"It follows that Delhi Express is not to be distinguished. CES alone was able to initiate a review by the TAC, and it cannot rely on the absence of a decision of the TAC to dispute the Tribunal’s jurisdiction (see Delhi Express at [21]). Accordingly, the Tribunal has jurisdiction." — Per Roger Giles IJ, Para 70
Case Information
- Citation: CES v International Air Transport Association [2020] SGHC(I) 08 (Para 0)
- Court: Singapore International Commercial Court (Para 0)
- Case Number: Originating Summons No 7 of 2019 (Para 0)
- Coram: Roger Giles IJ (Para 0)
- Hearing Dates: 9 January 2020; 9 December 2019; 13 April 2020 (Para 0)
- Judgment Date: 25 March 2020 (Para 0)
- Counsel for the Applicant: Pateloo Eruthiyanathan Ashokan and Soon Meiyi Geraldine (Withers KhattarWong LLP) (Para 116)
- Counsel for the Respondent: Toh Wei Yi, Leong Shan Wei Jaclyn, Lem Jit Min Andy and Ng Hua Meng Marcus (Huang Huaming, Marcus) (Eversheds Harry Elias LLP) (Para 116)
- Area of Law: International arbitration; jurisdiction; preconditions to arbitration; foreign law evidence; estoppel and waiver (Paras 3, 43, 44)
- Judgment Length: The extraction does not provide a page count or word count, so this is not answerable from the material provided.
Summary
This application concerned whether an arbitral tribunal constituted under the IATA Passenger Sales Agency framework had jurisdiction to hear IATA’s monetary claim against CES. CES invoked s 10 of the International Arbitration Act and Article 16(3) of the UNCITRAL Model Law to challenge the tribunal’s ruling on jurisdiction, contending that a prior decision of the Travel Agency Commissioner was a mandatory precondition to arbitration and that no such decision had been obtained. The court held that the tribunal did have jurisdiction and that the absence of a TAC decision could not be relied on by CES because CES itself was the party able to initiate the TAC review. (Paras 3, 4, 70)
The dispute arose from CES’s failure to remit ticket-sale monies in March 2013, IATA’s declaration of default and termination of the Passenger Sales Agency Agreement, and the later sequence of proceedings in India and Singapore. The court carefully traced the contractual and regulatory scheme, including the relevant resolutions and handbook provisions, and concluded that the TAC review mechanism was a precursor step that CES alone could trigger. On that basis, the court applied Delhi Express and rejected the attempt to distinguish it. (Paras 25, 29, 31, 34, 36, 47, 68, 70)
The court also rejected CES’s alternative reliance on estoppel and waiver. It held that the Indian pleadings did not amount to a clear representation that arbitration could proceed notwithstanding the absence of a TAC decision, and it treated the expert evidence on Indian law with caution because the experts had gone beyond proper expert function by opining on construction and legal conclusions. The application was dismissed, the tribunal’s jurisdiction was declared, and costs were ordered against CES. (Paras 73, 88, 92, 99, 102, 104, 107, 108)
What Was the Arbitration Framework and Why Did the TAC Review Matter?
The court began by situating the dispute within the IATA Passenger Sales Agency framework. CES had been appointed as an accredited travel agent by IATA under a Passenger Sales Agency Agreement dated 18 January 2005, and the claim concerned money due to airlines from ticket sales in March 2013. The jurisdictional question was not whether there was an arbitration agreement in the abstract, but whether the contractual and regulatory scheme required a prior review by the Travel Agency Commissioner before arbitration could be invoked. (Paras 2, 25)
"CES applied to the Singapore High Court, pursuant to s 10 of the International Arbitration Act (Cap 143A, 2002 Rev Ed) (“IAA”) read with Article 16(3) of the UNCITRAL Model Law on International Commercial Arbitration, to set aside the Tribunal’s ruling (more correctly, for the Court to decide the matter)." — Per Roger Giles IJ, Para 3
The court’s framing made clear that the issue was one of jurisdiction under the arbitration framework, not a merits dispute over the underlying debt. The amount in dispute was substantial, being INR 124,31,69,623, described as in the order of USD 19 million, plus interest. But the court’s task was confined to deciding whether the tribunal could hear the claim at all, and that depended on the proper construction of the TAC review mechanism and the parties’ conduct. (Paras 2, 3, 43, 44)
The court ultimately treated the TAC step as a precondition to arbitration, but a precondition that CES itself could have activated. That distinction was decisive. The court did not say that the TAC step was irrelevant; rather, it said that CES could not rely on the absence of a TAC decision when the absence resulted from CES’s own failure to initiate review. That reasoning drove the jurisdictional outcome. (Paras 47, 68, 70)
How Did the Dispute Arise From CES’s Failure to Remit Ticket-Sale Monies?
The factual chronology mattered because it showed how the dispute escalated from non-payment to termination, then to administrative correspondence, then to litigation and arbitration. On 26 March 2013, IATA wrote to CES stating that INR 46,43,37,605 due for the period 1–15 March 2013 had not been received and demanded payment by close of business on 28 March 2013. On 1 May 2013, IATA terminated the PSA with immediate effect. These facts formed the immediate commercial background to the later jurisdictional contest. (Paras 25, 29)
"On 26 March 2013, IATA wrote to CES stating that INR 46,43,37,605 due from it for the period 1-15 March 2013 had not been received, and demanding payment by close of business on 28 March 2013." — Per Roger Giles IJ, Para 25
"On 1 May 2013, IATA wrote to CES advising that the PSA was terminated with immediate effect." — Per Roger Giles IJ, Para 29
The chronology then moved into the TAC process and beyond. Over a year later, on 23 May 2014, CES wrote to the TAC, but the TAC responded that the time for review had long passed. IATA then commenced proceedings in India on 27 January 2016, claiming INR 124,31,69,623 plus interest against CES and its Chairman and Managing Director, M. Later, on 29 March 2018, IATA submitted a Request for Arbitration to the ICC, the designated institution under the relevant resolution. (Paras 31, 34, 36)
"Over a year later, on 23 May 2014, CES wrote to the TAC." — Per Roger Giles IJ, Para 31
"On 27 January 2016, IATA began proceedings against CES and its Chairman and Managing Director, “M”, claiming INR 124,31,69,623 plus interest." — Per Roger Giles IJ, Para 34
"On 29 March 2018, IATA submitted a Request for Arbitration to the International Chamber of Commerce (“the ICC”), the designated institution for arbitration in sub-para 12.2.1 of Resolution 818g." — Per Roger Giles IJ, Para 36
That sequence mattered because CES’s later jurisdictional objection depended on the proposition that no TAC decision existed. The court’s answer was that the absence of a TAC decision was not a neutral fact; it was a consequence of CES’s own failure to act in time. The court therefore treated the chronology as central to the jurisdictional analysis, not merely background. (Paras 31, 43, 47, 70)
What Were the Two Jurisdictional Questions the Court Had to Decide?
The court expressly identified two issues. The first was the “default question”: whether, notwithstanding the absence of a TAC decision, the tribunal nonetheless had jurisdiction because the absence should be attributed to CES’s failure to initiate TAC review. The second, which arose only if the first was answered against IATA, was whether CES was estopped or had waived the precondition by reason of representations made in the Indian proceedings. This structure governed the rest of the judgment. (Paras 43, 44)
"The first issue is whether, notwithstanding the absence of a TAC decision, the Tribunal nonetheless has jurisdiction because the absence of a TAC decision should be attributed to CES’s failure to initiate a review by the TAC, such that CES cannot rely on its non-fulfilment of the pre-condition to deny the Tribunal’s jurisdiction (“the default question”)." — Per Roger Giles IJ, Para 43
"The second issue, arising only if the default question is answered against IATA, is whether CES is estopped from denying the Tribunal’s jurisdiction, or has waived fulfilment of the precondition, by reason of representations concerning arbitration made in the course of the Indian proceedings (“the estoppel/waiver question”)." — Per Roger Giles IJ, Para 44
The court’s formulation is important because it shows that the estoppel and waiver arguments were secondary. The primary question was contractual and structural: who had the ability and responsibility to trigger TAC review? Only if CES could not be fixed with responsibility for the missing TAC decision would the court need to consider whether its later conduct in India barred it from objecting. (Paras 43, 44, 73)
That sequencing also shaped the reasoning. The court first examined the relevant resolutions and handbook provisions, then compared the case to Delhi Express and All India, and only after resolving the default question did it turn to the Indian proceedings and the expert evidence on s 8(1) of the Indian Arbitration and Conciliation Act. (Paras 47, 48, 68, 70, 75, 88, 90, 91, 92, 99)
Why Did the Court Hold That CES, Not IATA, Had to Initiate TAC Review?
The court’s central reasoning on the default question was that the relevant provisions did not oblige IATA to initiate TAC review. The court accepted that the TAC decision was a precondition to arbitration, but it rejected the proposition that IATA could or had to trigger that process. Instead, it held that the resolution paragraph incorporated into the handbook was a short-form provision that picked up the obligation to request review without expanding it into a broader duty on IATA. (Paras 68, 70)
"Sub-paragraph 1.3.12 in Resolution 820e is a short-form incorporation of the Resolution 818g paragraph, picking up its obligation to request a review without itself having a wider operation." — Per Roger Giles IJ, Para 68
"In my view, it is clear that the Resolution 818g paragraph did not oblige IATA to initiate a review." — Per Roger Giles IJ, Para 68
The court’s analysis turned on the structure of the handbook and the nature of the dispute. It rejected the attempt to read sub-para 1.3.12 as imposing on IATA a duty to seek TAC review in every case. The court held that the provision concerned a different situation, namely one involving prejudiced collection of funds and withdrawal of standard traffic documents, rather than the ordinary non-payment dispute that was before the court. That distinction was critical because it meant the provision could not be used to shift the burden of initiating review away from CES. (Paras 68, 70)
Once that construction was adopted, the court concluded that CES alone was able to initiate review by the TAC. CES therefore could not rely on the absence of a TAC decision to deny the tribunal’s jurisdiction. The court expressly said that Delhi Express was not to be distinguished, and it treated that authority as directly applicable to the facts before it. (Paras 47, 68, 70)
"Merely because the agreement between the parties provides for a precursor to the arbitration, arbitration cannot be avoided on the ground of the pre requisite step having not been taken." — Per Roger Giles IJ, Para 47
"A party cannot be permitted to renegate out of the Arbitration Agreement by contending that owing to its own default or otherwise the precursor event to arbitration has not occurred." — Per Roger Giles IJ, Para 47
That principle was the backbone of the holding. The court did not treat the TAC review as optional; rather, it treated the missing TAC decision as a consequence of CES’s own inaction. The jurisdictional objection therefore failed because a party cannot create the very absence on which it later relies to defeat arbitration. (Paras 47, 68, 70)
How Did Delhi Express and All India Shape the Court’s Decision?
Delhi Express was the principal authority. The court quoted it for the proposition that where an agreement provides for a precursor to arbitration, arbitration cannot be avoided merely because the precursor step was not taken. The court then applied that principle to the TAC mechanism and held that CES could not rely on the absence of a TAC decision when CES itself was the party able to initiate review. (Paras 47, 70)
"It follows that Delhi Express is not to be distinguished. CES alone was able to initiate a review by the TAC, and it cannot rely on the absence of a decision of the TAC to dispute the Tribunal’s jurisdiction (see Delhi Express at [21]). Accordingly, the Tribunal has jurisdiction." — Per Roger Giles IJ, Para 70
The court also referred to All India as a supporting Indian authority. It noted that in All India the agent unsuccessfully argued that the absence of a TAC decision was not its fault because, although it could have initiated review, it was not obliged to do so. The court used that case to reinforce the proposition that the ability to initiate review was enough to defeat a later jurisdictional objection based on the absence of a TAC decision. (Para 48)
"It was followed in this respect in International Air Transport Association v All India Travel Agency (Madurai) Private Ltd (2012) 4 CTC 748 (“All India”), where the agent unsuccessfully argued that the absence of a TAC decision was not its fault because, while it could have initiated a review, it was not obliged to do so (see All India at [5], [17]–[18] and [20])." — Per Roger Giles IJ, Para 48
These authorities mattered because they showed that the court was not inventing a new rule. It was applying an established principle: a party cannot rely on the non-occurrence of a precursor event when that non-occurrence is attributable to its own failure to act. The court’s reasoning was therefore both doctrinal and practical, aligning the TAC mechanism with the broader law of arbitration preconditions. (Paras 47, 48, 70)
Why Did the Court Reject CES’s Estoppel and Waiver Arguments?
The estoppel and waiver issue arose only because the court had already resolved the default question in IATA’s favour. IATA argued that CES’s conduct in the Indian proceedings amounted to a waiver of the TAC precondition or estopped CES from relying on its absence. CES responded that the Indian pleadings had to be understood in light of s 8(1) of the Indian Arbitration and Conciliation Act, which requires referral to arbitration where there is an arbitration agreement. The court ultimately held that the estoppel ground failed. (Paras 73, 75, 88, 99)
"IATA submitted that CES’s failure to initiate a review by the TAC was a waiver of the precondition to arbitration, or alternatively estopped CES from relying on the absence of a decision by the TAC." — Per Roger Giles IJ, Para 73
"CES responded that its application, and more particularly what was said about arbitrability in the documents filed in the Indian proceedings, were to be seen against the background of the law on s 8(1) of the ACA." — Per Roger Giles IJ, Para 88
The court’s treatment of waiver was cautious. It noted that waiver might simply be another way of saying that CES could not rely on its own default, citing M.K. Shah Engineers and Contractors. But because the court had already held that CES could not rely on the absence of the TAC decision, the waiver argument added little. The decisive point remained that the missing TAC decision was attributable to CES. (Para 73)
"Waiver may be a different way of saying that CES cannot rely on its own default, see M.K. Shah Engineers and Contractors v State of Madhya Pradesh (1999) 2 SCC 594 at [17]." — Per Roger Giles IJ, Para 73
As to estoppel, the court held that the Indian pleadings did not clearly represent that arbitration could proceed despite the absence of a TAC decision. The court therefore concluded that the estoppel ground failed. In practical terms, the court was unwilling to infer a clear and unequivocal representation from the materials before it, especially given the statutory context of s 8(1) and the limited role of the Singapore court in assessing foreign-law evidence. (Paras 88, 99)
"The estoppel ground fails." — Per Roger Giles IJ, Para 99
How Did the Court Treat the Indian Proceedings and Section 8(1) of the Indian Act?
The Indian proceedings were central to the estoppel and waiver arguments because they contained the pleadings and submissions on which IATA relied. The court reproduced the text of s 8(1) of the Arbitration and Conciliation Act, 1996, and noted that it requires a judicial authority to refer parties to arbitration if the matter is subject to an arbitration agreement, unless prima facie no valid arbitration agreement exists. That statutory setting explained why CES had taken the position it did in India. (Paras 75, 88, 90, 91)
"(1) A judicial authority, before which an action is brought in a matter which is the subject of an arbitration agreement shall, if a party to the arbitration agreement or any person claiming through or under him, so applies not later than the date of submitting his first statement on the substance of the dispute, then, notwithstanding any judgment, decree or order of the Supreme Court or any Court, refer the parties to arbitration unless it finds that prima facie no valid arbitration agreement exists." — Per Roger Giles IJ, Para 75
The court considered expert evidence from both sides on Indian law, including references to Ameet Lalchand Shah, Hema Khattar, Sundaram Finance, and Hindustan Petroleum. The evidence was used to illuminate the operation of s 8(1), but the court was careful not to let the experts usurp the judicial function. It noted that the experts did not directly address the specific question whether, in an application under s 8(1), referral could be resisted by contending that although there was an arbitration agreement, a precondition to arbitration was not satisfied. (Paras 90, 91, 92)
"The experts did not directly address the specific question of whether, in an application under s 8(1), referral to arbitration could be resisted by contending that although there was an arbitration agreement, a precondition to arbitration was not satisfied." — Per Roger Giles IJ, Para 92
The court’s approach shows a careful distinction between the existence of an arbitration agreement and the satisfaction of a contractual precondition to arbitration. The Indian authorities cited by the experts supported mandatory referral where an arbitration clause exists, but the Singapore court was not persuaded that the Indian pleadings amounted to a representation inconsistent with CES’s later jurisdictional challenge. The estoppel argument therefore failed not because the Indian proceedings were irrelevant, but because they did not establish the necessary clear representation. (Paras 88, 90, 91, 92, 99)
What Did the Court Say About the Expert Evidence on Foreign Law?
The court devoted substantial attention to the expert evidence because the parties had adduced affidavits from Indian legal experts and factual witnesses. On CES’s side, there were three affidavits of M and two affidavits of Rameshwar Singh Malik, a former Judge of the Punjab and Haryana High Court and Senior Advocate of the Supreme Court of India. On IATA’s side, there was an affidavit from D’Cruz and an affidavit from Raj Ramesh Panchmatia, an Advocate on Record in the Supreme Court of India. None of the deponents were cross-examined. (Para 40)
"The evidence comprised, on CES’s side, three affidavits of M and two affidavits of Rameshwarwar Singh Malik (“Rameshwar”), a former Judge of Punjab and Haryana High Court and Senior Advocate of the Supreme Court of India (“SCI”); and on IATA’s side, an affidavit of Rodney Augustine D’Cruz (“D’Cruz”), the Head of IATA’s India, Nepal and Bhutan branch, and an affidavit of Mr Raj Ramesh Panchmatia (“Raj”), an Advocate on Record in the SCI. None of the deponents were cross-examined." — Per Roger Giles IJ, Para 40
The court observed that the experts had gone beyond proper expert evidence by offering construction and conclusions that were for the court. It noted that the experts did not directly address the precise s 8(1) question in issue. The court also reminded practitioners that affidavits should not become vehicles for advocacy, citing Pacific Recreation, MCC Proceeds, Re Application by Dow Jones, and Gleeson v J Wippell. (Paras 92, 102, 104, 106)
"In Pacific Recreation at [76], the court adopted from MCC Proceeds Inc v Bishopsgate Investment Trust plc [1999] CLC 417 at [23] a summary of the function of an expert witness on foreign law:" — Per Roger Giles IJ, Para 102
"The experts were asked to go beyond their proper roles." — Per Roger Giles IJ, Para 104
"A party’s lawyers should ensure that the proper bounds are not transgressed, and should restrain their client’s enthusiasm to take on the advocate’s role (see, generally, Re Application by Dow Jones (Asia) Inc [1987] SLR(R) 627 at [16] and [17] and Gleeson v J Wippell & Co Ltd [1977] 3 All ER 54 at 63)." — Per Roger Giles IJ, Para 106
This part of the judgment is practically important because it warns litigants that foreign-law experts should explain the law, not decide the case. The court’s comments also show that, even where foreign law is relevant, the domestic court remains responsible for the ultimate legal characterization of the issue before it. (Paras 102, 104, 106)
How Did the Court Reach Its Final Orders?
Having rejected both the default argument and the estoppel/waiver argument, the court concluded that the tribunal had jurisdiction. It therefore dismissed the Originating Summons and ordered CES to pay IATA’s costs. The court also gave liberty to apply within 14 days if either party sought a different or additional costs order, and it invited the parties to agree the amount of costs or directions for determining it. (Paras 107, 108)
"CES fails in the application. Ordinarily, it will follow that it pays IATA’s costs. I will so order, but with liberty to apply with 14 days if either party seeks a different or additional order as to costs. I invite the parties to agree on the costs amount, or on directions for determining it." — Per Roger Giles IJ, Para 107
"I make the following orders: (a) Declare that the Tribunal has jurisdiction to hear the claims of IATA in the arbitration; (b) the Originating Summons is dismissed; and (c) CES is to pay IATA’s costs of the application, with liberty to apply within 14 days if either party seeks a different or additional order as to costs any such application may be made by letter to the Registry." — Per Roger Giles IJ, Para 108
The court also noted the confidentiality of arbitral proceedings under s 23 of the IAA, which it mentioned in the course of dealing with the judgment’s publication and the parties’ materials. That reference underscores the arbitration-sensitive context in which the court was operating, even though confidentiality was not itself the central issue. (Para 109)
In the end, the court’s orders reflected a straightforward application of the principle that a party cannot rely on its own failure to trigger a contractual precursor to arbitration. The tribunal’s jurisdiction was upheld, the challenge failed, and costs followed the event. (Paras 70, 107, 108)
Why Does This Case Matter?
This case matters because it clarifies an important point in arbitration practice: where a contractual scheme requires a prior administrative or regulatory review before arbitration, a party cannot defeat jurisdiction by pointing to the absence of that review if the party itself was the one able to initiate it. The court’s application of Delhi Express gives practical content to the principle that a party cannot rely on its own default to avoid arbitration. (Paras 47, 70)
The case also matters for cross-border disputes involving foreign law and parallel proceedings. The court showed that pleadings in foreign litigation do not automatically create estoppel in Singapore, especially where the legal context is a mandatory-referral provision like s 8(1) of the Indian Act. The judgment therefore offers guidance on how Singapore courts may assess foreign proceedings when jurisdictional objections are raised in arbitration-related litigation. (Paras 75, 88, 99)
Finally, the judgment is a useful reminder about expert evidence. The court’s criticism of experts who go beyond their proper role is a practical warning to litigators: foreign-law evidence should assist the court, not replace judicial reasoning. For arbitration practitioners, the case is a strong illustration of how procedural preconditions, foreign proceedings, and expert evidence can intersect in a jurisdictional challenge. (Paras 92, 102, 104, 106)
Cases Referred To
| Case Name | Citation | How Used | Key Proposition |
|---|---|---|---|
| Delhi Express Travels Pvt Ltd v International Air Transport Association & others | [2009] 3 Arb LR 303 | Main authority on the TAC/arbitration precondition and the effect of a party’s own default | Arbitration cannot be avoided merely because the precursor step was not taken; a party cannot rely on its own default (Paras 47, 70) |
| International Air Transport Association v All India Travel Agency (Madurai) Private Ltd | (2012) 4 CTC 748 | Supporting authority following Delhi Express | An agent could not resist the consequence of missing TAC review where it could have initiated review itself (Para 48) |
| Sanum Investments Ltd v Government of the Lao People’s Democratic Republic | [2016] 5 SLR 536 | Used to characterise the application as a hearing de novo | The court was deciding the matter afresh, not reviewing or appealing the tribunal’s decision (Para 39) |
| M.K. Shah Engineers and Contractors v State of Madhya Pradesh | (1999) 2 SCC 594 | Cited on waiver | Waiver may be another way of saying a party cannot rely on its own default (Para 73) |
| Pacific Recreation Pte Ltd v SY Technology Inc and another appeal | [2008] 2 SLR (R) 491 | Used on the function of foreign-law experts | Expert evidence on foreign law has defined limits and should not become advocacy (Para 102) |
| MCC Proceeds Inc v Bishopsgate Investment Trust plc | [1999] CLC 417 | Cited through Pacific Recreation for the role of foreign-law experts | Foreign-law experts explain the law; they do not decide the legal issue for the court (Para 102) |
| Re Application by Dow Jones (Asia) Inc | [1987] SLR(R) 627 | Used to caution against affidavits becoming advocacy | Affidavit evidence must stay within proper bounds and not assume the advocate’s role (Para 106) |
| Gleeson v J Wippell & Co Ltd | [1977] 3 All ER 54 | Used with Dow Jones on the limits of affidavit evidence | Witness evidence should not be used to make submissions in disguise (Para 106) |
| Ameet Lalchand Shah v Rishabh Enterprises | (2018) 15 SCC 678 | Cited by the expert Raj on s 8(1) | Supports referral to arbitration where an arbitration agreement exists and the court finds prima facie that such agreement exists (Para 90) |
| Hema Khattar and another v Shiv Khera | (2017) 7 SCC 716 | Cited by the expert Raj on mandatory referral | Where there is an arbitration clause, referral to arbitration is mandatory (Para 90) |
| M/S Sundaram Finance Limited v T Thankam | (2015) 14 SCC 444 | Cited by Rameshwar in the discussion of s 8(1) | Reinforces the mandatory-referral approach under Indian arbitration law (Para 91) |
| Hindustan Petroleum Corporation v M/S Pinhcity Medway Petroleums | (2003) 6 SCC 503 | Cited for mandatory referral despite dispute over applicability | Referral is mandatory even where the applicability of the arbitration clause is disputed (Para 91) |
Legislation Referenced
- International Arbitration Act (Cap 143A, 2002 Rev Ed), s 10 (Paras 3, 116) [CDN] [SSO]
- International Arbitration Act (Cap 143A, 2002 Rev Ed), s 23 (Para 109) [CDN] [SSO]
- UNCITRAL Model Law on International Commercial Arbitration, Article 16(3) (Para 3)
- Arbitration and Conciliation Act, 1996 (India), s 8(1) (Paras 75, 88, 90, 91)
Source Documents
- Original Judgment — Singapore Courts
- Archived Copy (PDF) — Litt Law CDN
- View in judgment: "Over a year later, on 23..."
- View in judgment: "Section 8(1) of the ACA provides:..."
- View in judgment: "The experts were asked to go..."
This article analyses [2020] SGHCI 8 for legal research and educational purposes. It does not constitute legal advice. Readers should consult the full judgment for the Court's complete reasoning.