Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Search articles, case studies, legal topics...
Singapore

Huber’s Pte Ltd v Hu Lee Impex Pte Ltd [2024] SGHC 230

In Huber’s Pte Ltd v Hu Lee Impex Pte Ltd, the High Court of the Republic of Singapore addressed issues of Land — Easements.

300 wpm
0%
Chunk
Theme
Font

Case Details

  • Citation: [2024] SGHC 230
  • Title: HUBER'S PTE. LTD. v HU LEE IMPEX PTE LTD
  • Court: High Court (General Division)
  • Originating Application No: Originating Application No 1130 of 2023
  • Date of Decision: 6 September 2024
  • Judges: Wong Li Kok, Alex JC
  • Hearing Dates: 1, 11, 18 July 2024
  • Applicant/Claimant: Huber’s Pte Ltd
  • Respondent/Defendant: Hu Lee Impex Pte Ltd
  • Legal Area(s): Land law; easements; statutory creation of easements over registered land
  • Statutes Referenced: Land Titles Act 1993 (2020 Rev Ed) (“LTA”); New South Wales Conveyancing Act 1919 (for comparative jurisprudence)
  • Key Statutory Provision: Section 97A of the Land Titles Act 1993
  • Judgment Length: 44 pages; 12,806 words
  • Cases Cited: None provided in the extract (the judgment notes reliance on New South Wales jurisprudence given the in pari materia relationship)

Summary

In Huber’s Pte Ltd v Hu Lee Impex Pte Ltd [2024] SGHC 230, the High Court considered an application under s 97A of the Land Titles Act 1993 (“LTA”) for the creation of temporary, court-ordered easements over a neighbour’s registered land. The applicant, Huber’s Pte Ltd (“Huber’s”), sought two easements over the respondent’s industrial premises to facilitate redevelopment works on Huber’s own land. The easements were intended to provide access and space for the installation of scaffolding, hoardings, and dust-and-noise barriers required for demolition and construction adjacent to a tall boundary wall.

The court allowed the application, finding that the easements were reasonably necessary for the effective development of Huber’s dominant tenement and that the proposed use would not be inconsistent with the public interest. The court also accepted that the respondent could be adequately compensated for the burden imposed during the limited construction period. In addition to granting the easements, the court provided the respondent with broad liberty to apply for compensation and to resolve operational issues that could not be agreed between the parties.

Notably, the judgment is significant because it appears to be among the first reported Singapore decisions addressing s 97A of the LTA. The court therefore took care to articulate the legal framework for “reasonable necessity” and the related balancing considerations, drawing on comparative jurisprudence from New South Wales due to the statutory provision being in pari materia with s 88K of the New South Wales Conveyancing Act 1919.

What Were the Facts of This Case?

Huber’s is a family-owned company in Singapore engaged in the butchery business. It was the registered tenant of an industrial property at 16 Chin Bee Avenue, Singapore 619939 (Lot No MK6-1341W), which the court referred to as the “Dominant Tenement”. The respondent, Hu Lee Impex Pte Ltd (“Hu Lee”), is a company importing and distributing fresh produce, and it was the registered tenant of an adjacent industrial property at 16A Chin Bee Avenue, Singapore 619945 (Lot No MK6-3877L), the “Servient Tenement”. Both properties were owned by JTC, and the dispute concerned the practical realities of redevelopment in a tight industrial setting.

Huber’s planned an “Intended Redevelopment” of the Dominant Tenement. The existing structure was a two-storey singular user factory that met only the minimum gross plot ratio (“GPR”) of 1.04, even though the maximum permitted GPR for the site was 1.40. To maximise the GPR and install an automated storage retrieval system for its food storage operations, Huber’s decided to demolish part of the existing structure and construct a new three-storey ancillary office (“New Structure”).

A key feature of the redevelopment was that Huber’s wished to demolish the boundary-facing wall (“Boundary Wall”) on the Dominant Tenement side. The Boundary Wall was described as approximately 15m to 20m tall and located close to the respondent’s premises. Because of the proximity and height, Huber’s asserted that it could not safely and effectively carry out demolition and subsequent works without installing temporary external works on the Servient Tenement—specifically scaffolding, hoardings, and dust-and-noise barriers (collectively, the “External Buildup”).

To implement the External Buildup, Huber’s sought two temporary easements over the Servient Tenement, both limited to a 60-day duration. First, it sought a 4m-wide, 60-day easement running along the entirety of the boundary line between the Dominant and Servient Tenements (“Boundary Line”). Second, it sought a 60-day easement adjacent to the Servient Tenement’s main entrance along Chin Bee Avenue to allow Huber’s agents and/or employees access to the Boundary Line easement. The easements were thus designed to address both the physical installation of temporary works and the operational access needed to carry out demolition and construction safely.

The central legal issue was whether the court could create easements under s 97A of the LTA. Section 97A(1) empowers the court, on application by an interested person, to create an easement over registered land if the easement is “reasonably necessary” for the effective use or development of other land that will benefit from the easement. The court must also be satisfied of additional statutory requirements under s 97A(2), including that the proposed use of the dominant land will not be inconsistent with the public interest.

Accordingly, the court had to determine (i) whether the easements were reasonably necessary for Huber’s redevelopment; (ii) whether the intended use of the dominant land would be inconsistent with the public interest; and (iii) whether the burden on the servient tenement could be justified, including whether the respondent could be adequately compensated for the interference during the limited period. These issues required the court to engage in a structured balancing exercise between the redevelopment needs of the applicant and the proprietary and commercial interests of the neighbouring landowner.

Because there were no previous reported Singapore cases on s 97A, the court treated the statutory text as the starting point and then relied on New South Wales jurisprudence interpreting the in pari materia provision (s 88K of the New South Wales Conveyancing Act 1919). The court had to adapt that comparative approach to Singapore’s context, particularly the “tight spaces” and the practical neighbourliness challenges inherent in Singapore’s industrial land use.

How Did the Court Analyse the Issues?

The court began by setting out the statutory framework of s 97A of the LTA. It emphasised that the power to create easements is exceptional: the court does not simply impose a neighbour’s burden to facilitate convenience. Instead, the applicant must show that the easement is reasonably necessary for the effective use or development of the dominant tenement. The court also noted that the statutory requirement is not merely about whether the easement is helpful, but whether it is necessary in the relevant legal sense.

In analysing “reasonable necessity”, the court adopted a structured approach informed by New South Wales authorities. While the extract does not reproduce the full doctrinal formulation, the judgment’s headings indicate that the court considered at least two sub-questions: the “Reasonable Use Question” and the “Substantially Preferable Question”. The “Reasonable Use Question” focuses on whether the use of the dominant land that the easement facilitates is a reasonable one in the circumstances. The “Substantially Preferable Question” addresses whether the proposed easement-based solution is substantially preferable to alternatives that would avoid or reduce the burden on the servient tenement.

Applying these principles, the court accepted that Huber’s redevelopment was not speculative or purely opportunistic. The existing factory was underutilised relative to the maximum permitted GPR, and the redevelopment aimed to increase capacity and install an automated storage retrieval system aligned with Huber’s food storage operations. The court also accepted that the demolition of the Boundary Wall—15m to 20m tall and located in close proximity to the respondent’s premises—created a safety and practical constraint that made the External Buildup necessary. The easements were therefore framed as temporary measures to enable safe demolition and construction rather than a permanent encroachment.

On the burden and alternatives, the court considered the respondent’s objections and the parties’ pre-action communications. Hu Lee had expressed concern that scaffolding from the ground was “a no-go” and that the demolition works would have “devastating effects” on its business. Huber’s responded by revising its plans, including elevating the External Buildup for most of the demolition period. The court treated these revisions as relevant to whether the easement solution was reasonably necessary and whether it minimised interference. The court also considered that the easements were limited to 60 days, which reduced the duration of the burden on the servient tenement.

Beyond necessity, the court addressed the public interest requirement under s 97A(2)(a). The court found that the intended redevelopment was not inconsistent with the public interest. This conclusion was consistent with the statutory purpose of s 97A: to facilitate efficient land use and redevelopment in Singapore, particularly where increased redevelopment activity makes neighbourly access arrangements more common and where the law can enable practical outcomes without undermining broader societal considerations.

The court also addressed compensation. While s 97A does not itself spell out a compensation mechanism in the extract, the judgment’s structure and the final orders indicate that the court was satisfied that the respondent could be adequately compensated for the burden imposed. The court’s additional order granting the respondent broad liberty to apply for compensation reflects a practical recognition that operational impacts during construction may vary and that a flexible process is needed to address them. This approach also aligns with the balancing logic of s 97A: the servient owner should not bear uncompensated burdens merely because redevelopment is desirable.

Finally, the court considered whether Huber’s had made all reasonable attempts to obtain the easements without court intervention. The factual narrative shows extensive pre-action communications between September 2022 and August 2023, including emails, meetings, and revised demolition plans. Huber’s sought to reassure the respondent through safety steps, offered indemnity and insurance concepts, and provided certain documents such as risk assessments and drawings. Although the respondent did not accept these proposals and requested a comprehensive demolition strategy (“CDS”) and other assurances, the court appears to have concluded that Huber’s had taken reasonable steps to negotiate and to address concerns, which supported granting the statutory relief.

What Was the Outcome?

The High Court allowed Huber’s application and granted the two temporary court-ordered easements over the Servient Tenement for the specified 60-day period, enabling Huber’s to carry out the redevelopment works and install the External Buildup and related access arrangements. The court’s decision thus operationalised s 97A as a mechanism for resolving redevelopment access disputes where statutory conditions are met.

In addition, the court granted the respondent broad liberty to apply for compensation and to resolve operational issues during the construction period that could not be resolved between the parties. This practical safeguard ensured that the respondent’s interests were not left solely to the applicant’s unilateral planning, and it provided a procedural pathway for addressing real-time impacts.

Why Does This Case Matter?

This decision is important for Singapore land practitioners because it provides the first reported, detailed judicial treatment of s 97A of the LTA. As redevelopment activity increases in dense urban settings, disputes about access for scaffolding, hoardings, and temporary works are likely to become more common. The judgment offers a structured framework for assessing “reasonable necessity” and for balancing redevelopment needs against the burdens imposed on neighbouring landowners.

For lawyers advising applicants, the case underscores the evidential and negotiation expectations that may influence the court’s discretion. The court’s attention to pre-action communications, plan revisions, safety-related assurances, and the limited duration of the easements suggests that applicants should document both (i) why the easement is necessary for effective development and (ii) why less intrusive alternatives are not substantially preferable. For respondents, the decision highlights that objections grounded in operational impact may be addressed through compensation and operational issue management, but that blanket refusal may not prevent court-ordered easements where statutory criteria are satisfied.

More broadly, the judgment illustrates how Singapore courts may use comparative jurisprudence from New South Wales where statutory provisions are in pari materia. However, the court also made clear that the comparative approach must be adapted to Singapore’s context, including the realities of “tight spaces” and the practical neighbourliness challenges in a highly developed land market.

Legislation Referenced

Cases Cited

  • (Not provided in the supplied extract. The judgment indicates reliance on New South Wales jurisprudence interpreting the in pari materia provision, but specific case names are not included in the text provided.)
  • Workplace Safety and Health Act 2006

Source Documents

This article analyses [2024] SGHC 230 for legal research and educational purposes. It does not constitute legal advice. Readers should consult the full judgment for the Court's complete reasoning.

Written by Sushant Shukla
1.5×

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.