Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Singapore

Range Construction Pte Ltd v Goldbell Engineering Pte Ltd [2020] SGHC 191

In Range Construction Pte Ltd v Goldbell Engineering Pte Ltd, the High Court of the Republic of Singapore addressed issues of Building and Construction Law – Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed.

Case Details

  • Citation: [2020] SGHC 191
  • Title: Range Construction Pte Ltd v Goldbell Engineering Pte Ltd
  • Court: High Court of the Republic of Singapore
  • Date: 10 September 2020
  • Judge: Lee Seiu Kin J
  • Coram: Lee Seiu Kin J
  • Case Number: Originating Summons No 382 of 2020
  • Procedural History: Application to set aside part of an adjudication determination dated 10 March 2020 (“AD”)
  • Plaintiff/Applicant: Range Construction Pte Ltd (“Range”)
  • Defendant/Respondent: Goldbell Engineering Pte Ltd (“Goldbell”)
  • Legal Area: Building and Construction Law – Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed)
  • Key Statutory Focus: Setting aside adjudication determination under the SOP Act regime
  • Contractual Framework: Letter of award dated 19 April 2017; clauses on retention, handing-over, maintenance certificate, and liquidated damages
  • Adjudication Application: Adjudication Application No SOP/AA/008/2020 (“AA 008”)
  • Payment Claim: Payment Claim dated 2 December 2019 (“Payment Claim No 28”)
  • Adjudicated Amount: $205,647.43 (after set-offs and adjustments)
  • Retention and Liquidated Damages Dispute: Liquidated damages awarded by adjudicator; retention release linked to issue of HO Certificate
  • Liquidated Damages Amount Challenged: $852,000.00 (as awarded in the AD)
  • Variation Claim Valuation Challenged: Nett variation claim valued at $38,455.54
  • Retention Sum Reference: First half due upon issue of HO Certificate; second half due upon issue of Maintenance Certificate; Maintenance Certificate timing depends on HO Certificate
  • Judicial Outcome: Application dismissed; part of AD not set aside
  • Counsel for Applicant: Choo Poh Hua Josephine and Chin Yan Xun (WongPartnership LLP)
  • Counsel for Respondent: Campos Conrad Melville, Chong Jia Hao and Michelle Lim Ann Nee (RHTLaw Asia LLP)

Summary

Range Construction Pte Ltd v Goldbell Engineering Pte Ltd [2020] SGHC 191 concerned an application under Singapore’s Building and Construction Industry Security of Payment Act (the “SOP Act”) to set aside part of an adjudication determination. The dispute arose from a construction contract under which Range, as contractor, had submitted a payment claim and was ultimately awarded an adjudicated amount of $205,647.43. Range sought to challenge two principal components of the adjudication determination: (i) the adjudicator’s award of $852,000 in liquidated damages to Goldbell, and (ii) the adjudicator’s valuation of Range’s nett variation claim at $38,455.54.

The High Court (Lee Seiu Kin J) dismissed Range’s application. The court held that the adjudicator acted within jurisdiction in taking liquidated damages into account, because liquidated damages were expressly dealt with in the employer’s payment response and were contemplated by the contract. The court also rejected Range’s broader complaints, including allegations that the adjudicator breached the fair hearing rule or failed to consider relevant matters, finding that the adjudication determination fell within the permissible scope of the SOP Act adjudication framework.

What Were the Facts of This Case?

Range and Goldbell were parties to a construction project governed by a contract formed by a letter of award dated 19 April 2017. Range acted as Goldbell’s contractor. The contract contained provisions linking (a) the release of retention sums to the issuance of a Handing-Over Certificate (“HO Certificate”), and (b) the contractor’s liability for liquidated damages to the time between the contractual completion date and the date the HO Certificate was issued. In other words, the HO Certificate was central to both the retention mechanism and the liquidated damages calculation.

After performance under the contract, a payment dispute arose. Goldbell issued a payment response to Range’s payment claim dated 2 December 2019 (Payment Claim No 28). Range then commenced adjudication under the SOP Act by filing Adjudication Application No SOP/AA/008/2020 (“AA 008”). In the adjudication, Range advanced claims totalling $2,445,225.58. The adjudicator ultimately awarded an adjudicated amount of $205,647.43 to Range, which reflected adjustments including retention-related issues, liquidated damages, and set-offs relating to variation works.

The adjudication determination focused heavily on Goldbell’s position that Range had not caused the HO Certificate to be issued. The HO Certificate mattered because it determined whether and how much of the retention sum would be released back to Range. Under the contract, the first half of the retention sum was due upon issue of the HO Certificate, while the second half was due upon issue of the Maintenance Certificate. The Maintenance Certificate timing depended on when the HO Certificate was issued, meaning that the HO Certificate’s issuance (or non-issuance) had knock-on effects for retention release.

In addition, the HO Certificate affected liquidated damages. The contract provided that liquidated damages were payable for each day between the contractual completion date (7 September 2018) and the date the HO Certificate was issued. In the present case, no HO Certificate was issued. The adjudicator therefore faced a practical difficulty: without an HO Certificate date, the adjudicator had to determine whether liquidated damages could still be awarded and, if so, what end date should be used for calculating the period of delay.

The adjudicator invited further submissions on the applicability of the contract’s liquidated damages clauses in light of the absence of an HO Certificate. After receiving further submissions, the adjudicator concluded that an HO Certificate was not a pre-condition for awarding liquidated damages. For quantum, the adjudicator selected 17 November 2018 as a reasonable date indicating that delays were still ongoing. This was based on an email dated 17 November 2018 from Range’s managing director, which admitted that certain components (including “the 3rd, 5th and roof level”) would only be completed about a week later. The adjudicator then calculated liquidated damages by taking the difference between 7 September 2018 and 17 November 2018.

Separately, the adjudication addressed Range’s claims for variation works. Goldbell contended that it had already paid $156,387.34 earlier and that any further variation claims should be set off against that earlier payment. Range did not substantially dispute that Goldbell had paid the earlier sum, but argued that Goldbell should have raised the set-off earlier in its payment response. The adjudicator accepted Goldbell’s position and found that $156,387.34 had been paid earlier, so sums due for variation works were set off against that amount.

The High Court identified the principal legal issues as falling into three broad categories: (a) whether the adjudicator acted in excess of jurisdiction, (b) whether the adjudicator breached the fair hearing rule, and (c) whether the adjudicator failed to consider assorted matters raised by Range. Although Range’s challenge covered multiple points, the court’s analysis turned on the jurisdictional question first, because jurisdictional error is a threshold ground for setting aside an adjudication determination.

On jurisdiction, Range’s “boldest” argument was that an adjudicator under the SOP Act regime had no jurisdiction to award or even take into account liquidated damages. Range argued that the SOP Act only permits claims for “loss and expense” that relate to the value of construction works done, and that liquidated damages are compensatory damages for breach of contract rather than payment for construction work. On this view, liquidated damages were not properly claimable under the SOP Act and should not have been considered in the adjudication.

Range also argued that the adjudicator identified a completion date in a manner that exceeded jurisdiction. In addition, Range alleged procedural unfairness and substantive failure to consider certain matters. While the judgment excerpt provided focuses most clearly on the liquidated damages jurisdictional argument, the court’s structure indicates that it addressed the fair hearing and failure-to-consider complaints as separate grounds, ultimately rejecting them.

How Did the Court Analyse the Issues?

Lee Seiu Kin J approached the jurisdictional challenge by examining the SOP Act’s statutory scheme and the nature of the adjudication. The court emphasised that liquidated damages were not being introduced as an independent damages claim outside the SOP Act framework; rather, they were part of what the employer had articulated in its payment response. The court relied on the SOP Act’s provision that the adjudicator’s jurisdiction encompasses matters listed in the payment response, including liquidated damages. In particular, the court referred to s 17(3)(d) of the SOP Act, which supports the adjudicator’s consideration of the employer’s stated entitlements.

On the facts, Goldbell’s payment response clearly described the liquidated damages entitlement. The court therefore held that the adjudicator was within jurisdiction to take liquidated damages into account when determining the adjudicated sum. The court rejected Range’s attempt to characterise liquidated damages as outside the SOP Act because they are “damages for breach”. The court’s reasoning was that liquidated damages are not “meant to be part of any contractor’s payment claim”; instead, they are typically asserted by employers in the payment response, and the SOP Act adjudication mechanism is designed to resolve the payment dispute by reference to what each party has stated in that process.

Range sought support from an Australian decision, Coordinated Construction Co Pty Ltd v J M Hargreaves (NSW) Pty Ltd [2005] NSWCA 228 (“Coordinated Construction”), which was said to stand for the proposition that a payment claim must relate to the carrying out of construction work and cannot include sums that are “of their nature damages for breach”. The High Court found this argument misconceived in the Singapore context. The court reasoned that the Coordinated Construction rule was directed at what may be validly claimed in a payment claim; however, liquidated damages in this case were not being advanced as part of Range’s payment claim. They were raised by Goldbell in its payment response, and thus the rule about the nature of payment claims did not directly apply.

Even if the Coordinated Construction principle were treated as applicable, the court found Range’s reliance unpersuasive. The High Court noted that in Coordinated Construction, the court accepted a distinction between (i) payments claims for construction work (which fall within adjudication jurisdiction) and (ii) claims for damages for breach (which may not). However, the Australian court in Coordinated Construction treated delay damages as not being “of their nature damages for breach” but rather as additional amounts that may become due and payable under the contract. The High Court considered that this reasoning aligned with the Singapore statutory approach because the Singapore SOP Act similarly requires progress payments to be calculated in accordance with the contract terms (s 6(a) of the SOP Act). Since the contract expressly provided for liquidated damages under clauses 19.1 and 19.2, Goldbell was entitled to set off the payment claim against its liquidated damages entitlement.

Having established jurisdiction, the court then addressed Range’s complaint about the adjudicator’s method for calculating liquidated damages in the absence of an HO Certificate. The adjudicator had not made a finding on the exact date when the HO Certificate should have been issued, because it was common ground that the adjudicator was not required to find the exact date of completion or the exact handing-over date. The court accepted that this created uncertainty about the liquidated damages period. The adjudicator resolved this by inviting further submissions and then selecting 17 November 2018 as a reasonable date indicating ongoing delay, supported by Range’s own email admitting that certain works would only be completed about a week later.

In this context, the court’s analysis reflects a key SOP Act principle: adjudication determinations are intended to be made expeditiously on the basis of the material before the adjudicator, and the court will not lightly interfere with the adjudicator’s evaluative judgments unless there is a clear jurisdictional or procedural error. The court’s rejection of Range’s jurisdictional argument meant that the adjudicator’s selection of an end date for liquidated damages calculation was treated as part of the adjudicator’s permissible assessment of quantum within the contract framework and the SOP Act’s payment dispute resolution function.

Although the excerpt provided truncates the remainder of the judgment, the court’s stated categorisation of Range’s complaints indicates that it also considered whether there was any fair hearing breach and whether the adjudicator failed to consider relevant matters. The court’s ultimate dismissal of the application suggests that it found either that the alleged procedural unfairness did not meet the threshold for setting aside, or that Range’s complaints amounted to disagreement with the adjudicator’s assessment rather than a legally cognisable error.

What Was the Outcome?

The High Court dismissed Range’s application to set aside part of the adjudication determination. As a result, the adjudicated amount of $205,647.43 stood, including the adjudicator’s allowance of liquidated damages of $852,000 and the set-off approach adopted for variation works.

Practically, the decision confirms that, in SOP Act adjudications, liquidated damages can be taken into account where they are expressly raised in the employer’s payment response and are contemplated by the contract. It also signals that challenges framed as “jurisdiction” disputes will fail where the adjudicator’s consideration falls within the statutory scope and the contract’s payment mechanics.

Why Does This Case Matter?

Range Construction v Goldbell Engineering is significant for practitioners because it clarifies the jurisdictional boundary between (i) what an adjudicator may consider in determining the adjudicated sum and (ii) what is excluded from the SOP Act process. The court’s reasoning underscores that liquidated damages are not automatically outside the SOP Act simply because they are characterised as “damages for breach” in ordinary contract law terms. Instead, the operative question is whether the liquidated damages entitlement is properly raised in the employer’s payment response and whether it is part of the contractual calculation of progress payments and set-offs.

For contractors, the case is a reminder that SOP Act adjudications are not limited to straightforward claims for work done. Where the contract provides for liquidated damages and the employer asserts them in the payment response, contractors should expect adjudicators to consider them. For employers, the decision supports the strategic and legal viability of including liquidated damages in payment responses, thereby bringing them within the adjudication’s scope.

From a litigation strategy perspective, the case also illustrates the high threshold for setting aside adjudication determinations. Even where the adjudicator faces practical difficulties (such as the absence of an HO Certificate), the court will generally treat the adjudicator’s resolution of quantum as an evaluative exercise within jurisdiction, unless a clear jurisdictional or procedural defect is demonstrated. This makes it important for parties to focus their challenges on genuine legal errors rather than substantive disagreement with the adjudicator’s assessment.

Legislation Referenced

  • Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) (“SOP Act”)
  • Section 6(a) (progress payments calculated in accordance with the terms of the contract)
  • Section 17(3)(d) (matters the adjudicator may consider, including those stated in the payment response)

Cases Cited

  • Coordinated Construction Co Pty Ltd v J M Hargreaves (NSW) Pty Ltd [2005] NSWCA 228
  • [2020] SGHC 191 (the present case)

Source Documents

This article analyses [2020] SGHC 191 for legal research and educational purposes. It does not constitute legal advice. Readers should consult the full judgment for the Court's complete reasoning.

Written by Sushant Shukla

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.