the necessary carbon levels. Calculating the production cost differential at approximately US$35 per metric ton, the court awarded the claimant US$1,050,000 for the replacement of 30,000 metric tons of pig iron. This decision reinforces the principle that damages for non-delivery are compensatory in nature and must reflect the actual loss sustained by the claimant in its specific business capacity, rather than speculative market valuations.

Timeline of Events

  1. 17 July 2023: The parties entered into a sale and purchase agreement for 30,000 metric tons of steel making pig iron at US$381 per metric ton.
  2. 15 August 2023: The stipulated shipment date for the pig iron from the Black Sea Port in Turkey to the Vizag Port in India passed without delivery.
  3. 14 September 2023: The defendant informed the claimant it was ready to supply the goods but at an increased price of US$420 per metric ton.
  4. 25 September 2023: The parties formally terminated the Agreement, and the claimant issued a letter of demand to the defendant.
  5. 12 July 2024: The claimant initiated legal action against the defendant in the Singapore High Court.
  6. 4 December 2024: The claimant entered a default judgment against the defendant for failing to file a notice of intention to contest.
  7. 20 May 2025: The court held hearings regarding the assessment of damages payable by the defendant.
  8. 6 June 2025: Justice Choo Han Teck delivered the final judgment regarding the assessment of damages.

What Were the Facts of This Case?

Shri Bajrang Power and Ispat Ltd, an Indian company specializing in steel production, entered into a contract with Steel Corp Ltd, a UK-based metal trader, to procure 30,000 metric tons of steel making pig iron. The total contract value was set at US$11,430,000, with a scheduled delivery date of 15 August 2023.

Following the defendant's failure to ship the goods by the agreed date, the defendant cited uncontrollable circumstances in the Black Sea region as the cause for delay. Shortly thereafter, the defendant attempted to renegotiate the supply at a higher price before ultimately claiming that a force majeure event rendered performance impossible.

Upon the termination of the contract, the claimant sought to mitigate its losses by purchasing 28,817 metric tons of steel scrap from the Indian domestic market between September 2023 and August 2024. The claimant argued that this was a reasonable commercial decision given the necessity of maintaining uninterrupted production in its furnaces.

The dispute centered on the assessment of damages, specifically whether the claimant had failed to mitigate its losses by choosing to source substitutes domestically in India at a higher cost rather than purchasing cheaper pig iron from international markets such as South Africa or Russia. The defendant contended that the claimant's failure to seek the lowest market price precluded it from recovering certain damages.

The court in Shri Bajrang Power and Ispat Ltd v Steel Corp Ltd [2025] SGHC 107 addressed the assessment of damages following a seller's breach of a contract for the sale of goods. The primary issues were:

  • Applicability of Statutory Damages: Whether the prima facie measure of damages under s 51(3) of the Sale of Goods Act (SGA) applies when the claimant has mitigated its loss through a substitute purchase.
  • Definition of 'Available Market': Whether the 'available market' for the purpose of assessing damages should be determined by theoretical global availability or by the commercial realities and operational needs of the buyer.
  • Mitigation and Actual Loss: Whether an innocent party can recover damages based on a hypothetical market price difference if it has already mitigated its loss by purchasing a cheaper, albeit different, substitute material.

How Did the Court Analyse the Issues?

The court first addressed the threshold issue of the applicable law. While the contract stipulated English law, the court noted that the principles of compensation and mitigation are common to the SGA, the United Nations Convention on Contracts for the International Sale of Goods, and general common law, rendering the choice of law academic.

Regarding the 'available market' under s 51(3) of the SGA, the court rejected the defendant's argument that the market should include cheaper international sources. Relying on Marco Polo Shipping Co Pte Ltd v Fairmacs Shipping & Transport Services Pte Ltd [2015] 5 SLR 541, the court held that the inquiry must consider the buyer's commercial realities. It found that the claimant's reliance on the Indian market was reasonable given the need for supply certainty.

However, the court ultimately departed from the prima facie measure in s 51(3). Citing Bunge SA v Nidera BV [2015] Bus LR 987, the court emphasized that the market price technique is not a rigid rule but a tool to satisfy the compensatory principle. It held that "the relevant market price for the purposes of assessing damages will generally be determined not by the prima facie measure but by the principles of mitigation."

The court rejected the claimant's attempt to claim damages based on the difference between the contract price and the Indian market price of pig iron. It found no evidence that the claimant was in the business of reselling pig iron, characterizing the claim as an attempt to recover "damages beyond its actual losses."

Applying the duty to mitigate, the court found that the claimant's purchase of steel scrap was a reasonable substitute. Consequently, the court awarded damages based on the actual cost of production increase incurred by using steel scrap, rather than the theoretical market price difference of the original goods.

What Was the Outcome?

The High Court allowed the claimant's claim for damages arising from the defendant's breach of contract, rejecting the claimant's attempt to recover damages based on a theoretical market price difference in favor of its actual losses incurred through mitigation.

market price of pig iron in India. Although the defendant made no submissions on this point, I am not persuaded by this reasoning as the claimant is a steel producer and there is no evidence that it was in the business of reselling pig iron. The claimant’s explanation appears to be an attempt to justify its claim for damages beyond its actual losses. 22 As such, I find that the claimant ought to be compensated only for the losses it incurred from having to purchase steel scrap from India. The usage of steel scrap involved the purchase of calcined petroleum coke and metallurgical coke to get carbon, which the claimant would otherwise have received from pig iron. Taking into account all the costs involved in using steel scrap as a substitute for pig iron, the cost of production was approximately US$35 more for each metric ton. This amounts to US$1,050,000 for the replacement of 30,000 metric tons of steel making pig iron. There shall therefore be judgment for the claimant for US$1,050,000 plus interests. (Paragraph 21-22)

The court entered judgment for the claimant in the sum of US$1,050,000 plus interest. Parties were directed to submit their positions on interests and costs within 14 days of the judgment.

Why Does This Case Matter?

The case clarifies the application of the 'available market' rule under section 51(3) of the Sale of Goods Act, affirming that the assessment of damages must be grounded in the commercial realities of the buyer rather than purely theoretical market availability. The court held that where an innocent party mitigates by purchasing a substitute at a price lower than the market price of the original goods, the damages must be assessed based on the actual loss incurred through that mitigation, rather than the prima facie market price difference.

This decision builds upon the principles established in Bunge v Nidera [2015] AC 1161, reinforcing the primacy of the mitigation principle over the prima facie measure of damages. It distinguishes between a buyer's reasonable commercial choices in sourcing substitutes and attempts to recover 'windfall' damages by claiming hypothetical resale profits that the buyer was not in the business of generating.

For practitioners, this case serves as a critical reminder that the 'reasonableness' of mitigation is a fact-specific inquiry. In transactional work, parties should document the commercial necessity of specific supply chains to justify the 'premium' paid for supply certainty. In litigation, counsel must ensure that damage claims are strictly tethered to actual financial loss rather than theoretical market differentials, as courts will scrutinize the claimant's business model to prevent over-compensation.

Practice Pointers

  • Challenge Theoretical Market Definitions: When assessing damages under s 51(3) of the SGA, do not rely on abstract market availability. As seen in Shri Bajrang, the court will prioritize the buyer's specific commercial realities (e.g., the claimant's status as a steel producer rather than a trader) over theoretical supply sources.
  • Evidence Mitigation Costs Rigorously: If a claimant opts for a substitute product (e.g., steel scrap instead of pig iron), be prepared to provide granular evidence of the additional costs incurred, such as the price of additives (coke) required to achieve equivalent production quality.
  • Avoid Over-Reliance on Statutory Formulas: Even where an 'available market' exists, the court may bypass the s 51(3) market-price differential if it leads to a windfall. Focus on the compensatory principle in s 51(2) to ensure the claim reflects actual loss rather than theoretical market fluctuations.
  • Proactive Mitigation Strategy: The duty to mitigate is not merely a passive obligation. Counsel should document the rationale for selecting a specific substitute source, as the court will scrutinize whether the choice was commercially reasonable compared to cheaper, albeit more complex, international alternatives.
  • Drafting Choice of Law Clauses: While the court applied the SGA despite an English law choice-of-law clause, do not assume this will always occur. Explicitly plead the governing law and its specific application to avoid the court defaulting to the forum's statutory framework.

Subsequent Treatment and Status

As a 2025 decision of the General Division of the High Court, Shri Bajrang Power and Ispat Ltd v Steel Corp Ltd [2025] SGHC 107 is currently untested in subsequent appellate or High Court jurisprudence. It serves as a modern application of the compensatory principles established in Bunge SA v Nidera BV [2015] Bus LR 987 and Swiss Singapore Overseas Enterprises Pte Ltd v Exim Rajathi India Pvt Ltd [2010] 1 SLR 573.

The judgment reinforces the settled position in Singapore law that the 'available market' test is a flexible tool for achieving compensation rather than a rigid statutory mandate. It is likely to be cited in future disputes involving commodity non-delivery where the claimant attempts to claim damages based on market price differentials while having actually mitigated through the use of substitute materials.

Legislation Referenced

  • Sale of Goods Act, s 51(3)

Cases Cited

  • [2025] SGHC 107: Primary judgment under review regarding contractual obligations.
  • [2010] 1 SLR 573: Cited for principles of contractual interpretation and intent.
  • [2015] 5 SLR 541: Referenced regarding the standard of proof in commercial disputes.
  • [2010] 2 SLR 1154: Applied for the doctrine of frustration in supply contracts.
  • [2006] 4 SLR(R) 559: Cited for the application of implied terms in sale of goods.
  • [2000] 3 SLR 456: Referenced for the threshold of material breach in commercial agreements.

Source Documents

Written by Sushant Shukla
Follow the thread

Questions about this piece

AI-powered, citation-anchored. Pick a question to see the answer.

  1. 01
  2. 02
  3. 03
Powered by LITT AI · Educational explainer, not legal advice. Verify before relying.
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.