Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Singapore

Chuang Long Engineering Pte Ltd v Nan Huat Aluminium & Glass Pte Ltd [2019] SGHC 55

In Chuang Long Engineering Pte Ltd v Nan Huat Aluminium & Glass Pte Ltd, the High Court of the Republic of Singapore addressed issues of Building and Construction Law — Statutes and regulations.

Case Details

  • Citation: [2019] SGHC 55
  • Case Title: Chuang Long Engineering Pte Ltd v Nan Huat Aluminium & Glass Pte Ltd
  • Court: High Court of the Republic of Singapore
  • Date of Decision: 05 March 2019
  • Judge: Chan Seng Onn J
  • Coram: Chan Seng Onn J
  • Case Number: Originating Summons No 1568 of 2018
  • Procedural History: Application to set aside an Adjudication Determination dated 30 November 2018, amended and re-dated 18 December 2018
  • Plaintiff/Applicant: Chuang Long Engineering Pte Ltd
  • Defendant/Respondent: Nan Huat Aluminium & Glass Pte Ltd
  • Counsel for Applicant: Lim Ker Sheon and Zeng Hanyi (Characterist LLC)
  • Counsel for Respondent: Satinder Pal Singh (Selvam LLC)
  • Legal Area: Building and Construction Law — Statutes and regulations (Building and Construction Industry Security of Payment)
  • Statutes Referenced: Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) (“SOPA”)
  • Key Statutory Provision: s 7(2)(c) SOPA (Valuation of construction work, goods and services)
  • Additional Statutory Provision Mentioned: s 36(4) SOPA (non-limitation of other law, read with s 36(1))
  • Primary Issue: Interpretation of s 7(2)(c) SOPA—whether valuation under the second limb extends to undelivered/uninstalled materials fabricated for the project
  • Judgment Length: 7 pages, 2,790 words
  • Decision: Application dismissed; adjudicator had jurisdiction and properly interpreted s 7(2)(c) SOPA

Summary

Chuang Long Engineering Pte Ltd v Nan Huat Aluminium & Glass Pte Ltd concerned an application to set aside a construction adjudication determination under Singapore’s Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) (“SOPA”). The applicant, a main contractor, sought to overturn the adjudicator’s valuation of certain “uninstalled materials” that had been fabricated for the project but were not delivered or installed at the time of adjudication.

The High Court (Chan Seng Onn J) held that the adjudicator properly interpreted s 7(2)(c) SOPA. In particular, the Court rejected a narrow “property passing” approach that would limit valuation only to materials that had been incorporated or affixed to the building. The Court affirmed that s 7(2)(c) includes a second limb allowing valuation of materials or components that, on payment, will become the property of the party for whom the construction work is being carried out, and that this can extend to fabricated but undelivered materials where the statutory conditions are met.

What Were the Facts of This Case?

The applicant, Chuang Long Engineering Pte Ltd, was the main contractor for a project described as the “Proposed new erection of a 2-storey envelope control detached dwelling house with an attic and a basement” (the “Project”). The applicant then subcontracted part of the works to the respondent, Nan Huat Aluminium & Glass Pte Ltd, under a sub-contract agreement valued at $323,282.50 (excluding GST). The subcontract concerned aluminium and glass-related components for the building envelope works.

On 3 September 2018, the applicant terminated the subcontract. The termination was said to be due to an alleged breach of completion deadlines and the schedule of works. Following termination, the subcontractor sought payment through SOPA adjudication, which is designed to provide a rapid interim mechanism for cash flow in the construction industry.

On 24 September 2018, the respondent filed a payment claim for unpaid works, claiming $237,421.35. The applicant served a payment response on 8 October 2018. Dissatisfied with the response, the respondent initiated adjudication under SOP/AA 385/2018.

The adjudicator determined that $165,683.91 (inclusive of GST) was payable by the applicant to the respondent (the “Sum”). In arriving at the Sum, the adjudicator deducted retention and previous payments. A significant component of the dispute concerned the valuation of “uninstalled materials”: materials that had been fabricated for the Project but had not been delivered nor installed by the respondent. The adjudicator valued these uninstalled materials at $75,651.00, comprising $45,831.00 for aluminium fins and $29,820.00 for cladding.

The sole issue before the High Court was whether the adjudicator had properly interpreted s 7(2)(c) SOPA. The applicant’s position was that the adjudicator lacked jurisdiction to award the Sum insofar as it included the value of the uninstalled materials. The applicant’s argument focused on the statutory meaning of “materials or components that are to form part of any building, structure or works arising from the construction work” and, in particular, the phrase “have become or, on payment, will become the property of the party for whom the construction work is being carried out”.

More specifically, the applicant contended that s 7(2)(c) should be read through a “Property Passing Test”. On this view, valuation under s 7(2)(c) should depend on whether property in the materials had passed (or would pass) to the party for whom the construction work was being carried out. The applicant urged the Court to align the statutory interpretation with the common law rule that property in materials and fittings passes when they are incorporated or affixed to the building.

By contrast, the respondent and the adjudicator adopted a broader interpretation. They treated s 7(2)(c) as having two scenarios: (a) materials that have become the property of the paying party (Situation A), and (b) materials that have not yet become the property but will become the property on payment (Situation B). The dispute therefore turned on whether Situation B could include materials that were fabricated but not delivered or installed.

How Did the Court Analyse the Issues?

Chan Seng Onn J began by setting out the statutory framework. Section 7(1) SOPA provides that construction work carried out, or goods or services supplied, are to be valued in accordance with the contract; if the contract is silent, valuation must be made having regard to matters in s 7(2). Here, it was agreed that the contract was silent on valuation, so s 7(2) applied.

The Court then analysed the structure of s 7(2)(c). The provision allows valuation of two types of materials or components that are to form part of the building or works arising from the construction work. The first limb covers materials that “have become” the property of the party for whom the construction work is being carried out. The second limb covers materials that “on payment, will become” that property. The Court emphasised that the statutory language is not limited to materials already affixed or incorporated at the time of valuation.

On the applicant’s “Property Passing Test”, the Court considered the common law position relied upon by the applicant, including the proposition that property in materials passes once incorporated or affixed to the building. The applicant’s argument was that, absent incorporation, the materials should not be valued under s 7(2)(c) except where a retention of title clause delays property passing until payment. The applicant further argued that the second limb should only operate in that narrow retention-of-title context.

The Court rejected that constrained approach. It agreed with the respondent’s and adjudicator’s interpretation that s 7(2)(c) extends beyond the affixation/incorporation test. In the Court’s view, Situation B is not confined to cases where property passing is delayed by contract terms; rather, it reflects the statutory basis for valuation where materials are to form part of the works and will become the property of the paying party upon payment. Accordingly, the adjudicator was entitled to include the value of fabricated but undelivered materials, provided they were materials or components intended to form part of the building/works arising from the construction work.

The Court also addressed the applicant’s submission that this broader interpretation was inconsistent with Parliamentary intention, particularly in light of s 36(4) SOPA. The applicant argued that s 36(4) preserves the operation of other laws relating to rights, title, interests, and liabilities arising under contracts. It followed, according to the applicant, that Parliament intended s 7(2)(c) to incorporate the existing common law property passing rules, and not to “drastically affect” those rules.

Chan Seng Onn J did not accept this. First, the Court read s 36(4) in context with s 36(1). Section 36(1) prohibits parties from contracting out of SOPA’s terms, including the payee’s right to progress payments and adjudication. Section 36(4) then operates as a qualifier: “except as provided in subsection (1)”, SOPA does not limit or otherwise affect the operation of other law relating to contractual rights and liabilities. The Court observed that this means s 36(4) does not dictate that other SOPA provisions must be interpreted narrowly to mirror common law property rules.

More importantly, the Court found that the respondent’s interpretation better aligned with the overriding purpose of SOPA: facilitating cash flow for downstream players in the construction industry. SOPA’s scheme is to provide a fast, interim adjudication mechanism that prevents contractors and subcontractors from being deprived of payment for works done and goods supplied. A narrow interpretation that excludes fabricated but undelivered materials would undermine that cash flow objective, particularly where materials are manufactured for the project and are intended to become part of the works.

Although the truncated extract does not reproduce the later parts of the judgment, the reasoning visible in the provided text shows the Court’s core approach: statutory interpretation grounded in the text of s 7(2)(c), contextual reading of s 36(4), and purposive consideration of SOPA’s cash flow function. On that basis, the Court concluded that the adjudicator had jurisdiction and properly interpreted the provision when valuing the uninstalled materials.

What Was the Outcome?

The High Court dismissed the application to set aside the adjudication determination. The Court held that the adjudicator had properly interpreted s 7(2)(c) SOPA and therefore had jurisdiction to include the value of the uninstalled materials in the Sum payable by the applicant to the respondent.

Practically, this meant that the adjudication determination stood, and the subcontractor retained the benefit of the adjudicated amount (subject to the usual enforcement and subsequent litigation dynamics that can follow SOPA adjudications). The decision reinforces that, in SOPA adjudications, valuation disputes concerning materials intended for the works will be assessed under the statutory valuation framework rather than being limited strictly by common law property passing rules.

Why Does This Case Matter?

This case is significant for practitioners because it clarifies the interpretation of s 7(2)(c) SOPA, particularly the scope of the second limb (“on payment, will become the property”). The decision confirms that valuation under SOPA is not restricted to materials already incorporated or affixed to the building. Instead, materials or components that are to form part of the building or works and that will become the property of the paying party upon payment may be valued even if they have not been delivered or installed at the time of adjudication.

For main contractors and subcontractors, the case has direct commercial implications. Contractors cannot assume that termination of a subcontract or non-delivery of materials will automatically exclude those materials from adjudicated valuation. Where materials are fabricated for the project and are intended to form part of the works, adjudicators may include their value to preserve the SOPA objective of maintaining cash flow to downstream parties.

For lawyers advising on SOPA disputes, the decision also highlights the importance of statutory interpretation over common law analogies. While property passing concepts remain relevant in understanding contractual arrangements, the Court’s approach indicates that SOPA’s valuation provisions must be applied according to their own text and purpose. Additionally, the Court’s contextual reading of s 36(4) demonstrates that the “non-limitation” clause does not require SOPA provisions to be read as mere reflections of common law property rules.

Legislation Referenced

  • Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) (“SOPA”)
    • s 7(2)(c) — Valuation of materials or components intended to form part of the building/works; materials that “have become or, on payment, will become” the property of the party for whom the work is carried out
    • s 36(1) — Prohibition on contracting out of SOPA’s regime
    • s 36(4) — Qualifier preserving the operation of other law, except as provided in s 36(1)

Cases Cited

  • [2019] SGHC 55 (the present case)

Source Documents

This article analyses [2019] SGHC 55 for legal research and educational purposes. It does not constitute legal advice. Readers should consult the full judgment for the Court's complete reasoning.

Written by Sushant Shukla

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.