Submit Article
Legal Analysis. Regulatory Intelligence. Jurisprudence.
Singapore

Bintai Kindenko Pte Ltd v Samsung CT Corp [2017] SGHC 321

In Bintai Kindenko Pte Ltd v Samsung CT Corp, the High Court of the Republic of Singapore addressed issues of Building and Construction Law — Dispute resolution.

Case Details

  • Citation: [2017] SGHC 321
  • Title: Bintai Kindenko Pte Ltd v Samsung C&T Corp
  • Court: High Court of the Republic of Singapore
  • Date of Decision: 19 December 2017
  • Judge: Foo Chee Hock JC
  • Coram: Foo Chee Hock JC
  • Case Number: Originating Summons No 975 of 2017 (Summons No 4276 of 2017)
  • Procedural Posture: Samsung applied to set aside an adjudication determination; Bintai commenced OS 975/2017 to enforce the adjudication determination
  • Plaintiff/Applicant: Bintai Kindenko Pte Ltd
  • Defendant/Respondent: Samsung C&T Corp
  • Counsel (OS 975/2017): Chong Kuan Keong and Ernest Sia (Chong Chia & Lim LLC) for the applicant in OS 975/2017; Kelvin Aw, Leonard Chew and Eugene Lee (Morgan Lewis Stamford LLC) for the respondent in OS 975/2017
  • Legal Area: Building and Construction Law — Dispute resolution; adjudication; setting aside adjudication determination
  • Statute(s) Referenced: Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed)
  • Related Appeal: Appeal to this decision in Civil Appeal No 211 of 2017 dismissed by the Court of Appeal on 9 April 2018 (see [2018] SGCA 39)
  • Judgment Length: 7 pages, 2,994 words
  • Adjudication Determination: Dated 15 August 2017
  • Adjudicator: Not named in the extract
  • Works and Project Context: Alteration and addition works at Suntec City Convention Centre and retail podium
  • Contracting Roles: Samsung as main contractor; Bintai as subcontractor for mechanical, electrical and plumbing works

Summary

This case concerns an application to set aside an adjudication determination made under Singapore’s Building and Construction Industry Security of Payment Act (“SOPA”). Bintai, a subcontractor, sought to enforce an adjudication determination requiring Samsung to release the first half of retention monies. Samsung applied to set aside the determination on the ground that the adjudicator failed to consider two substantive issues—backcharges for scaffolding and variation works—raised in the parties’ submissions. The High Court (Foo Chee Hock JC) held that the adjudicator had deliberately decided not to deal with those issues, and that this amounted to a breach of natural justice.

The court emphasised that while SOPA adjudication is designed to be fast and limited in scope, the adjudicator must still address the issues raised by the parties in good faith. Where the determination’s reasoning shows that a critical issue was not considered, the court will intervene. The adjudication determination was therefore set aside, and the enforcement application failed.

What Were the Facts of This Case?

Samsung C&T Corp was the main contractor for alteration and addition works at the Suntec City Convention Centre and retail podium. Bintai Kindenko Pte Ltd was engaged as a subcontractor to supply and install mechanical, electrical and plumbing works. The dispute arose in the context of payment claims and the subsequent SOPA adjudication process.

On 19 May 2017, Bintai submitted Payment Claim No 59, claiming $13,479,366.43 against Samsung. Samsung responded with Payment Response No 59, asserting a negative response amount of $2,190,963.62, which Samsung claimed was due from Bintai. The negative response figure was not arbitrary; it was derived by taking into account two particular categories of dispute that featured in the parties’ submissions: (i) backcharges for scaffolding and (ii) variation works that had been certified and paid earlier but were later reversed in the payment response.

On 7 July 2017, Bintai served a notice of intention to apply for adjudication and lodged its adjudication application the same day. Notably, although Bintai’s payment claim sought a very large sum, its adjudication application did not pursue the entire claimed amount. Instead, Bintai’s adjudication case was limited to the release of the first half of the retention monies under the subcontract, quantified at $2,146,250. This meant that the adjudication determination was expected to focus on whether Samsung should release that retention, but the parties’ competing calculations still depended on the backcharges and variation issues.

In the adjudication proceedings, both parties dealt with the two issues of backcharges and variation works in their written submissions. The court observed that the negative response amount submitted by Samsung was reached only by considering these two issues. Bintai’s own submissions also reflected this structure: Bintai presented tabular summaries showing the retention component, the backcharges component, and the variation works component. At the oral conference, the adjudicator heard submissions on the issues highlighted in the written submissions. The court later found that the adjudicator’s determination, however, did not substantively address those issues.

The central legal issue was whether the adjudicator’s failure to consider the backcharges and variation works amounted to a breach of natural justice, such that the adjudication determination should be set aside under SOPA. Samsung’s sole ground was that the adjudicator had not considered those issues, and that this failure deprived Samsung of a fair consideration of its case.

Related to this was the question of how the court should characterise the adjudicator’s omission. Bintai argued that any error was merely an error of merits and should not justify setting aside the determination. The court therefore had to decide whether the omission was a reviewable jurisdictional defect (natural justice) rather than a non-interferable error within the adjudicator’s merits assessment.

A further issue was whether the adjudicator had, despite not expressly dealing with the issues, implicitly considered them. Bintai attempted to argue that the adjudicator’s reasoning on retention entitlement necessarily involved an implicit rejection or dismissal of the backcharges and variation works. The court had to assess whether such an inference was legally and logically warranted on the face of the determination.

How Did the Court Analyse the Issues?

Foo Chee Hock JC began by examining the parties’ submissions and the adjudication determination itself. The court accepted that the two issues—backcharges for scaffolding and variation works—were indeed raised and were central to the parties’ competing calculations. The adjudicator’s determination, however, expressly stated that the dispute “centered solely on the release of the first retention monies, and not the variations or backcharges.” The court treated these statements as highly significant because they revealed the adjudicator’s intended scope of inquiry.

The court then rejected Bintai’s attempt to rely on certain paragraphs in the adjudication determination to show that the adjudicator had considered the backcharges and variation works. Bintai pointed to preliminary remarks in the determination that referenced the payment response and the existence of backcharges and retention deductions. The High Court held that those references were inconsequential to the substantive argument Bintai was making. More importantly, the court found that paragraph 50 (and similar language at paragraph 28) made the adjudicator’s mind directed to the retention-only framing of the dispute. On an objective reading, it was inconceivable that the adjudicator had considered and rejected the two issues while simultaneously stating that the dispute did not concern them.

The court also addressed Bintai’s reliance on the principle from Metropole Pte Ltd v Designshop Pte Ltd that an adjudicator need not expressly set out all findings, provided that any omitted finding is “implicit beyond doubt.” The High Court accepted the general proposition that not every issue requires express findings, but stressed that the Metropole approach is context-sensitive. Here, the court found that the adjudicator’s reasoning did not support an inference that the backcharges and variation issues were implicitly resolved. The entitlement to retention monies was not a logically prior issue that would necessarily dispose of the other two issues; rather, the amounts for the three components had to be taken into account in the final outcome. Therefore, the court held there was no basis to infer that the adjudicator had made the implied findings Bintai argued for.

In addition, Bintai suggested that the adjudicator was entitled to defer consideration of backcharges and variations to a later stage—such as the second half of retention monies or a future claim. The High Court found this unpersuasive for two reasons. First, neither party had raised the “second half of retention monies” deferral point in the adjudication proceedings, and the adjudicator had not asked the parties to address it. Second, the court noted that the determination’s explicit reference to the second half of retention monies related to a different context (compensation for loss stemming from unapproved penetrations in brick walls), not to the backcharges and variation issues in dispute. Accordingly, the court concluded that the adjudicator had not considered those issues at all, and had deliberately chosen not to deal with them.

Having found that the adjudicator did not consider the two issues, the court turned to whether this amounted to a breach of natural justice. Bintai argued that the adjudicator’s decision concerned the merits and that the court should not conduct a merits review. The High Court agreed with the general principle that SOPA adjudication is not intended to be a forum for full merits review, citing authorities such as SEF Construction Pte Ltd v Skoy Connected Pte Ltd and Lee Wee Lick Terence v Chua Say Eng. However, the court distinguished between an error of merits and a failure of good faith consideration of issues raised by the parties.

In this regard, the court relied on the reasoning in Brookhollow Pty Ltd v R&R Consultants Pty Ltd & Anor, as adopted in SEF Construction. Brookhollow recognises that an adjudicator’s failure to mention a critical issue may indicate oversight, but not every oversight invalidates the determination. The key is whether the oversight results from a failure overall to address in good faith the issues raised by the parties. The High Court held that this was “one such case” where the omitted issues were of such major consequence and so prominent in the parties’ submissions that no adjudicator acting in good faith could have regarded them as requiring no specific examination in the reasons.

In short, the court’s analysis combined (i) the prominence of the issues in the parties’ submissions and calculations, (ii) the adjudicator’s express statements narrowing the dispute away from those issues, and (iii) the absence of any logically implicit resolution. Together, these factors led to the conclusion that the adjudicator’s approach breached natural justice.

What Was the Outcome?

The High Court set aside the adjudication determination dated 15 August 2017. As a result, Bintai’s originating summons to enforce the adjudication determination failed because the determination was no longer valid.

The decision also underscores that, although SOPA adjudication is intended to be swift and limited, the adjudicator must still address the substantive issues raised by the parties. The Court of Appeal later dismissed the appeal on 9 April 2018 (Civil Appeal No 211 of 2017), confirming the High Court’s approach.

Why Does This Case Matter?

This decision is important for practitioners because it clarifies the boundary between non-reviewable merits errors and reviewable jurisdictional defects grounded in natural justice. While courts generally do not re-litigate the merits of an adjudicator’s decision, they will intervene where the adjudicator fails to consider critical issues raised by the parties in good faith. The case therefore provides a practical framework for assessing whether an adjudicator’s omission is merely an error or a fair hearing problem.

From a drafting and advocacy perspective, the case highlights the significance of how parties frame their “issues in dispute” and how those issues are reflected in the adjudicator’s reasoning. Where the determination expressly states that certain issues are not part of the dispute, and those issues are in fact central to the parties’ calculations, the risk of a successful setting-aside application increases substantially.

For subcontractors and main contractors alike, the case also demonstrates that retention disputes under SOPA cannot be treated as purely mechanical. Even if the adjudication application is framed as limited to retention release, the adjudicator may still need to grapple with the components that affect the retention entitlement, particularly where the payment response and the parties’ submissions show that those components drive the net position.

Legislation Referenced

  • Building and Construction Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) (“SOPA”)

Cases Cited

  • [2010] SGHC 80
  • [2015] SGHC 293
  • [2017] SGHC 321
  • [2018] SGCA 39
  • SEF Construction Pte Ltd v Skoy Connected Pte Ltd [2010] 1 SLR 733
  • Lee Wee Lick Terence (alias Li Weili Terence) v Chua Say Eng (formerly trading as Weng Fatt Construction Engineering) and another appeal [2013] 1 SLR 401
  • Metropole Pte Ltd v Designshop Pte Ltd [2017] 4 SLR 277
  • TMM Division Maritima SA de CV v Pacific Richfield Marine Pte Ltd [2013] 4 SLR 972
  • Brookhollow Pty Ltd v R&R Consultants Pty Ltd & Anor [2006] NSWSC 1

Source Documents

This article analyses [2017] SGHC 321 for legal research and educational purposes. It does not constitute legal advice. Readers should consult the full judgment for the Court's complete reasoning.

Written by Sushant Shukla

More in

Legal Wires

Legal Wires

Stay ahead of the legal curve. Get expert analysis and regulatory updates natively delivered to your inbox.

Success! Please check your inbox and click the link to confirm your subscription.