Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Singapore

Huber’s Pte Ltd v Hu Lee Impex Pte Ltd [2024] SGHC 230

In Huber’s Pte Ltd v Hu Lee Impex Pte Ltd, the High Court of the Republic of Singapore addressed issues of Land — Easements.

Case Details

  • Citation: [2024] SGHC 230
  • Title: Huber’s Pte Ltd v Hu Lee Impex Pte Ltd
  • Court: High Court of the Republic of Singapore (General Division)
  • Date of Decision: 6 September 2024
  • Originating Application No: Originating Application No 1130 of 2023
  • Judge(s): Wong Li Kok, Alex JC
  • Plaintiff/Applicant: Huber’s Pte Ltd
  • Defendant/Respondent: Hu Lee Impex Pte Ltd
  • Legal Area(s): Land — Easements
  • Statutes Referenced: Section 97A of the Land Titles Act 1993 (2020 Rev Ed) (“LTA”); Section A of the Land Titles Act 1993; Section K of the New South Wales Conveyancing Act 1919; Land Titles Act; New South Wales Conveyancing Act; Workplace Safety and Health Act; Workplace Safety and Health Act 2006
  • Cases Cited: [2024] SGHC 230 (as provided in metadata)
  • Judgment Length: 44 pages, 12,806 words

Summary

In Huber’s Pte Ltd v Hu Lee Impex Pte Ltd [2024] SGHC 230, the High Court considered an application under s 97A of the Land Titles Act 1993 (LTA) for court-ordered easements over neighbouring registered land. The applicant, Huber’s Pte Ltd, sought two temporary easements over the respondent’s industrial premises to facilitate redevelopment works on the applicant’s own adjacent property. The easements were intended to enable the installation of external construction works—such as scaffolding, hoardings, and dust-and-noise barriers—before demolition of a boundary wall and related structures.

The court granted the application, holding that the easements were reasonably necessary for the effective use or development of the applicant’s land. The judge also found that the proposed use was not inconsistent with the public interest, that the respondent could be adequately compensated, and that the applicant had made all reasonable attempts to obtain agreement before resorting to court. Importantly, the court’s reasoning emphasised the practical realities of Singapore’s tightly constrained industrial sites and the need to balance redevelopment efficiency with neighbourly protection.

What Were the Facts of This Case?

Huber’s Pte Ltd (“Huber’s”) is a family-owned Singapore company involved in the butchery business. It is the registered tenant of the dominant tenement at 16 Chin Bee Avenue, Singapore 619939 (Lot No. MK6-1341W). The respondent, Hu Lee Impex Pte Ltd (“Hu Lee”), is a Singapore company importing and distributing fresh produce. Hu Lee is the registered tenant of the servient tenement at 16A Chin Bee Avenue, Singapore 619945 (Lot No. MK6-3877L). Both properties are industrial properties owned by Jurong Town Corporation (JTC). The dispute arose because Huber’s redevelopment plans required temporary access and construction encroachment over the boundary area adjacent to Hu Lee’s ongoing business operations.

Huber’s sought two temporary court-ordered easements over Hu Lee’s premises. First, it requested a 4m-wide, 60-day easement running along the entirety of the boundary line between the dominant and servient tenements. Second, it requested a 60-day easement adjacent to Hu Lee’s main entrance along Chin Bee Avenue, to allow Huber’s agents and/or employees to access the boundary-line easement. The practical purpose of these easements was to allow Huber’s to install external construction measures necessary for demolition and redevelopment works, while managing safety and environmental impacts such as dust and noise.

Huber’s intended redevelopment was driven by underutilisation of its existing factory. The existing structure was a two-storey, single-user factory with a gross plot ratio (GPR) of 1.04, despite the maximum GPR permitted for the site being 1.40. Huber’s planned to demolish part of the existing structure and construct a new three-storey ancillary office, alongside an automated storage retrieval system to facilitate its food storage operations. A key feature of the plan involved demolishing the boundary wall (“Boundary Wall”) that faced Hu Lee’s premises. The Boundary Wall was approximately 15m to 20m tall and located close to Hu Lee’s property.

Because of the Boundary Wall’s proximity, Huber’s needed to install external buildup works (“External Buildup”) such as scaffolding, hoardings, and a dust-and-noise barrier before commencing demolition. This included the demolition of the Boundary Wall itself. Huber’s obtained approvals from JTC and relevant authorities: JTC approved the redevelopment by letter dated 14 April 2023, and the Building and Construction Authority (BCA) approved demolition using ground-to-roof scaffolding (including a demolition permit dated 9 May 2023). Despite these approvals, Hu Lee resisted granting access or allowing the proposed construction measures over its premises, citing adverse effects on its business operations.

The central legal issue was whether the court should create easements under s 97A of the LTA. Specifically, the court had to determine whether the easements were “reasonably necessary” for the effective use or development of Huber’s land. This required the court to assess not only the applicant’s development needs but also the extent to which the proposed easements were necessary in the circumstances, including whether alternative arrangements could have been adopted.

A second key issue concerned the statutory limitation that the use of the dominant land (benefiting from the easement) must not be inconsistent with the public interest. While redevelopment is generally consistent with land-use efficiency, the court had to consider whether the proposed works—particularly those involving demolition and external construction measures adjacent to a neighbour’s operating business—raised any public interest concerns.

Third, the court had to address whether Hu Lee could be adequately compensated for the burden imposed by the easements. Although s 97A empowers the court to create easements, it is not intended to impose disproportionate harm on the servient owner without appropriate safeguards, including compensation and practical arrangements to manage operational disruption during the temporary period.

How Did the Court Analyse the Issues?

The judge began by setting out the statutory framework of s 97A. Under s 97A(1), the court may create an easement over registered land if it is reasonably necessary for the effective use or development of other land that will benefit from the easement. Under s 97A(2), the court may only make the order if it is satisfied, among other things, that the use of the dominant land is not inconsistent with the public interest. The court also considered the broader context and purpose of s 97A: the provision was enacted to address increased redevelopment activity and to ensure efficient land use, while still protecting neighbours through judicial oversight.

A significant part of the analysis involved interpreting “reasonably necessary”. The parties agreed that s 97A of the LTA is in pari materia with s 88K of the New South Wales Conveyancing Act 1919 (NSW Act). The judge therefore drew on New South Wales jurisprudence, but adapted it to Singapore’s context. The judgment expressly recognised that Singapore’s built environment—particularly in industrial estates with tight boundaries and limited manoeuvring space—creates different practical challenges for neighbourliness and redevelopment planning. This contextual approach mattered because it influenced how the court evaluated necessity and the feasibility of alternatives.

In applying the “reasonable necessity” test, the court analysed two related questions: (i) the “reasonable use” question and (ii) the “substantially preferable” question. The reasonable use question focused on whether the proposed development and the use of the dominant land would be a reasonable and legitimate use that the easement would facilitate. The substantially preferable question addressed whether the easement-based solution was substantially preferable to other practical options, such as redesigning the redevelopment to avoid encroachment, using different construction methods, or obtaining access through other arrangements. The court’s approach indicates that necessity under s 97A is not satisfied by mere convenience; it requires a demonstrable need tied to effective development and a comparative assessment of alternatives.

On the facts, the court accepted that the redevelopment was not speculative or opportunistic. Huber’s had a concrete redevelopment plan to maximise permitted GPR and to install an automated storage retrieval system for its food storage operations. The Boundary Wall demolition was a necessary step in the redevelopment design. The External Buildup was also functionally linked to safety and compliance for demolition works adjacent to a neighbour’s premises. The judge considered that the easements were tailored to the redevelopment’s requirements: they were temporary (60 days), limited in width and location, and designed to enable specific construction tasks rather than a broad, indefinite occupation of the servient land.

The court also considered the burden imposed on the servient tenement. While the easements would allow access and installation of construction measures, the burden was mitigated by the temporary nature of the easements and by the fact that the works were aimed at enabling demolition and redevelopment in a controlled manner. The judge’s reasoning reflects a balancing exercise: the court must ensure that the servient owner is not subjected to an excessive or unnecessary interference, and that the easement is proportionate to the development need.

Beyond necessity, the court addressed whether the intended redevelopment was inconsistent with the public interest. The judge found that it was not. The redevelopment was approved by JTC and BCA, which supported the conclusion that the project aligned with regulatory land-use and safety frameworks. The court also considered the nature of the works and the safeguards that would be implemented, including the use of dust-and-noise barriers and scaffolding/hoardings to manage environmental and safety impacts. In this way, the public interest inquiry was not treated as a general policy question divorced from evidence; it was grounded in the regulatory approvals and the practical safety measures proposed.

The court further considered compensation. Although the judgment extract provided does not reproduce the full details of the compensation analysis, it indicates that the respondent could be adequately compensated. This was reflected in the additional order granted by the court: Hu Lee was given broad liberty to apply for compensation and to resolve operational issues during the construction period that could not be resolved between the parties. This structure is consistent with the statutory purpose of s 97A: enabling redevelopment while ensuring that the servient owner has recourse for losses and disruption.

Finally, the judge addressed the applicant’s pre-action conduct. The judgment emphasised that Huber’s made all reasonable attempts to obtain the easements without court intervention. The parties exchanged emails and met on multiple occasions. Hu Lee initially indicated that the easements were “clearly untenable” and objected to aspects of the proposed construction approach, including concerns that erecting scaffolding from the ground was “a no-go”. Huber’s responded by revising its redevelopment plans, including elevating the External Buildup for most of the demolition period and seeking regulatory approvals. Huber’s also offered indemnity and insurance arrangements and proposed monetary compensation for “loss of use” of the access area. While Hu Lee remained concerned and requested a comprehensive demolition strategy and additional assurances, the court found that Huber’s had nonetheless pursued reasonable alternatives and engagement before commencing the application.

What Was the Outcome?

The High Court allowed Huber’s application and granted the two temporary court-ordered easements over Hu Lee’s premises for the specified period and locations. The order enabled Huber’s to carry out the redevelopment works, including the installation of External Buildup and the demolition of the Boundary Wall, subject to the terms of the easements.

Crucially, the court also granted Hu Lee broad liberty to apply for compensation and to resolve operational issues during the construction period that could not be resolved between the parties. This ensured that, while the easements were created to facilitate redevelopment, the servient owner retained procedural and substantive protections against uncompensated disruption.

Why Does This Case Matter?

Huber’s Pte Ltd v Hu Lee Impex Pte Ltd is significant because it appears to be among the first reported Singapore decisions providing detailed guidance on s 97A of the LTA. The judgment is expressly framed as useful because there were “no previous reported cases on s 97A” at the time. For practitioners, this makes the decision a primary reference point for how Singapore courts will interpret and apply the “reasonably necessary” requirement and the related “reasonable use” and “substantially preferable” inquiries.

The case also illustrates how Singapore courts will engage with foreign jurisprudence where statutory provisions are in pari materia. By relying on New South Wales authorities under the NSW Act, while adapting the analysis to Singapore’s physical and commercial realities, the court demonstrated a method that future litigants can expect: comparative reasoning will be used, but not mechanically. This is particularly relevant in land disputes where the built environment and neighbourly constraints differ across jurisdictions.

From a practical standpoint, the judgment underscores the importance of evidence and negotiation. The court’s willingness to grant easements was linked to the applicant’s concrete redevelopment plan, regulatory approvals, and efforts to mitigate impact through revised designs, safety measures, and offers of indemnity/insurance and compensation. For developers and landowners, the decision signals that a successful s 97A application will likely require a demonstrated necessity supported by alternatives considered, a proportionate scope of easement, and a clear record of reasonable attempts to reach agreement.

Legislation Referenced

  • Land Titles Act 1993 (2020 Rev Ed), s 97A
  • Land Titles Act 1993, Section A (as referenced in metadata)
  • New South Wales Conveyancing Act 1919, s 88K (as referenced in pari materia analysis)
  • New South Wales Conveyancing Act 1919, Section K (as referenced in metadata)
  • Workplace Safety and Health Act
  • Workplace Safety and Health Act 2006

Cases Cited

  • [2024] SGHC 230 (as provided in metadata)

Source Documents

This article analyses [2024] SGHC 230 for legal research and educational purposes. It does not constitute legal advice. Readers should consult the full judgment for the Court's complete reasoning.

Written by Sushant Shukla

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.