Case Details
- Citation: [2024] SGHC 121
- Court: General Division of the High Court of the Republic of Singapore
- Decision Date: 8 May 2024
- Coram: Lee Seiu Kin SJ
- Case Number: Suit No 718 of 2021
- Hearing Date(s): 27–28 July, 1–2, 4, 8, 10–11, 15, 17 August 2023, 22 April 2024
- Claimants / Plaintiffs: Center for Competency-Based Learning and Development Pte Ltd (“CBLD”)
- Respondent / Defendant: SkillsFuture Singapore Agency (“SSG”)
- Counsel for Claimants: [None recorded in extracted metadata]
- Counsel for Respondent: [None recorded in extracted metadata]
- Practice Areas: Contract — Discharge — Stipulated event — Innocent party entitled to terminate in event of breach of warranty or term of contract
Summary
The decision in Center for Competency-Based Learning and Development Pte Ltd v SkillsFuture Singapore Agency [2024] SGHC 121 represents a significant judicial examination of the intersection between statutory administrative discretion and private law contractual obligations. At its core, the dispute concerned the termination of a long-standing funding arrangement between the SkillsFuture Singapore Agency ("SSG"), a statutory body established under the SkillsFuture Singapore Agency Act 2016, and the Center for Competency-Based Learning and Development Pte Ltd ("CBLD"), a private training provider. The High Court was tasked with determining whether SSG’s termination of the contract, based on findings of "gross moral turpitude" and breaches of warranty regarding the integrity of training records, was legally valid under the complex web of terms and conditions governing the SkillsConnect portal.
The judgment provides a masterclass in the application of the Braganza duty—the implied term that a party exercising a contractual discretion must do so honestly, for a proper purpose, and not in a manner that is irrational, capricious, or arbitrary. While SSG argued for a "sole and absolute discretion" that was largely immune from judicial review in a private law context, the Court affirmed that such discretions are never entirely unfettered. However, the Court ultimately found that SSG had met the requisite standard. The decision underscores that where a statutory body is tasked with the stewardship of public funds, its "opinion" regarding a counterparty's conduct will be upheld if it is based on a rational investigative process, even if the underlying evidence (such as hearsay statements from elderly trainees) is contested or imperfect.
Furthermore, the case clarifies the operation of contractual "clawback" mechanisms. SSG sought to recover millions of dollars in previously disbursed funding, relying on clauses that allowed for the recovery of all support provided if the contract was terminated for fault. CBLD attempted to resist this through various equitable and legal doctrines, including promissory estoppel, unconscionability, and the argument that the clawback clause constituted an unenforceable penalty. The Court’s nuanced treatment of these issues—particularly the limited success of CBLD’s estoppel argument for specific claim sums—offers critical guidance for practitioners drafting and litigating government-linked commercial contracts.
Ultimately, the High Court dismissed CBLD’s claim for wrongful termination and allowed SSG’s counterclaim in substantial part. The judgment reinforces the principle that training providers operating within the SkillsFuture ecosystem must maintain the highest standards of record-keeping and integrity. Any failure to ensure that attendance tracking systems are robust and that information provided to the Agency is "true, accurate and complete" can trigger draconian contractual consequences, including the total cessation of funding and the retrospective recovery of disbursed grants.
Timeline of Events
- May 2007: CBLD enters into the initial contractual arrangement with SSG (or its predecessor) to obtain funding through the SkillsConnect portal.
- 30 September 2018: A specific date noted in the factual matrix regarding the ongoing relationship and funding submissions.
- 5 September 2019: Relevant date concerning the administration of training grants and portal interactions.
- 21 September 2019: Further date noted in the chronology of training course administration.
- 19 October 2019: Date associated with specific training grant applications or claims.
- 3 February 2020: SSG begins an audit process involving the call-up of trainees for interviews.
- 4 February 2020: Continuation of the trainee interview and audit phase.
- 7 February 2020: Further trainee interviews conducted by SSG investigators.
- 21 February 2020: Date relevant to the gathering of evidence from trainees.
- 26 February 2020: Completion of an early phase of the trainee audit.
- April – July 2020: SSG calls up 14 trainees for an audit of CBLD’s processes and training attendance.
- 17 June 2020: Date noted in the investigative timeline.
- 21 July 2020: Further investigative actions taken by SSG.
- 7 September 2020: Date relevant to the internal review of audit findings by SSG.
- 12 October 2020: Date associated with the communication of audit concerns.
- 16 October 2020: A critical date for the promissory estoppel argument; SSG makes representations regarding the processing of certain claims.
- 19 October 2020: Date relevant to the reliance of CBLD on SSG's representations.
- 22 October 2020: Internal SSG communications regarding the status of CBLD's funding.
- 23 October 2020: Further internal deliberations at SSG.
- 29 October 2020: Date noted in the procedural history of the audit.
- 12 November 2020: SSG continues to process or review claim submissions.
- 13 November 2020: Date relevant to the finalization of the audit report.
- 15 November 2020: Date associated with the formal internal recommendation for termination.
- 12 December 2020: SSG conducts a second round of trainee call-ups and audits.
- 14 December 2020: Further trainee statements obtained.
- 15 December 2020: Investigative phase nears conclusion.
- 16 December 2020: SSG issues a letter or internal memo regarding the findings of "gross moral turpitude".
- 17 December 2020: Final internal approvals for termination are sought.
- 23 December 2020: Date noted in the lead-up to the formal termination notice.
- 19 January 2021: SSG continues to hold internal discussions on the clawback of funds.
- 10 March 2021: Final review of the termination letter.
- 25 March 2021: SSG formally terminates the contract with CBLD via a termination letter.
- 15 April 2021: CBLD responds to the termination, disputing the grounds.
- 28 June 2021: Formal demand for the return of funds is made by SSG.
- 26 August 2021: CBLD commences Suit No 718 of 2021 against SSG for wrongful termination.
- 30 October 2021: Date relevant to the filing of pleadings and counterclaims.
- 21 February 2023: Pre-trial conference or interlocutory matter date.
- 8 May 2023: The Court grants an application to admit four statutory declarations from trainees pursuant to Evidence Act 1893.
- 27 July – 17 August 2023: Substantive hearing of the trial.
- 21 September 2023: Post-trial submissions phase.
- 12 October 2023: Further submissions or clarifications.
- 9 November 2023: Final arguments or closing submissions.
- 30 November 2023: Date noted in the post-hearing schedule.
- 22 April 2024: Final hearing date for clarifications.
- 8 May 2024: Judgment delivered by Lee Seiu Kin SJ.
What Were the Facts of This Case?
The Plaintiff, Center for Competency-Based Learning and Development Pte Ltd ("CBLD"), is a Singapore-incorporated company specializing in the provision of training courses, particularly those related to the cleaning industry. Since 2007, CBLD had been a participant in the SkillsConnect ecosystem, an online portal managed by the Defendant, SkillsFuture Singapore Agency ("SSG"). SSG is a statutory body established under s 3 of the SkillsFuture Singapore Agency Act 2016, tasked with the critical mission of implementing the SkillsFuture initiative and administering the Skills Development Fund under the Skills Development Levy Act 1979. This fund is used to subsidize the costs of training courses for Singaporeans, with SSG acting as the steward of these public monies.
The contractual relationship was governed by a complex, multi-layered set of documents. These included the SkillsConnect General Terms and Conditions ("General T&C"), the Terms of Use, the Privacy Statement, and various Specific Terms and Conditions, most notably the Funding – Specific Terms and Conditions ("Funding T&C"). A priority-of-terms clause (cl 12.5 of the General T&C) established that in the event of any conflict, the General T&C would prevail over the Specific Terms, which in turn prevailed over Guidelines and other documents. Under this framework, CBLD would submit training grant applications for approval. Once approved, CBLD would conduct the courses and subsequently submit claims for the disbursement of monetary support through the SkillsConnect portal. These claims typically covered course fee subsidies and absentee payroll funding.
The seeds of the dispute were sown in early 2020 when SSG initiated an audit of CBLD’s training activities. Between April and July 2020, and again in December 2020, SSG investigators contacted 14 trainees who had purportedly attended CBLD’s cleaning-related courses. The trainees were largely elderly cleaners, many of whom were sent for training by their employers. The purpose of the audit was to verify whether the training had actually taken place as reported and whether the attendance records submitted by CBLD were accurate. The investigators obtained "Trainee Statements" from these individuals, which suggested significant discrepancies. Some trainees claimed they had never attended the courses, others stated they had only attended for a fraction of the required time, and several alleged that they were asked to sign attendance sheets for multiple days on a single occasion.
Based on these statements, SSG formed the opinion that CBLD had engaged in deceptive practices. Specifically, SSG concluded that CBLD had submitted claims for trainees who did not attend the full duration of the courses and had maintained a flawed attendance tracking system that allowed for the retrospective or bulk signing of attendance sheets. This led SSG to invoke cl 12.1(d) of the General T&C, which allowed for immediate termination if SSG formed the "opinion" that the training provider was guilty of "gross moral turpitude". SSG also relied on cl 12.1(a), alleging breaches of warranty—specifically that CBLD had failed to ensure that all information provided was "true, accurate and complete" and that its attendance tracking system was robust.
On 25 March 2021, SSG issued a formal termination letter. The consequences were severe: SSG not only ceased all future funding but also invoked cl 13.1 of the General T&C (the "Clawback Clause"), demanding the return of all funding previously disbursed to CBLD. SSG’s counterclaim in the subsequent litigation sought the recovery of a staggering $7,759,215.25, representing the total funding provided to CBLD over the years. CBLD, in turn, sued for wrongful termination, arguing that the trainee statements were unreliable hearsay, that the "gross moral turpitude" standard was not met, and that SSG was estopped from clawing back funds for certain claims it had previously encouraged CBLD to submit.
The evidentiary landscape at trial was unusual. Neither party called any of the 14 trainees to testify in person. CBLD argued that the trainees were elderly, potentially suffering from memory lapses, and that the SSG investigators had used leading questions to elicit incriminating statements. SSG, however, relied on the documentary evidence of the statements and statutory declarations, which the Court admitted under the Evidence Act 1893. The Court was thus required to determine whether SSG’s opinion was validly formed based on the material it had at the time, rather than conducting a de novo trial of whether "gross moral turpitude" had objectively occurred.
What Were the Key Legal Issues?
The resolution of this dispute required the High Court to navigate several complex legal issues, primarily centered on contract law and the law of evidence. The first and most critical issue was the validity of the termination. This involved a two-pronged inquiry:
- Whether SSG could justify termination under cl 12.1(a) of the General T&C for breach of warranty. This required the Court to determine if CBLD had breached its obligation to provide "true, accurate and complete" information and to maintain a proper attendance tracking system.
- Whether SSG could justify termination under cl 12.1(d), which turned on SSG’s "opinion" that CBLD was guilty of "gross moral turpitude". This raised the fundamental question of the scope of SSG's discretion and whether it was subject to the Braganza duty of rationality and good faith.
The second major issue concerned the implied limits on contractual discretion. CBLD argued that even if the contract granted SSG "sole and absolute discretion," such power must be exercised in accordance with an implied term that it would not be exercised dishonestly, for an improper purpose, irrationally, capriciously, or arbitrarily. The Court had to decide whether this Braganza/Socimer doctrine applied to a statutory body acting in a commercial capacity and whether SSG’s investigative process met this standard.
The third issue was the enforceability of the Clawback Clause (cl 13.1). CBLD challenged this clause on several grounds:
- Whether the clause was unconscionable or constituted an unenforceable penalty.
- Whether there was an implied term that SSG’s discretion to claw back funds must also be exercised rationally and not arbitrarily.
- Whether SSG was estopped from relying on the clawback clause for certain claims, specifically those submitted after 16 October 2020, following representations made by SSG staff.
The fourth issue involved evidential burdens and the standard of proof. Given that the trainees did not testify, the Court had to determine the weight to be given to the Trainee Statements and Statutory Declarations admitted under s 32 and s 32C of the Evidence Act 1893. Furthermore, the Court had to address the standard of proof required for an allegation of "gross moral turpitude," which CBLD argued was higher than the balance of probabilities due to the gravity of the charge.
Finally, the Court had to determine the quantum of the counterclaim. This involved a detailed accounting of the "Defective Claim Entries" (where specific trainees were found not to have attended) versus the "Ad hoc Claim submissions" and the "Post-16/10/2020 Claim Sum." The Court also had to consider CBLD’s alternative claim for quantum meruit for the training services it had actually provided.
How Did the Court Analyse the Issues?
The Court’s analysis began with the contractual framework. Lee Seiu Kin SJ emphasized that the relationship was governed by the written terms of the SkillsConnect portal. He noted that cl 12.1(a) allowed for termination if the training provider breached any warranty. One such warranty was that all information provided to SSG was "true, accurate and complete to the best of its knowledge." Another was the requirement to maintain an attendance tracking system that ensured signatures were collected only on the actual date of the session. The Court found that the evidence from the trainees, even in hearsay form, strongly suggested that CBLD had failed these requirements. For instance, trainees reported signing for multiple days at once, and some reported not attending at all despite claims being filed in their names. The Court held that these were clear breaches of warranty, justifying termination under cl 12.1(a).
The analysis then moved to cl 12.1(d) and the "opinion" of gross moral turpitude. The Court addressed the standard of proof for such an allegation. While CBLD argued for a higher standard, the Court followed the principle in Foo Song Mee v Ho Kiau Seng [2011] SGCA 45 and Tang Yoke Kheng v Lek Benedict [2005] 3 SLR(R) 263, holding that the standard remains the balance of probabilities, though the degree of proof required may vary depending on the gravity of the allegation. The Court noted:
"In so far as the statutory definitions in s 3 of the Evidence Act are concerned... where the party asserting a particular fact... some things are inherently more likely than others. It would need more cogent evidence to satisfy the court that the thing happened." (at [18], [60])
However, the Court clarified that under cl 12.1(d), the issue was not whether CBLD was guilty of gross moral turpitude, but whether SSG had formed the opinion that it was. This brought the Braganza duty into sharp focus.
The Court applied the Braganza/Socimer test, as adopted in Singapore cases like Leiman, Ricardo v Noble Resources Ltd [2018] SGHC 166 and Dong Wei v Shell Eastern Trading (Pte) Ltd [2022] 1 SLR 1318. The Court held that SSG’s discretion was subject to an implied term that it must not be exercised "dishonestly, for an improper purpose, irrationally, capriciously, or arbitrarily" (at [182]). The Court scrutinized SSG's investigative process. It found that SSG had interviewed 14 trainees, obtained detailed statements, and even secured statutory declarations from four of them. Despite CBLD's criticisms of the investigators' methods, the Court found that SSG had a rational basis for its opinion. The discrepancies identified—such as trainees being at work while purportedly in class—were objective facts that a reasonable administrator could rely upon to form an opinion of "gross moral turpitude."
On the Clawback Clause (cl 13.1), the Court rejected CBLD’s argument that it was unconscionable. The Court noted that CBLD was a sophisticated commercial entity that had operated under these terms for over a decade. The clause was a clear allocation of risk: if a provider was found to be at fault, they risked losing all funding. The Court also distinguished the clawback from a penalty, viewing it as a restitutionary mechanism for the recovery of public funds rather than a sum stipulated in terrorem. Regarding the implied term of rationality for the clawback, the Court held that while the Braganza duty might apply to the decision to claw back, it did not allow the Court to rewrite the contract to limit the amount recoverable if the conditions for clawback were met.
The promissory estoppel argument was the only area where CBLD achieved partial success. CBLD pointed to a critical interaction on 16 October 2020. At that time, SSG was already investigating CBLD but had not yet terminated the contract. SSG staff encouraged CBLD to continue submitting claims to "clear the backlog." CBLD argued that this constituted a representation that the claims would be paid and that SSG would not later invoke the clawback clause for these specific sums. The Court applied the test from Aero-Gate Pte Ltd v Engen Marine Engineering Pte Ltd [2013] SGHC 148 and Tractors Singapore Ltd v Pacific Ocean Engineering & Trading Pte Ltd [2021] 4 SLR 44. It found that for the "Post-16/10/2020 Claim Sum" (amounting to $778,839.49), there was a clear representation and detrimental reliance. It would be inequitable for SSG to encourage the submission of these claims only to claw them back immediately upon termination. Thus, SSG was estopped from recovering this specific portion of the funding.
Finally, the Court addressed quantum meruit. CBLD argued that even if the contract was terminated, it should be paid for the value of the training actually provided. The Court rejected this, citing Foo Song Mee and Eng Chiet Shoong v Cheong Soh Chin [2016] 4 SLR 728. It held that where a valid contract covers the subject matter, there is no room for a restitutionary claim in quantum meruit. The contract expressly provided for the consequences of termination and the recovery of funds; those terms must prevail.
What Was the Outcome?
The High Court’s decision resulted in a comprehensive victory for SSG on the issue of liability, though the quantum of its recovery was slightly tempered by the estoppel finding. The Court’s primary orders were as follows:
1. Dismissal of CBLD’s Claim: The Court held that SSG had validly terminated the contract on 25 March 2021. The termination was justified under both cl 12.1(a) (breach of warranty) and cl 12.1(d) (opinion of gross moral turpitude). Consequently, CBLD’s claim for damages for wrongful termination was dismissed in its entirety.
2. Allowance of SSG’s Counterclaim: The Court upheld SSG’s right to invoke the clawback provisions under cl 13.1 of the General T&C. SSG was entitled to recover the funding disbursed to CBLD, subject to specific deductions. The Court’s analysis of the quantum involved several distinct figures:
- Defective Claim Entries: SSG was entitled to recover sums related to the specific trainees where attendance was proven to be false.
- The Total Funding Counterclaim: While SSG initially sought $7,759,215.25, the Court’s final award was adjusted to account for the estoppel finding.
- The Estoppel Deduction: The Court found that SSG was estopped from clawing back the "Post-16/10/2020 Claim Sum" of $778,839.49. This amount was to be deducted from SSG's total recovery.
3. Specific Monetary Findings: The judgment referenced several specific amounts that formed part of the accounting exercise:
- $793,083.79 (related to certain claim categories).
- $1,439,157.72 (representing a tranche of the funding).
- $591,121.90 (another specific funding component).
- $22,082.30 and $13,575.40 (smaller administrative or specific course amounts).
The Court directed the parties to perform the final calculation based on these findings.
4. Operative Paragraph on Costs and Stood-down Claims:
"I will hear parties in relation to the stood-down claims and on costs" (at [276]).
The Court did not make a final order on costs in the main judgment, reserving that for further submissions. However, given SSG's substantial success, it was anticipated that costs would follow the event in SSG's favor.
5. Rejection of Alternative Remedies: The Court expressly rejected CBLD’s alternative claim for quantum meruit and its attempt to have the clawback clause declared an unenforceable penalty. The Court maintained the primacy of the contractual agreement, ensuring that the financial consequences of the breach were governed by the terms the parties had agreed upon at the outset of their 14-year relationship.
Why Does This Case Matter?
CBLD v SSG is a landmark decision for several reasons, particularly for practitioners operating at the intersection of administrative law and commercial litigation. First, it provides the most detailed application to date of the Braganza duty in the context of a Singapore statutory body’s contractual discretion. The Court’s refusal to accept that "sole and absolute discretion" means "unfettered discretion" is a critical reminder that even the most powerful contractual language is subject to the overarching requirements of rationality and good faith. For statutory bodies, this means that their internal investigative processes must be robust enough to withstand judicial scrutiny for "arbitrariness" or "capriciousness."
Second, the case reinforces the integrity of the SkillsFuture ecosystem. By upholding the termination based on "gross moral turpitude" and breaches of warranty regarding attendance records, the Court has sent a clear signal to training providers. The stewardship of public funds requires absolute transparency and accuracy. The Court’s willingness to accept hearsay evidence from trainees (via s 32 of the Evidence Act 1893) to support an administrator’s "opinion" shows that the threshold for a statutory body to act is not as high as a criminal standard of proof, provided the process is rational.
Third, the decision provides clarity on contractual clawback clauses. These clauses are common in government grants and subsidies but are often challenged as penalties. The Court’s characterization of the clawback as a valid risk-allocation and restitutionary tool, rather than a penalty, provides a strong precedent for the enforceability of such terms. Practitioners drafting these clauses should ensure they are linked to fault-based termination to maximize their chances of being upheld as non-penal.
Fourth, the promissory estoppel finding serves as a cautionary tale for government agencies. Even in the midst of an investigation, the conduct and representations of operational staff can bind the agency and limit its ability to exercise contractual rights like clawbacks. The fact that SSG lost the right to recover nearly $780,000 because its staff encouraged the provider to "clear the backlog" highlights the need for strict internal communication protocols during audits and investigations.
Finally, the case touches upon the standard of proof for civil fraud and turpitude. By affirming that the standard remains the balance of probabilities—albeit with a requirement for more cogent evidence for more serious allegations—the Court has maintained consistency with the Tang Yoke Kheng line of authority. This provides a predictable framework for litigants facing allegations of "moral turpitude" or "dishonesty" in a commercial context.
Practice Pointers
- Drafting Discretionary Clauses: Practitioners should be aware that phrases like "sole and absolute discretion" will not exclude the Braganza duty of rationality. To minimize the risk of challenge, consider specifying the criteria or the process the decision-maker will follow.
- Integrity of Records: For training providers and grant recipients, this case emphasizes that an "attendance tracking system" is not merely an administrative tool but a core contractual warranty. Any systemic failure to ensure real-time, accurate signatures can justify immediate termination and total clawback of funds.
- Managing Audits and Investigations: Statutory bodies must ensure that their investigators follow a rational process. While they do not need to meet the standards of a criminal trial, they should obtain clear, documented evidence (like the statutory declarations used here) to support the formation of an "opinion" under fault-based termination clauses.
- Estoppel Risks: During an audit, agencies should be extremely careful about making representations that encourage a provider to continue incurring costs or submitting claims. A "reservation of rights" letter should be issued early and frequently to prevent an estoppel from arising.
- Hearsay Evidence: This case illustrates the strategic use of s 32 and s 32C of the Evidence Act 1893. If key witnesses (like elderly trainees) are unavailable or unreliable as live witnesses, practitioners should focus on the admissibility and weight of their contemporaneous statements and statutory declarations.
- Clawback vs. Penalty: To ensure a clawback clause is not struck down as a penalty, it should be framed as a recovery of support provided rather than a fixed sum of damages. The Court is more likely to view the return of disbursed subsidies as restitutionary.
- Priority of Terms: In complex contracts with multiple annexes and guidelines, always identify the "priority of terms" clause. As seen in this case (cl 12.5), the General T&C will usually override more specific guidelines, which can be decisive in termination disputes.
Subsequent Treatment
As a relatively recent decision from May 2024, CBLD v SSG has not yet been extensively cited in subsequent reported judgments. However, its detailed analysis of the Braganza duty in a statutory-commercial context is expected to be a primary reference point for future disputes involving government agencies and private contractors. The case follows the established ratio in Leiman and Dong Wei regarding the limits of contractual discretion and reinforces the high evidentiary threshold required to overturn a decision-maker's "opinion" if a rational investigative process was followed.
Legislation Referenced
- SkillsFuture Singapore Agency Act 2016 (No. 24 of 2016), s 3
- Skills Development Levy Act 1979 (2020 Rev Ed)
- Evidence Act 1893 (2020 Rev Ed), s 3, s 32(1)(b)(iv), s 32(5), s 32C(1)(a), s 32C(2), s 103
- Oaths and Declarations Act (Cap 211, 2001 Rev Ed)
Cases Cited
- Applied / Followed:
- Foo Song Mee v Ho Kiau Seng [2011] SGCA 45
- Leiman, Ricardo and another v Noble Resources Ltd and another [2018] SGHC 166
- Dong Wei v Shell Eastern Trading (Pte) Ltd and another [2022] 1 SLR 1318
- Tang Yoke Kheng (trading as Niklex Supply Co) v Lek Benedict and others [2005] 3 SLR(R) 263
- Aero-Gate Pte Ltd v Engen Marine Engineering Pte Ltd [2013] SGHC 148
- Referred to / Considered:
- Max Master Holdings Ltd and others v Taufik Surya Dharma and others [2016] SGHC 147
- Bumi Geo Engineering Pte Ltd v Civil Tech Pte Ltd [2015] 5 SLR 1322
- Loo Chay Sit v Estate of Loo Chay Loo, deceased [2010] 1 SLR 286
- Alliance Concrete Singapore Pte Ltd v Comfort Resources Pte Ltd [2009] 4 SLR(R) 602
- The “Chem Orchid” [2015] 2 SLR 1020
- AL Shams Global Ltd v BNP Paribas [2019] 3 SLR 1189
- LTT Global Consultants v BMC Academy Pte Ltd [2011] 3 SLR 903
- Lim Lay Bee and another v Allgreen Properties Ltd [1998] 3 SLR(R) 1028
- Naughty G Pte Ltd v Fortune Marketing Pte Ltd [2018] 5 SLR 1208
- Sembcorp Marine Ltd v PPL Holdings Pte Ltd and another [2013] 4 SLR 193
- Fook Gee Finance v Liu Cho Chit [1998] 1 SLR(R) 385
- BOM v BOK and another appeal [2019] 1 SLR 349
- Braganza v BP Shipping Ltd and another [2015] 1 WLR 1661
- Socimer International Bank Ltd (in liquidation) v Standard Bank London Ltd [2008] EWCA Civ 116