Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
Singapore

Shanghai Chong Kee Furniture & Construction Pte Ltd v Church of St Teresa [2024] SGHC 5

In Shanghai Chong Kee Furniture & Construction Pte Ltd v Church of St Teresa, the High Court of the Republic of Singapore addressed issues of Building and Construction Law — Performance bond, Injunctions — Unconscionability.

300 wpm
0%
Chunk
Theme
Font

Case Details

  • Citation: [2024] SGHC 5
  • Court: High Court (General Division)
  • Originating Application No: 876 of 2023
  • Title: SHANGHAI CHONG KEE FURNITURE & CONSTRUCTION PTE LTD v CHURCH OF ST TERESA
  • Judges: Wong Li Kok, Alex JC
  • Date of Judgment: 11 January 2024
  • Hearing Dates: 7, 17 November, 6 December 2023
  • Applicant/Claimant: Shanghai Chong Kee Furniture & Construction Pte Ltd
  • Respondent/Defendant: Church of St Teresa
  • Legal Area(s): Building and Construction Law; Injunctions; Performance bonds
  • Key Topics: Performance bond; injunctions; unconscionability; “Erinford injunctions”; Covid-19 reliefs under COTMA; liquidated damages; warranties; retention and bond call reduction
  • Interim Relief: Interim injunction granted on 30 August 2023 (pending determination of HC/OA 876/2023)
  • Final Decision at First Instance: Application dismissed; call on the performance bond not restrained
  • Bond Details: Unconditional performance bond issued by Lonpac Insurance Bhd for S$629,998.70
  • Contract Context: Restoration works at the Church; contract signed 19 August 2019; completion date 2 September 2020
  • Architect: Jiudong LLP
  • Contract Conditions: Articles and Conditions of Contract for Minor Works 2012 (First Edition, December 2012) published by the Singapore Institute of Architects
  • Statutory/Regulatory Context: Covid-19 (Temporary Measures) Act 2020 (COTMA); Insolvency, Restructuring and Dissolution Act 2018 (moratorium)
  • Judgment Length: 41 pages; 11,889 words

Summary

This High Court decision concerns a contractor’s attempt to restrain an employer from calling on an unconditional performance bond. The contractor, Shanghai Chong Kee Furniture & Construction Pte Ltd (“Shanghai Chong Kee”), sought a declaration and injunction on the basis that the Church of St Teresa (“the Church”) had acted unconscionably by calling on the whole of a performance bond issued by Lonpac Insurance Bhd (“Lonpac”) for S$629,998.70. The bond was provided under a contract for restoration works at the Church’s premises, governed by the Singapore Institute of Architects’ Minor Works 2012 conditions.

The court dismissed the contractor’s application. While an interim injunction had been granted earlier, the judge found that the contractor failed to establish a “strong prima facie case” of unconscionability. The court also addressed related arguments about entitlement to liquidated damages, the effect of Covid-19 reliefs under COTMA, issues relating to outstanding rectification works and warranties, and whether the bond call should be reduced to reflect retention sums already held by the employer.

In practical terms, the decision reinforces the high threshold for obtaining an injunction to restrain payment under an unconditional performance bond. It also illustrates that disputes about underlying contractual entitlements—such as liquidated damages, warranties, and rectification scope—will generally not suffice unless they clearly demonstrate unconscionable conduct in the bond call itself.

What Were the Facts of This Case?

On 19 August 2019, Shanghai Chong Kee and the Church entered into a contract for restoration works (“the Project”) at the Church’s premises. The contract incorporated the Articles and Conditions of Contract for Minor Works 2012 (First Edition, December 2012) published by the Singapore Institute of Architects (“the Conditions of Contract”). The contract set a commencement date of 3 September 2019 and a completion date of 2 September 2020.

Clause 26 of the Conditions of Contract required the contractor to provide a performance bond in the amount of 10% of the contract sum. The contract sum was S$6,299,987.00, so the bond amount was S$629,998.70. Shanghai Chong Kee delivered the performance bond dated 9 October 2019 to the Church. The parties agreed that the bond was unconditional and irrevocable: Lonpac undertook to pay “in full forthwith upon demand in writing” up to the maximum aggregate of S$629,998.70.

The bond’s validity was initially from 3 September 2019 to 2 September 2021 and was later extended until 31 July 2023. The contract also appointed Jiudong LLP as architect (“the Architect”), with duties that included administering the contract as agent of the employer, issuing interim and final certificates, assessing defective work, and issuing certificates of liquidated damages entitlement. The Architect’s certificates were contractually binding in the absence of fraud or improper pressure or interference.

Progress on the Project was delayed due to Covid-19 restrictions. Around 9 January 2022, Shanghai Chong Kee submitted a Notification for Relief under s 9 of COTMA to the Church seeking Covid-19 relief. Separately, the contractor encountered business difficulties and was placed under a moratorium pursuant to s 64 of the Insolvency, Restructuring and Dissolution Act 2018 (2020 Rev Ed) by an order dated 19 April 2023, restraining legal proceedings against it for six months until 20 September 2023.

By July 2023, the Church considered the delays and outstanding works unacceptable and made a call on the bond on 20 July 2023. According to the Parish Priest, Father Fenelon, the Church’s claim comprised: (a) liquidated damages estimated at S$345,000 for alleged delay; (b) outstanding warranties estimated at S$87,000; (c) outstanding rectification works estimated at S$393,660; and (d) further anticipated costs for continued delay. The total claimed was S$825,660 (excluding further anticipated costs). On 29 August 2023, Shanghai Chong Kee commenced HC/OA 876/2023 seeking a declaration that the bond call was unconscionable in whole or in part and an injunction restraining payment from Lonpac. In the alternative, it sought an assessment and reduction of the amount the Church could receive under the bond, to account for retention sums already held by the Church of S$233,116.67. An interim injunction had been granted on 30 August 2023, but the High Court ultimately dismissed the application.

The central legal issue was whether the Church’s call on an unconditional performance bond could be restrained by injunction on the ground of unconscionability. The contractor relied on the doctrine associated with “Erinford injunctions” (ie, the exceptional jurisdiction to restrain a bond call where unconscionability is established to a high threshold). The court had to determine whether Shanghai Chong Kee met the required evidential standard for a strong prima facie case of unconscionability.

A second issue concerned the contractor’s substantive arguments that the Church’s underlying claims were not properly payable. This included disputes about entitlement to liquidated damages, the effect of Covid-19 relief under COTMA on delay and liquidated damages, and whether the Architect’s certifications (and the contractual mechanisms for assessing entitlement) supported the Church’s position.

Third, the court had to consider whether the bond call should be reduced to reflect retention sums already held by the employer. Shanghai Chong Kee argued that the Church should not be able to recover the full bond amount when retention was already being held, and it sought an assessment to “reasonably account” for the retention sum of S$233,116.67.

How Did the Court Analyse the Issues?

The court began from the well-established principle that unconditional performance bonds are designed to provide prompt and reliable security to employers. As a result, courts are generally reluctant to interfere with a bond call. The exceptional intervention—through an injunction—requires more than a mere dispute over the underlying contract. The contractor must show unconscionable conduct by the employer in making the call, and the court emphasised that the contractor must establish a strong prima facie case of unconscionability.

On the unconscionability threshold, the judge examined the contractor’s four pleaded grounds. The extract indicates that the court addressed, among other matters, whether the Architect’s certification of liquidated damages entitlement could support an inference of unconscionability. The court’s approach reflected the contractual allocation of roles: the Architect was contractually tasked with assessing defective work, issuing certificates of liquidated damages entitlement, and issuing interim and final certificates. The Conditions of Contract further provided that the parties would be bound by the Architect’s certificates absent fraud or improper pressure or interference.

In relation to liquidated damages, the court considered whether the contractor could show that the Church’s call on the bond was unconscionable because liquidated damages were not properly due. The contractor’s argument appears to have been that the Architect’s process and/or the underlying entitlement were flawed, and that the Church’s reliance on those amounts to call the bond was therefore unconscionable. The court, however, did not accept that the contractor had cleared the high evidential bar required for an Erinford-type injunction. The judge treated the dispute as one that, at most, raised issues for trial rather than demonstrating clear unconscionability in the bond call.

The court also addressed the Covid-19 dimension. Shanghai Chong Kee had submitted a COTMA notification seeking relief. The analysis would have required the court to consider whether Covid-19 relief affected the employer’s entitlement to liquidated damages and, consequently, whether the employer’s bond call was unconscionable. The judge’s reasoning, as reflected in the judgment headings, indicates that the court did not find that the contractor’s COTMA position undermined the Church’s bond call to the extent necessary to show unconscionability. In other words, even if Covid-19 relief might be relevant to the merits of delay and liquidated damages, that did not automatically translate into a finding that the employer acted unconscionably by calling the bond.

Beyond liquidated damages, the court considered the “dome and tarmac” issues and outstanding warranties and rectification works. The judgment headings suggest that the court examined whether the Church’s claims for outstanding rectification and warranties were supported by the contractual framework and the factual record. The court’s analysis appears to have treated these as substantive disputes about scope of works and completion/defects, rather than evidence of bad faith or improper pressure sufficient to meet the unconscionability threshold.

Finally, the court addressed the alternative relief sought by Shanghai Chong Kee: reduction of the bond call to account for retention sums already held by the Church. The judge considered whether the bond call amount should be reduced because the employer already held retention. The court’s conclusion, as indicated by the judgment headings (“Should the defendant’s call on the bond be reduced?”), was that the contractor did not establish a basis to reduce the bond call in the manner sought. This is consistent with the nature of performance bonds: retention and bond security are typically distinct mechanisms, and unless the bond instrument or contract provides a clear basis for set-off or reduction, courts will not readily rewrite the bargain at the interlocutory stage.

In addition, the judgment includes a post-judgment addendum dealing with an Erinford injunction. This suggests the court was attentive to evolving or clarified principles governing the exceptional injunction jurisdiction. The overall reasoning culminated in a finding that there was no strong prima facie case of unconscionability, and therefore no basis to restrain payment under the unconditional bond.

What Was the Outcome?

The High Court dismissed Shanghai Chong Kee’s application to restrain the Church from receiving payment under the performance bond. The interim injunction that had been granted on 30 August 2023 was therefore not maintained, and the Church was not restrained from pursuing the bond call against Lonpac.

In addition, the court did not grant the alternative relief of assessing and reducing the amount the Church was entitled to receive under the bond to account for retention sums. The practical effect is that the employer retained the ability to realise the bond security notwithstanding ongoing disputes about underlying contractual entitlements.

Why Does This Case Matter?

This case is significant for practitioners because it underscores the strict approach Singapore courts take toward injunctions restraining calls on unconditional performance bonds. The decision illustrates that even where there are serious disputes about contractual performance—such as delay, liquidated damages, rectification scope, and warranties—the court will not readily interfere with the bond mechanism. The contractor must demonstrate unconscionability in the bond call itself, and the evidential threshold is high.

For employers and contractors alike, the judgment highlights the importance of the contractual architecture surrounding certificates and entitlements. Where the contract provides for an architect’s certifications to be binding absent fraud or improper interference, a contractor seeking to resist a bond call will face an uphill task. The court’s reasoning indicates that interlocutory proceedings are not the forum for re-litigating the merits of entitlement unless the evidence clearly shows unconscionable conduct.

The decision also has practical implications for how parties handle Covid-19-related relief claims. While COTMA relief may affect substantive rights and obligations, it does not automatically provide a basis to restrain bond realisation. Contractors should therefore ensure that their COTMA notifications, supporting evidence, and the downstream consequences for liquidated damages are properly documented and pursued through the appropriate contractual and dispute resolution channels, rather than relying solely on an injunction to stop bond payment.

Legislation Referenced

Cases Cited

Source Documents

This article analyses [2024] SGHC 5 for legal research and educational purposes. It does not constitute legal advice. Readers should consult the full judgment for the Court's complete reasoning.

Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.