Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Singapore

Choi Peng Kum and another v Tan Poh Eng Construction Pte Ltd [2013] SGHCR 19

In Choi Peng Kum and another v Tan Poh Eng Construction Pte Ltd, the High Court of the Republic of Singapore addressed issues of Building and Construction Law — Statutes and regulations, Civil Procedure.

Case Details

  • Citation: [2013] SGHCR 19
  • Title: Choi Peng Kum and another v Tan Poh Eng Construction Pte Ltd
  • Court: High Court of the Republic of Singapore
  • Decision Date: 05 July 2013
  • Originating Process: Originating Summons No 275 of 2013
  • Coram: Eunice Chua AR
  • Judgment Reserved: 5 July 2013
  • Judicial Officer: AR Eunice Chua
  • Plaintiff/Applicant: Choi Peng Kum and another
  • Defendant/Respondent: Tan Poh Eng Construction Pte Ltd
  • Counsel for Applicants: Philip Ling and Ang Hou Fu (Wong Tan & Molly Lim LLC)
  • Counsel for Respondent: Tan Joo Seng and Wee Qian Liang (Chong Chia & Lim LLC)
  • Legal Areas: Building and Construction Law — Statutes and regulations; Civil Procedure
  • Statutes Referenced: Building and Construction Industry Security of Payments Act (Cap 30B, 2006 Rev Ed) (“SOP Act”); Singapore SOP Act; New South Wales equivalent of the SOP Act (“NSW SOP Act”)
  • Contractual Instrument Referenced: Singapore Institute of Architects, Articles and Conditions of Building Contract, Lump Sum Contract, 9th Edition (“SIA Conditions”); Addendum to the contract
  • Key Contract Clauses Referenced: cl 32(8)(a); cl 31(4)
  • Judgment Length: 7 pages, 3,709 words
  • Cases Cited: [2013] SGHC 95; [2013] SGHCR 19

Summary

In Choi Peng Kum and another v Tan Poh Eng Construction Pte Ltd [2013] SGHCR 19, the High Court (per Eunice Chua AR) considered an application to set aside an adjudication determination made under Singapore’s Building and Construction Industry Security of Payments Act (the “SOP Act”). The applicants (property owners) sought to overturn an adjudicator’s decision awarding the contractor the full amount claimed under “Progress Claim No. 9”. Their primary contention was that, because the construction contract had been terminated, the contract provisions prevented any further sums from being certified as due, and therefore the contractor had no entitlement to progress payment and no basis to trigger adjudication.

The court rejected the applicants’ attempt to treat the existence of a contractual entitlement to payment as a jurisdictional prerequisite for SOP Act adjudication. Applying the statutory scheme, the court emphasised that the SOP Act creates a separate statutory entitlement to progress payment for work done under a construction contract, and that the adjudication process is designed to be “fast and low cost” and to facilitate cash flow. The court also addressed the interaction between the SOP Act and the SIA Conditions, including the effect of termination and the contractual requirements for interim valuations.

What Were the Facts of This Case?

The applicants were property owners who engaged the respondent contractor to carry out reconstruction works on their property. The contract was entered on 25 November 2011 and incorporated the SIA Conditions (Lump Sum Contract, 9th Edition) together with an addendum that allocated responsibilities between the Architect and the Quantity Surveyor. In particular, the addendum provided that, save for the Architect’s role in providing design and necessary information, directions and obligations (including extensions of time) would be carried out by the Quantity Surveyor. The Quantity Surveyor was also responsible for certification of payment, determining variation works, omissions, and the value of works carried out by the contractor.

Disputes later arose between the parties concerning alleged defective works and works not carried out. On 7 February 2013, the applicants terminated the contractor’s employment. Despite termination, the contractor had already issued a progress claim before termination: on 31 January 2013, the respondent issued “Progress Claim No. 9” for $480,109.97. The applicants did not respond to that progress claim. Their position was that the claim was not supported by a valuation by the Quantity Surveyor and instead consisted only of a description and breakdown of items claimed without enclosing supporting documentation.

On 7 March 2013, the respondent lodged an adjudication application in respect of Progress Claim No. 9 under the SOP Act. The adjudication application was served on the applicants on 8 March 2013. The applicants lodged their adjudication response at 5.20pm on 15 March 2013. The appointed adjudicator treated the response as lodged on 16 March 2013 because it was submitted after 4.30pm on 15 March 2013. As a result, pursuant to s 16(2) of the SOP Act, the adjudicator regarded the adjudication response as out of time and did not consider it.

On 22 March 2013, the adjudicator issued an adjudication determination in favour of the respondent for the full amount of Progress Claim No. 9. Although the applicants’ adjudication response was not considered, the record noted that a “Progress Valuation No. 9”, dated 14 March 2013, certified $7,086.61 as payable on Progress Claim No. 9. The applicants then filed the present application on 28 March 2013 to set aside the adjudication determination and seek consequential orders.

The case raised two connected legal questions. First, the court had to determine whether a court may set aside an adjudication determination under the SOP Act on the basis that there was no entitlement to payment under the terms of the construction contract. This issue went to the boundary between (i) contractual merits and (ii) the statutory entitlement and adjudication jurisdiction under the SOP Act.

Second, assuming that such a basis could, in principle, found an application to set aside, the court had to consider whether the respondent could establish a contractual entitlement to the progress payment claimed in Progress Claim No. 9 consistent with the SIA Conditions. The applicants relied on two specific contractual provisions: cl 32(8)(a), which they argued prevented further certification of sums due after termination until a “Cost of Termination Certificate” was issued; and cl 31(4), which they argued required interim payments based on periodic valuation to be supported by a retrospective re-evaluation of work up to a specified date.

How Did the Court Analyse the Issues?

The court began by examining the statutory framework of the SOP Act. Section 5 provides that “any person who has carried out any construction work, or supplied any goods or services, under a contract is entitled to a progress payment.” Section 6 and s 10 then set out how the amount is calculated and how payment claims are to be made. In particular, s 10(1) allows a claimant to serve “one payment claim in respect of a progress payment” on a person who, “under the contract concerned, is or may be liable to make the payment” (or such other person as specified or identified in accordance with the contract). This statutory architecture, the court reasoned, separates the existence of a statutory entitlement to a progress payment from the contractual question of whether the employer is liable to pay the ultimate amount claimed.

Against this, the applicants argued that the right to a progress payment is created by the construction contract, not by the SOP Act. They relied on Australian authority interpreting the NSW equivalent of the SOP Act, including Roseville Bridge Marina Pty Ltd v Bellingham Marine Australia Pty Ltd [2009] NSWSC 320, where the court stated that the Act does not create a right to remuneration but creates and regulates a right to obtain a progress payment, and that the contract provides the starting point for rights under the Act. They also relied on commentary (Chow Kok Fong, Security of Payments and Construction Adjudication) suggesting that the phrase “under a contract” in the statutory provision premises the right to be paid on performance, so that if there is breach, the right does not crystallise.

The court considered these submissions to be “too extreme”. The applicants’ approach would require the court, when hearing a setting-aside application or an enforcement-related challenge, to summarily determine whether there was a contractual entitlement to payment before it could find that there was a statutory entitlement to a progress payment and a valid basis for adjudication. The court held that this would undermine the SOP Act’s scheme and purpose. The court referred to Lee Wee Lick Terence (alias Li Weili Terence) v Chua Say Eng (formerly trading as Weng Fatt Construction Engineering) and another appeal [2013] 1 SLR 401, which described the SOP Act as a “fast and low cost adjudication system” intended to facilitate cash flow. In that scheme, a contractor obtains the right to seek adjudication after serving a payment claim in the prescribed form, and the adjudicator’s decision is binding in an interim manner.

On that basis, the court concluded that the entitlement to a progress payment arises once the claimant has carried out construction work or supplied goods or services under a construction contract, and that the right to make a payment claim under the SOP Act is a separate matter from the employer’s liability to pay under the contract. The applicants’ proposed approach would effectively convert the adjudication setting-aside stage into a merits trial about contractual entitlement, which is inconsistent with the interim nature of adjudication under the SOP Act.

Although the extract provided does not include the remainder of the court’s reasoning, the court’s analysis in the visible portion indicates a clear doctrinal stance: contractual disputes about whether sums are due, or whether contractual conditions for certification have been satisfied, are generally matters for adjudication on the merits rather than matters that negate the adjudicator’s jurisdiction or the statutory entitlement to progress payment. The court’s reasoning also reflects the SOP Act’s design to prevent employers from withholding cash flow by raising complex contractual defences at the setting-aside stage.

Turning to the second issue, the applicants’ arguments on cl 32(8)(a) and cl 31(4) were premised on the idea that the contractor’s entitlement to claim and adjudication could not arise because termination and valuation requirements under the SIA Conditions allegedly prevented any further certification of sums due. The court’s earlier conclusion about the separation between statutory entitlement and contractual liability would, in practice, limit the extent to which such contractual provisions can be used to set aside an adjudication determination. In other words, even if the applicants could argue that the contractor’s claim did not comply with contractual certification or valuation requirements, that would not necessarily mean the adjudicator lacked power to determine the payable amount under the SOP Act.

What Was the Outcome?

The court dismissed the application to set aside the adjudication determination. The practical effect was that the adjudicator’s determination awarding the respondent the full amount of Progress Claim No. 9 remained enforceable, at least on an interim basis consistent with the SOP Act’s statutory design.

Accordingly, the applicants could not rely on contractual termination provisions or valuation requirements under the SIA Conditions to overturn the adjudication decision at the setting-aside stage. The decision reinforces that the SOP Act adjudication process is not intended to be derailed by merits-based arguments about contractual entitlement, particularly where the statutory scheme already confers a progress payment entitlement for work done under a construction contract.

Why Does This Case Matter?

This decision is significant for practitioners because it clarifies the relationship between the SOP Act and the underlying construction contract. The court’s reasoning supports a key principle in Singapore security of payments jurisprudence: the statutory entitlement to a progress payment is distinct from the employer’s contractual liability to pay the ultimate sum. As a result, arguments that the contractor had no contractual entitlement—whether due to termination clauses, certification mechanisms, or valuation requirements—are generally not a straightforward basis to set aside an adjudication determination.

For contractors and employers, the case underscores the importance of responding to payment claims and adjudication applications within statutory timelines. Here, the applicants’ adjudication response was treated as out of time because it was lodged after the relevant cutoff. While the court’s analysis in the extract focuses on the interaction between statutory entitlement and contractual terms, the procedural posture also highlights how quickly an adjudication can become binding in an interim manner if responses are not properly filed.

For law students and litigators, the case provides a useful framework for analysing setting-aside applications under the SOP Act. It demonstrates that courts will resist approaches that effectively require a merits determination at the setting-aside stage. Instead, courts will focus on whether the SOP Act scheme has been followed and whether the adjudicator’s decision can be challenged on legally permissible grounds, rather than re-litigating contractual entitlement.

Legislation Referenced

  • Building and Construction Industry Security of Payments Act (Cap 30B, 2006 Rev Ed) (“SOP Act”)
  • Singapore SOP Act provisions: s 5, s 6, s 10, s 16(2)
  • New South Wales equivalent of the SOP Act (“NSW SOP Act”)

Cases Cited

  • Lee Wee Lick Terence (alias Li Weili Terence) v Chua Say Eng (formerly trading as Weng Fatt Construction Engineering) and another appeal [2013] 1 SLR 401
  • Roseville Bridge Marina Pty Ltd v Bellingham Marine Australia Pty Ltd [2009] NSWSC 320
  • [2013] SGHC 95
  • [2013] SGHCR 19

Source Documents

This article analyses [2013] SGHCR 19 for legal research and educational purposes. It does not constitute legal advice. Readers should consult the full judgment for the Court's complete reasoning.

Written by Sushant Shukla

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.