"Based on the above, I find that the defendant was not in breach of any of his duties in respect of the Solar Project." — Per Hoo Sheau Peng J, Para 99
Case Information
- Citation: [2022] SGHC 49 (Para 0)
- Court: In the General Division of the High Court of the Republic of Singapore (Para 0)
- Date: 8 March 2022 (Para 0)
- Coram: Hoo Sheau Peng J (Para 0)
- Case Number: Suit No 844 of 2020 (Para 0)
- Area of Law: Companies — Directors — Duties (Para 0)
- Counsel for the Plaintiff: Yeo Lai Hock Nichol and Qua Bi Qi (Solitaire LLP) (Para 100)
- Counsel for the Defendant: Aqbal Singh s/o Kuldip Singh, Wong Yiping and Cheng Cui Wen (Pinnacle Law LLC) (Para 100)
- Judgment Length: Judgment reserved; extracted reasons span the issues addressed in the reported grounds (Para 0)
Summary
This case concerned a directors’ duties dispute arising from two Vietnam-related ventures undertaken by the plaintiff, Darco Water Technologies Limited: the Water Project and the Solar Project. The plaintiff alleged that the defendant, a former director and chief executive officer, caused the company to enter into transactions and make payments without proper board approval, without adequate due diligence, and without a proper contractual basis, and then failed to recover the money when the projects did not proceed. The court rejected those allegations and dismissed the claim in full. (Para 2) (Para 3)
The court’s analysis turned on the contractual and governance architecture surrounding each project. For the Water Project, the court held that the relevant Framework Agreement did not amount to an acquisition or disposal within the meaning of the Group Charter, so board approval was not required for its entry or for the Deposit. The court also found that the defendant was not responsible for the due diligence exercise and was not obliged to seek a refund of the Deposit on the basis of the draft report. For the Solar Project, the court held that board approval was not required for the Advancement Letter or the staged Payments, and that the defendant had reasonably relied on Mr Zach Thye, who was the key person in charge of the project. (Para 26) (Para 44) (Para 54) (Para 58) (Para 65) (Para 90)
More broadly, the judgment reiterates orthodox Singapore principles on directors’ duties: the subjective-objective test for acting bona fide in the interests of the company, the minimum objective standard of care, skill and diligence, and the court’s reluctance to second-guess honest commercial decisions. The court also emphasised that the plaintiff had not proved causation for the alleged losses in the Solar Project, even assuming breach. The result was a complete dismissal of the claim, with costs to be addressed by submissions. (Para 29) (Para 30) (Para 93) (Para 100)
What Were the Two Vietnam Projects and Why Did They Give Rise to the Dispute?
The dispute arose from two separate Vietnam projects that the plaintiff pursued through the defendant’s stewardship: the Water Project and the Solar Project. The court described the case as one in which the plaintiff alleged that, in managing these projects, the defendant breached duties owed to the company and caused losses, while the defendant denied any breach. The judgment makes clear that the projects were commercially unsuccessful, but the legal question was whether the defendant’s conduct crossed the line into breach of duty. (Para 2) (Para 3)
"At the heart of this dispute are two projects in Vietnam. I shall refer to them as the “Water Project” and the “Solar Project”. In managing these projects, the plaintiff claims that the defendant breached duties owed to it, and seeks damages arising from the defendant’s breaches. In response, the defendant denies that he was in breach of his duties." — Per Hoo Sheau Peng J, Para 2
The Water Project involved a Framework Agreement signed on 14 December 2017 and a US$1 million Deposit paid that same day. The Solar Project involved three documents prepared in late 2018 and three payments totalling US$600,000 made between 30 November 2018 and 15 February 2019. Neither project materialised, and the plaintiff was unable to fully recover the sums paid. Those facts framed the plaintiff’s attempt to attribute the losses to alleged failures by the defendant in governance, diligence, and recovery efforts. (Para 10) (Para 14) (Para 15)
The court’s treatment of the facts was not merely chronological; it was tied to the legal character of each transaction. The Water Project turned on whether the Framework Agreement was an acquisition or disposal requiring board approval under the Group Charter, and whether the defendant had any duty to act on the draft Mazars report. The Solar Project turned on whether the Advancement Letter and the staged payments were authorised, whether contractual milestones had to be satisfied before payment, and whether the defendant should have procured recovery of the money. (Para 26) (Para 27)
How Did the Water Project Begin, and What Was the Significance of the Framework Agreement and Deposit?
The Water Project began with the Framework Agreement signed on 14 December 2017. The same day, Mr Teh remitted US$1 million to CA Trading as the Deposit pursuant to the agreement. The plaintiff later relied on a draft Mazars report sent on 6 August 2018 to argue that the defendant should have sought a refund, but the court treated the legal significance of the agreement and the report separately. (Para 10) (Para 11)
"On 14 December 2017, the agreement was signed (“Framework Agreement”). Later that day, pursuant to the terms of the Framework Agreement, Mr Teh remitted US$1m (“the Deposit”) to CA Trading." — Per Hoo Sheau Peng J, Para 10
The plaintiff’s case was that the defendant should have obtained board approval before entering the Framework Agreement and before the Deposit was paid. It also argued that the defendant should have exercised the company’s contractual right to seek a refund once the draft Mazars report revealed negative findings. The defendant’s answer was that the Group Charter did not require board approval for this transaction and that he was not the person responsible for the due diligence exercise. (Para 17) (Para 22) (Para 26)
The court accepted the defendant’s position on the first issue because the Framework Agreement was not an acquisition or disposal. That conclusion mattered because the Group Charter’s approval thresholds were tied to acquisitions and disposals, and the plaintiff’s own annual reports described the Charter as governing “material contracts and investments exceeding specified amounts.” The court therefore held that the defendant did not need board approval to enter the Framework Agreement or to cause the Deposit to be paid. (Para 36) (Para 44)
"Accordingly, I find that the Framework Agreement does not involve an acquisition or disposal. This means that the defendant was not required under the Group Charter to obtain approval from the Board to enter into the Framework Agreement." — Per Hoo Sheau Peng J, Para 44
Why Did the Court Reject the Plaintiff’s Complaint About Due Diligence and the Draft Mazars Report in the Water Project?
The plaintiff argued that the defendant was responsible for due diligence on the Water Project and should have acted on the Draft Mazars Report by seeking a refund of the Deposit. The court rejected that submission after examining the evidence on who actually conducted the due diligence exercise and what the report did and did not establish. The court found that the plaintiff had not shown that the defendant was responsible for the exercise in the first place. (Para 17) (Para 54)
"Accordingly, I find that the plaintiff has not shown that the defendant was responsible for the due diligence exercise." — Per Hoo Sheau Peng J, Para 54
The court also held that the defendant was not obliged to intervene to seek a refund merely because the draft report contained negative findings. The reasoning was that the report was a draft, and the plaintiff had not established a basis for concluding that the defendant had a duty to treat it as a trigger for immediate recovery action. The court therefore disagreed that the defendant should have taken over the process and demanded repayment of the Deposit. (Para 11) (Para 58)
"Accordingly, I disagree that the defendant should have intervened to seek a refund of the Deposit." — Per Hoo Sheau Peng J, Para 58
This part of the judgment is important because it shows the court distinguishing between commercial disappointment and legal breach. The plaintiff’s case depended on converting an adverse draft report into a duty to recover funds, but the court did not accept that the defendant had that responsibility on the evidence. The court’s approach was anchored in the actual allocation of responsibility within the company and the project structure, rather than hindsight after the project failed. (Para 54) (Para 58) (Para 100)
How Did the Solar Project Operate, and What Were the Three Payments in Issue?
The Solar Project involved three documents prepared in October and November 2018 and three payments made under the 30 November 2018 Advancement Letter. The payments were US$200,000 on 30 November 2018, US$300,000 on 10 January 2019, and US$100,000 on 15 February 2019, for a total of US$600,000. The plaintiff alleged that these payments were made without proper authority, without a contractual obligation, and without the necessary due diligence and milestone compliance. (Para 14) (Para 18)
"Three payments totalling a US$600,000 were made to Mr Dao under the 30 November 2018 Advancement Letter by the plaintiff on behalf of DWS. The first payment of US$200,000 was made on 30 November 2018 (“First Payment”); the second payment of US$300,000 was made on 10 January 2019 (“Second Payment); and the last payment of US$100.000 was made on 15 February 2019 (“Third Payment”)." — Per Hoo Sheau Peng J, Para 14
The defendant’s response was differentiated by payment. He said Mr Zach Thye authorised the first and second payments within his authority as managing director of DWS, and that the defendant himself authorised the third payment in his capacity as managing director and chief executive officer of the plaintiff. The court accepted that the evidence pointed to Mr Zach Thye as the key person in charge of the Solar Project, which was central to the court’s conclusion that the defendant’s conduct was not shown to be improper. (Para 24) (Para 62)
"This is consistent with Mr Teh and Ms Tan’s evidence, who both state that Mr Zach Thye was the key person in charge of the Solar Project." — Per Hoo Sheau Peng J, Para 62
The plaintiff’s case on the Solar Project was broader than a simple complaint about authority. It also alleged that the defendant failed to ensure that contractual milestones were met, failed to ensure that DWS obtained the necessary documents for due diligence, and failed to ensure satisfactory due diligence. The court addressed those allegations by examining the contractual documents, the role of Mr Zach Thye, and the absence of a pleaded or evidential basis for imposing the asserted duties on the defendant. (Para 18) (Para 27) (Para 47)
What Did the Court Say About the Group Charter and Board Approval Requirements?
A central issue in both projects was whether the plaintiff’s internal Group Charter required board approval. The court found that the Group Charter was operative and featured in the plaintiff’s annual reports from 2017 to 2020, where the reports stated that it set out internal guidelines for material contracts and investments exceeding specified amounts. However, the court’s key move was to identify the scope of the Charter and then determine whether the transactions in question fell within it. (Para 36)
"The Group Charter features in the plaintiff’s Annual Reports from 2017 to 2020. Across all four years, the reports highlight the role of the Group Charter, stating that the “Group Charter sets out the Group’s internal guidelines for material contracts and investments exceeding specified amounts”." — Per Hoo Sheau Peng J, Para 36
For the Water Project, the court held that the Framework Agreement did not involve an acquisition or disposal, and therefore did not trigger the board approval requirement under the Group Charter. For the Solar Project, the court similarly held that board approval was not required for entry into the 30 November 2018 Advancement Letter or for the Payments to be made. In both contexts, the court treated the contractual and governance documents as decisive, rather than the plaintiff’s ex post characterisation of the transactions. (Para 44) (Para 65)
"Accordingly, I find that Board approval was not required for entry into the 30 November 2018 Advancement Letter or for the Payments to be made." — Per Hoo Sheau Peng J, Para 65
The court’s reasoning also illustrates a broader principle of corporate governance litigation: internal approval rules must be applied according to their actual terms. The plaintiff could not simply assert that board approval should have been obtained; it had to show that the relevant transaction fell within the scope of the approval regime. Because the court found that the Framework Agreement was not an acquisition or disposal and that the Solar Project documents did not require board approval, the plaintiff’s governance-based complaints failed at the threshold. (Para 44) (Para 65)
Why Did the Court Find That the Defendant Was Not Responsible for the Due Diligence Exercises?
The plaintiff attempted to attribute responsibility for due diligence to the defendant in both projects, but the court did not accept that characterisation. In the Water Project, the court found that the plaintiff had not shown that the defendant was responsible for the due diligence exercise. In the Solar Project, the court found that the evidence pointed to Mr Zach Thye as the key person in charge, which undermined the suggestion that the defendant personally bore the operational responsibility the plaintiff alleged. (Para 54) (Para 62)
The court’s approach was evidence-driven. It considered the documentary record, including the annual reports, the internal audit materials, the Framework Agreement, the Three Letters, and the correspondence surrounding the projects. It also considered the testimony of Ms Tan and Mr Teh. On that evidence, the court concluded that the plaintiff had not established the factual foundation needed to impose the asserted due diligence duties on the defendant. (Para 36) (Para 42) (Para 62)
"The auditors noted that it was unclear whether the Framework Agreement created a binding agreement on the terms of the acquisition. In response, the plaintiff clarified that the moneys disbursed under the Framework Agreement indicated good faith and enabled them to conduct further due diligence prior to the signing of any binding agreement, that being, an agreement involving an acquisition." — Per Hoo Sheau Peng J, Para 42
That passage is significant because it shows the plaintiff’s own explanation of the Water Project payments as part of a further due diligence process rather than as a completed acquisition. The court used that context to reinforce its conclusion that the Framework Agreement did not fall within the Group Charter’s acquisition/disposal approval mechanism. The plaintiff therefore could not transform the due diligence process into a basis for alleging that the defendant had breached a duty to obtain board approval or to recover the Deposit. (Para 42) (Para 44) (Para 54)
How Did the Court Deal with the Plaintiff’s Allegation That the Defendant Should Have Procured Recovery of the Payments?
The plaintiff’s recovery argument was that, once the projects failed or once adverse information emerged, the defendant should have taken steps to recover the money paid out. The court rejected that argument in both projects. In the Water Project, the court said it disagreed that the defendant should have intervened to seek a refund of the Deposit. In the Solar Project, the court held that the plaintiff had failed to prove that the defendant did not discharge his duties in authorising the Payments, and it also found that causation was not established. (Para 58) (Para 90) (Para 93)
"In sum, I find that the plaintiff has failed to prove that the defendant did not discharge his duties in authorising the Payments." — Per Hoo Sheau Peng J, Para 90
The causation point mattered because even if the defendant had been in breach, the plaintiff still had to show that the breach caused the losses. The court expressly noted that the plaintiff would have to demonstrate an unbroken chain of causation from breach to loss. That requirement was fatal to the plaintiff’s damages case on the Solar Project, because the court was not persuaded that the alleged failures by the defendant were the legal cause of the US$600,000 loss. (Para 93)
"Even if, arguendo, the defendant was in breach of his duty to act reasonably, or with due care, skill and diligence, when he authorised the payments, the plaintiff would have to demonstrate an unbroken chain of causation leading from the defendant’s breach to the losses suffered" — Per Hoo Sheau Peng J, Para 93
The court’s treatment of recovery also reflects a practical commercial reality: not every failed project creates a duty on a director to reverse or claw back payments. The plaintiff had to show a specific duty, a breach of that duty, and causation. Because the court found those elements lacking, the recovery complaint failed as part of the broader dismissal of the claim. (Para 58) (Para 90) (Para 93)
What Legal Principles on Directors’ Duties Did the Court Apply?
The court set out the governing principles on directors’ duties in a way that is central to understanding the outcome. It stated the subjective-objective test for the duty to act bona fide in the interests of the company, and it identified the minimum objective standard for the duty of care, skill and diligence. These principles framed the court’s evaluation of the defendant’s conduct across both projects. (Para 29) (Para 30)
"The test in respect of this duty is both subjective and objective. The subjective element lies in the court’s consideration of whether the director had exercised his discretion bona fide in what he considered was in the interests of the company while the objective test requires an assessment of whether an intelligent and honest man in the position of a director of a company concerned could, in the whole of the existing circumstances, have reasonably believed that the transactions were for the benefit of the company" — Per Hoo Sheau Peng J, Para 29
The court also noted that the duty of care, skill and diligence is not a core fiduciary duty in the same way as honesty, fidelity, and loyalty. Instead, it is subject to a minimum objective standard requiring reasonable steps to place oneself in a position to guide and monitor management. Those principles were important because the plaintiff’s case repeatedly tried to recast commercial decisions and project management choices as fiduciary breaches. (Para 30)
"The standard of care, skill and diligence expected of a director is subject to a minimum objective standard which entails the obligation to take reasonable steps to place oneself in a position to guide and monitor the management of the company" — Per Hoo Sheau Peng J, Para 30
The court also referred to the statutory overlay in section 157(1) of the Companies Act 1967, noting that the statutory duties to act honestly and reasonably are largely similar in content and scope to the common law duties discussed. This statutory framework mattered because the defendant also invoked section 391 as a possible excuse if breach were established, although the court ultimately found no breach and therefore did not need to grant relief on that basis. (Para 31) (Para 25)
How Did the Court Treat the Evidence of Mr Zach Thye and the Other Witnesses?
The evidence of Ms Tan and Mr Teh was important because it helped the court identify who was actually running the Solar Project. The court expressly noted that both witnesses said Mr Zach Thye was the key person in charge of the Solar Project. That evidence supported the defendant’s position that operational responsibility lay elsewhere and that he was entitled to rely on the project’s internal management structure. (Para 62)
The court also considered the plaintiff’s own witnesses’ inability to testify with conviction that there was anything seriously wrong with the defendant’s actions at the material time. That observation was made in the context of the court’s broader assessment of the evidence and its reluctance to infer breach from hindsight. The court’s reasoning suggests that the live evidence did not establish the kind of clear wrongdoing the plaintiff needed to prove. (Para 100)
"This aptly captures the situation at hand. In this connection, I am perturbed that the plaintiff’s only two witnesses, Ms Tan and Mr Teh (who worked on the two projects), were not able to testify with any degree of conviction that there was anything seriously wrong with the defendant’s actions at the material time." — Per Hoo Sheau Peng J, Para 100
That evidential assessment was not a side note; it went to the heart of the court’s confidence in the plaintiff’s case. If the witnesses closest to the projects could not convincingly identify wrongdoing at the relevant time, the court was understandably unwilling to infer breach from the mere fact that the projects failed. The judgment therefore ties witness credibility and evidential weight directly to the ultimate dismissal. (Para 100)
Why Did the Court Say It Was Slow to Interfere in Honest Commercial Decisions?
The court concluded with a reminder that commercial decisions made honestly are not lightly disturbed merely because they later prove financially detrimental. That principle was especially apt here because the plaintiff’s case was built around failed projects and unrecovered payments, but the court found no sufficient basis to convert failure into breach. The court’s final reasoning thus linked legal doctrine to commercial realism. (Para 100)
"It is trite that the court is slow to interfere in commercial decisions which have been made honestly even if they turn out, on hindsight, to be financially detrimental" — Per Hoo Sheau Peng J, Para 100
The court applied that principle after finding that the defendant had not breached his duties in respect of the Solar Project and, more generally, that no breach had been proved in either project. The court also noted that the plaintiff’s witnesses could not say with conviction that the defendant’s actions were seriously wrong at the time. In that setting, the court was not prepared to impose liability simply because the ventures failed and money was lost. (Para 99) (Para 100)
That approach is significant for directors’ duties litigation because it distinguishes between poor outcomes and actionable misconduct. A director is not liable merely because a commercial venture fails, even if the company later regrets the decision. The plaintiff had to prove a breach of duty, and the court found that it had not done so. (Para 99) (Para 100)
Why Does This Case Matter?
This case matters because it demonstrates how Singapore courts analyse directors’ duties in the context of commercial projects that involve preliminary agreements, staged payments, and internal approval processes. The judgment shows that a plaintiff cannot succeed by pointing to losses alone; it must prove the precise duty said to have been breached, the factual basis for that duty, and the causal link to loss. The court’s careful treatment of the Group Charter, the Framework Agreement, and the Solar Project documents is a practical reminder that corporate governance disputes are often won or lost on the actual wording of the documents. (Para 36) (Para 42) (Para 44) (Para 65) (Para 93)
The case also matters because it reinforces the evidential burden on a plaintiff alleging that a director should have taken over project management or recovery efforts. The court was not persuaded that the defendant was the person responsible for due diligence, nor that he should have overridden the project structure or intervened to recover funds. The evidence instead pointed to Mr Zach Thye as the key person in charge of the Solar Project, and the plaintiff’s own witnesses did not convincingly establish wrongdoing by the defendant at the relevant time. (Para 54) (Para 58) (Para 62) (Para 100)
Finally, the judgment is a useful statement of judicial restraint in commercial matters. It confirms that courts will not lightly second-guess honest business judgments simply because they later turn out badly. For practitioners, the case underscores the importance of documenting authority, responsibility, and due diligence roles clearly at the outset of a transaction, especially where multiple entities and cross-border projects are involved. (Para 29) (Para 30) (Para 100)
Cases Referred To
| Case Name | Citation | How Used | Key Proposition |
|---|---|---|---|
| Goh Chan Peng and others v Beyonics Technology Ltd and another and another appeal | [2017] 2 SLR 592 | Used in the statement of the subjective-objective test for the duty to act bona fide in the interests of the company. | The objective inquiry asks whether an intelligent and honest director could reasonably believe the transaction benefited the company. (Para 29) |
| Then Khek Koon v Arjun Permanand Samtani | [2014] 1 SLR 245 | Used to explain that care, skill and diligence are not core fiduciary duties and again on causation. | The duty of care, skill and diligence is distinct from core fiduciary duties; a plaintiff must show an unbroken chain of causation from breach to loss. (Para 30) (Para 93) |
| Ho Yew Kong v Sakae Holdings Ltd and other appeals and other matters | [2018] 2 SLR 333 | Used for the minimum objective standard of care, skill and diligence and for conflict principles. | Directors must take reasonable steps to place themselves in a position to guide and monitor management; a director must not put himself in a conflict position. (Para 30) (Para 32) |
| Tan Kia Poh v Hong Leong Finance Ltd | [1993] 3 SLR(R) 429 | Used on pleading specificity. | A party may not pursue a line of argument if the pleadings are not sufficiently specific. (Para 47) |
| AMG Global Investments & Holdings Pte Ltd (in Liquidation) v Ong Kee Ming Richard and another | [2021] SGHC 222 | Cited by the plaintiff on the need for supporting documentation before authorising payments. | A director authorising payment must believe it is for a proper purpose and take reasonable steps to understand the transaction and review supporting documents. (Para 75) |
| Ho Kang Peng v Scintronix Corp Ltd (formerly known as TTL Holdings Ltd) | [2014] 3 SLR 329 | Used in the conclusion on judicial restraint in commercial decisions. | The court is slow to interfere in honest commercial decisions even if they later prove financially detrimental. (Para 100) |
Legislation Referenced
- Companies Act 1967, section 157(1) (Para 31)
- Companies Act 1967, section 391 (Para 25)
Source Documents
This article analyses [2022] SGHC 49 for legal research and educational purposes. It does not constitute legal advice. Readers should consult the full judgment for the Court's complete reasoning.